Official seal of Sipocot

Sipocot: Government

Municipality in Camarines Sur, Bicol, Luzon · 46 barangays

National projects

Built by DPWH in Sipocot since 2016.

274projects
₱8.99Bin all
51ongoing
4slow
  • Roads and bridges ₱6.54B
  • Flood control ₱1.80B
  • Buildings ₱424.4M
  • Schools ₱165.6M
  • Water ₱62.4M

Showing 151 to 180 of 199

Concreting of brgy. road, Brgy. anib to brgy. calampinay, Cam. sur Roads and bridges · 2018 · HKP CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Rehabilitation of barangay road, Barangay north centro Roads and bridges · 2018 · 301 ENGINEERS
₱940KCompleted · 100%
Const. of multi-purpose building, Lanot es, Brgy. lanot, Mercedes cams. norte Buildings · 2018 · JAEJR ELECTRICAL, CONSTRUCTION & SUPPLY
₱1.9MCompleted · 100%
Rehabilitation of barangay road at barangay south centro Roads and bridges · 2018 · F.N. ROLA CONSTRUCTION AND DEVELOPMENT CORP.
₱939KCompleted · 100%
Construction of flood control system, Brgy. north centro, Cam. sur Flood control · 2018 · DELPAR CONSTRUCTION & SUPPLIES
₱1.9MCompleted · 100%
Concreting of drainage system, Barangay north centro and barangay south centro Flood control · 2018 · DELPAR CONSTRUCTION & SUPPLIES
₱1.9MCompleted · 100%
₱1.9MCompleted · 100%
₱960KCompleted · 100%
₱1.9MCompleted · 100%
Construction of multi-purpose building, Barangay manangle Buildings · 2018 · JMLD CONSTRUCTION
₱1.9MCompleted · 100%
₱960KCompleted · 100%
₱1.9MCompleted · 100%
₱1.9MCompleted · 100%
₱31.5MCompleted · 100%
₱27.8MCompleted · 100%
₱5.1MCompleted · 100%
₱2.7MCompleted · 100%
₱2.7MCompleted · 100%
₱2.8MCompleted · 100%
₱2.7MCompleted · 100%
Construction of water system at barangay cabuyao Water · 2017 · HGG BUILDERS & SUPPLY
₱2.8MCompleted · 100%
₱1.9MCompleted · 100%
Construction of seawall at brgy. manga Flood control · 2017 · 301 ENGINEERS
₱1.9MCompleted · 100%
₱1.9MCompleted · 100%
Concreting of barangay road at brgy. south centro, Cam. sur Roads and bridges · 2017 · AARCON BUILDERS
₱1.9MCompleted · 100%
Concreting of barangay road at brgy. bulan, Cam. sur Roads and bridges · 2017 · JMLD CONSTRUCTION
₱1.9MCompleted · 100%
Concreting of barangay road at brgy. mantila, Cam. sur Roads and bridges · 2017 · 301 ENGINEERS
₱1.4MCompleted · 100%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Sipocot since 2016.

1
JMLD CONSTRUCTION21 projects · ₱97.0M
2
3-L CONSTRUCTION19 projects · ₱151.8M
3
HGG BUILDERS & SUPPLY16 projects · ₱741.1M
4
E. GARCIA CONSTRUCTION CORP.(FOR. E. GARCIA CONST15 projects · ₱556.8M
5
G.C.I. CONSTRUCTION AND DEV'T. CORP.13 projects · ₱1.52B

See something wrong?

A project that looks finished on paper but not on the ground, or work that stopped. Post a photo on the Talk board, or report it to DPWH on the project's own page.

Post on Talk →