National projects
263projects
₱9.24Bin all
31ongoing
3slow
- Roads and bridges ₱4.97B
- Flood control ₱3.13B
- Schools ₱576.4M
- Buildings ₱524.8M
- Water ₱39.7M
Construction of by-pass and diversion roads-naga-jct. magarao-canaman-libmanan jct. pph road (skybridge), Package 1
Roads and bridges · 2024 · G.C.I. CONSTRUCTION AND DEV'T. CORP.
₱149.6MOn-Going · 43%Slow
Construction of multipurpose building, Brgy. san juan
Buildings · 2023 · SCHEIRMAN CONSTRUCTION CONSOLIDATED INC.
₱95.5MOn-Going · 0%Slow
Construction/repair/rehabilitation/improvement of various infrastructure including local projects-building and other structures-school buildings-construction of school building with multi-purpose covered court phase 1, Potot, Cama
Schools · 2020 · NATIONSTAR DEVELOPMENT CORPORATION
₱237.6MOn-Going · 58%Slow
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
BICOL GOLDROCK CONSTRUCTION CORPORATION30 projects · ₱1.49B
2
JMLD CONSTRUCTION28 projects · ₱375.9M
3
G.C.I. CONSTRUCTION AND DEV'T. CORP.26 projects · ₱2.52B
4
ALNINO CONSTRUCTION & SUPPLY CORPORATION18 projects · ₱586.5M
5
EDROX CONSTRUCTION, INC.10 projects · ₱46.8M