National projects
162projects
₱5.89Bin all
26ongoing
3slow
- Roads and bridges ₱3.56B
- Buildings ₱1.84B
- Flood control ₱341.3M
- Schools ₱136.1M
- Water ₱9.9M
Construction of multi-purpose building, Capitol complex, Barangay cadlan, Camarines su
Buildings · 2023 · R.K.X. ODIAMAR CONSTRUCTION
₱144.7MOn-Going · 27%Slow
Construction of multi-purpose building (camarines sur iconic capitol building)phase 2, Baran
Buildings · 2023 · NATIONSTAR DEVELOPMENT CORPORATION
₱189.1MOn-Going · 56%Slow
Construction/repair/rehabilitation/improvement of various infrastructure including local projects-building and other structures-construction of camarines sur iconic capitol building (phase i), Camarines sur 3rd legislati
Buildings · 2020 · NATIONSTAR DEVELOPMENT CORPORATION
₱482.5MOn-Going · 51%Slow
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
PHILWORKS CONSTRUCTION & SUPPLY17 projects · ₱842.2M
2
AA PAHATI CONSTRUCTION AND SUPPLY10 projects · ₱35.2M
3
DELPAR CONSTRUCTION & SUPPLIES7 projects · ₱54.4M
4
PHIL MANNA CONSTRUCTION & SUPPLY7 projects · ₱25.7M
5
BICOL GOLDROCK CONSTRUCTION CORPORATION6 projects · ₱225.5M