National projects
147projects
₱4.16Bin all
26ongoing
2slow
- Roads and bridges ₱2.77B
- Flood control ₱801.7M
- Other ₱193.0M
- Water ₱166.7M
- Schools ₱122.2M
- Buildings ₱113.4M
Showing 91 to 120 of 147
Concreting of purok 10 brgy. road, Brgy. poblacion, Sta. elena cams. norte
Roads and bridges · 2019 · RUR CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Construction of multi-purpose building, Brgy. villa san isidro
Buildings · 2019 · RUR CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Concreting of purok 4 brgy. road, Brgy. poblacion, Cams. norte
Roads and bridges · 2019 · RUR CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Concreting of kabuluan road, Brgy. kabuluan, Sta. elena cams. norte
Roads and bridges · 2019 · RUR CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Concreting of sta. elena brgy. road, Brgy. kagtalaba, Sta. elena cams. norte
Roads and bridges · 2019 · RUR CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Concreting of 14 to purok 15 brgy. road, Brgy. poblacion, Sta. elena cams. norte
Roads and bridges · 2019 · RUR CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Const./improvement of access roads leading to trades, Industries & economic zones, Guisican brgy. ro
Flood control · 2019 · SHEAR CONSTRUCTION AND SUPPLY
₱14.1MCompleted · 100%
Construction of water system at patag ibaba es, Brgy. patag ibaba, Sta elena cams. norte
Water · 2019 · NJNY CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Concreting of brgy. san antonio road, Brgy. san antonio, Capalonga cams. norte
Roads and bridges · 2019 · KENZOLE CONSTRUCTION AND GENERAL MERCHANDISE
₱1.9MCompleted · 100%
Asset preservation - rehab/reconst. of national roads with slips, Slope collapse and landslide -prim
Roads and bridges · 2019 · B2K LUMBER, CONSTRUCTION SUPPLIES AND SERVICES
₱47.9MCompleted · 100%
Construction of water system at patag ilaya es, Brgy. patag ilaya, Sta elena cams. norte
Water · 2019 · NJNY CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Const. of new bridges-binawangan bridge 1 along sta. elena-capalonga by pass coastal road (phase ii)
Roads and bridges · 2019 · EUS CONSTRUCTION
₱29.1MCompleted · 100%
Construction of multi-purpose building (covered court) bayabas elementary school, Brgy. bayabas, Lab
Schools · 2019 · GOLDEN CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Construction of multi-purpose building, Brgy. salvacion, Sta. elena cams. norte
Buildings · 2019 · YAKAL CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Construction of multi-purpose building (municipal plaza), Brgy. poblacion, Camarines nor
Buildings · 2019 · RUR CONSTRUCTION AND SUPPLY
₱4.8MCompleted · 100%
Const. of two (2) storey four (4) classroom school bldg., Don tomas elem. school, Sta. elena cams. n
Schools · 2018 · GOLDEN CONSTRUCTION AND SUPPLY
₱10.1MCompleted · 100%
Const. of one (1) storey three (3) classroom school bldg., Portugal chavez elem. school, Capalonga c
Schools · 2018 · N.E.B. CONSTRUCTION AND SUPPLY
₱4.2MCompleted · 100%
Construction of two (2) storey six (6) classroom school building, F. caudilla es, Labo cams. norte
Schools · 2018 · GOLDEN EGG BUILDER
₱16.4MCompleted · 100%
Construction of two (2) storey six (6) classroom school building, Juan a. amparo es, Sta. elena cams
Schools · 2018 · SPRING STAR CONSTRUCTION AND SUPPLY
₱16.5MCompleted · 100%
Const. of two (2) storey four (4) classroom school building, Rizal national h/s, Sta. elena cams. no
Schools · 2018 · RUR CONSTRUCTION AND SUPPLY
₱14.1MCompleted · 100%
Const. of hanging bridge, Brgy. cabatuhan, Labo cams. norte
Roads and bridges · 2018 · 128 DRAGON CONSTRUCTION AND SUPPLIES
₱1.9MCompleted · 100%
Construction of polyclinic
Buildings · 2018 · JURASSIC CONSTRUCTION & SUPPLIES
₱23.0MCompleted · 100%
Construction (completion) of multi-purpose building, Brgy. san antonio, Capalonga camarines norte
Buildings · 2018 · GOLDEN EGG BUILDER
₱968KCompleted · 100%
Widening primary roads, Daang maharlika (lz), Sta. k0247+883-sta.k0251+800 (with exceptions)
Roads and bridges · 2018 · HGG BUILDERS & SUPPLY
₱137.7MCompleted · 100%
Const. (completion) of multi-purpose bldg., Brgy. basiad, Sta. elena cams. norte
Buildings · 2018 · GOLDEN EGG BUILDER
₱2.0MCompleted · 100%
Const. of evacuation center, Brgy. san lorenzo, Cams. norte
Buildings · 2018 · RUR CONSTRUCTION AND SUPPLY
₱2.0MCompleted · 100%
Construction of evacuation center, Brgy. tabugon, Sta. elena cams. norte
Buildings · 2018 · RUR CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Const. of evacuation center, Brgy. bulala, Cams. norte
Buildings · 2018 · KENZOLE CONSTRUCTION AND GENERAL MERCHANDISE
₱1.9MCompleted · 100%
Upgrading of damaged paved roads, Primary roads quirino h-way-k0249+818-k0250+130, K
Roads and bridges · 2018 · NFH CONSTRUCTION & SUPPLY
₱13.0MCompleted · 100%
Preventive maintenance tertiary roads, Sta. elena-capalonga by pass co
Roads and bridges · 2018 · BRENTMIN ROOFING ENTERPRISE
₱10.0MCompleted · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
JAEJR ELECTRICAL, CONSTRUCTION & SUPPLY18 projects · ₱177.0M
2
N.E.B. CONSTRUCTION AND SUPPLY15 projects · ₱203.6M
3
BRENTMIN ROOFING ENTERPRISE12 projects · ₱226.8M
4
RUR CONSTRUCTION AND SUPPLY11 projects · ₱43.6M
5
GREAT WALL ENGINEERING9 projects · ₱98.3M