RA
Rapu-Rapu: Government
Municipality in Albay, Bicol, Luzon · 34 barangays
National projects
244projects
₱13.30Bin all
133ongoing
19slow
- Roads and bridges ₱9.41B
- Flood control ₱3.48B
- Buildings ₱313.6M
- Schools ₱92.7M
- Water ₱12.9M
Showing 91 to 120 of 244
Construction of road with slip, Slope collapse and landslide protection at masaga - sagrada section
Roads and bridges · 2022 · HI-TONE CONSTRUCTION & DEVELOPMENT CORP.
₱96.5MCompleted · 100%
Construction of road with slip, Slope collapse and landslide protection at calanaga - san ramon section
Roads and bridges · 2022 · SUNWEST, INC.
₱96.5MCompleted · 100%
Construction of road with slip, Slope collapse and landslide protection at batan - bagaobawan section
Roads and bridges · 2022 · HI-TONE CONSTRUCTION & DEVELOPMENT CORP.
₱96.5MCompleted · 100%
Construction of morocborocan road, Rapu-rapu road
Roads and bridges · 2022 · SUNWEST, INC.
₱96.5MOn-Going · 76%
Construction of morocborocan - poblacion road
Roads and bridges · 2022 · SUNWEST, INC.
₱96.5MOn-Going · 58%Slow
Construction of mancao-galicia access route road, Sta. 6 + 075 - sta. 7 + 275
Roads and bridges · 2022 · SUNWEST, INC.
₱67.5MOn-Going · 52%Slow
Construction of ridge road, Villahermosa-hamorawon
Roads and bridges · 2022 · SUNWEST, INC.
₱96.5MOn-Going · 95%
Construction of buenavista - mananao road
Roads and bridges · 2022 · SUNWEST, INC.
₱93.4MOn-Going · 79%
Rehabilitation of lagundi-bogtong road, Sta. 0+000 - sta. 0+550
Roads and bridges · 2022 · MACROPRIME BUILDERS CORPORATION
₱28.8MOn-Going · 31%Slow
Construction of poblacion shore protection
Flood control · 2022 · SUNWEST, INC.
₱96.5MCompleted · 100%
Construction of road, Malobago to sta. barbara
Roads and bridges · 2022 · SUNWEST, INC.
₱93.3MOn-Going · 99%
Construction of buenavista-guadalupe interior road
Roads and bridges · 2022 · 3RB CONSTRUCTION & SUPPLY / FSQUARE CONSTRUCTION
₱51.5MOn-Going · 93%
Construction of guadalupe-carogcog interior road
Roads and bridges · 2022 · 3RB CONSTRUCTION & SUPPLY / FSQUARE CONSTRUCTION
₱53.1MOn-Going · 97%
Construction of mananao - buenavista road
Roads and bridges · 2022 · SUNWEST, INC.
₱96.5MOn-Going · 77%
Construction of mananao - morocborocan road
Roads and bridges · 2022 · SUNWEST, INC.
₱96.5MOn-Going · 76%
Construction of road, Bogtong to dapdap phase 2
Roads and bridges · 2022 · SUNWEST, INC.
₱95.5MCompleted · 100%
Construction of ridge road, Caracaran - lagundi
Roads and bridges · 2022 · SUNWEST, INC.
₱92.6MOn-Going · 76%
Construction (completion) of multi-purpose building (phase 2), Barangay linao
Buildings · 2022 · 9LEAVES BUILDERS & SUPPLY CORP.
₱2.9MCompleted · 100%
Construction of ridge road, Lagundi - bogtong
Roads and bridges · 2022 · SUNWEST, INC.
₱95.5MCompleted · 100%
Construction of ridge road, Sagrada - dapdap
Roads and bridges · 2022 · SUNWEST, INC.
₱95.5MCompleted · 100%
Construction of road, Bilbao to calanaga
Roads and bridges · 2022 · SUNWEST, INC.
₱95.5MCompleted · 100%
Construction of san ramon - minso road
Roads and bridges · 2022 · SUNWEST, INC.
₱96.5MCompleted · 100%
Construction of buenavista-mananao road
Roads and bridges · 2022 · SUNWEST, INC.
₱49.0MCompleted · 100%
Construction of evacuation center, Brgy. poblacion
Buildings · 2022 · 3DIAMONDS CONSTRUCTION CORPORATION
₱6.8MCompleted · 100%
Construction of pagcolbon-malobago interior road
Roads and bridges · 2022 · KRATOS DEVELOPMENT CORP. / PROTECH CONSTRUCTION & DEVELOPMENT CORP.
₱53.1MOn-Going · 64%
Construction of linao-santa barbara interior road
Roads and bridges · 2022 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION
₱47.4MOn-Going · 70%
Rehabilitation of bilbao shore protection structure (phase 2)
Flood control · 2022 · HI-TONE CONSTRUCTION & DEVELOPMENT CORP.
₱69.3MCompleted · 100%
Construction of caracaran - lagundi road (phase 2), Barangay caracaran and lagundi
Roads and bridges · 2022 · SUNWEST, INC.
₱67.1MOn-Going · 65%
Construction of road in barangays lagundi and caracaran (phase 4)
Roads and bridges · 2022 · SUNWEST, INC.
₱59.4MCompleted · 100%
Construction of morocborocan interior road
Roads and bridges · 2022 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION
₱47.4MOn-Going · 62%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
SUNWEST, INC.106 projects · ₱9.01B
2
9LEAVES BUILDERS & SUPPLY CORP.37 projects · ₱251.7M
3
HI-TONE CONSTRUCTION & DEVELOPMENT CORP.10 projects · ₱778.6M
4
NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION7 projects · ₱234.3M
5
MACROPRIME BUILDERS CORPORATION7 projects · ₱223.6M