Placer: Government

Municipality in Masbate, Bicol, Luzon · 35 barangays

National projects

Built by DPWH in Placer since 2016.

76projects
₱1.52Bin all
4ongoing
1slow
  • Roads and bridges ₱1.28B
  • Schools ₱125.6M
  • Flood control ₱54.3M
  • Buildings ₱47.9M
  • Water ₱12.8M

Showing 31 to 60 of 76

₱11.5MCompleted · 100%
₱8.9MCompleted · 100%
₱10.0MCompleted · 100%
₱7.6MCompleted · 100%
₱9.9MCompleted · 100%
₱10.0MCompleted · 100%
₱10.0MCompleted · 100%
₱10.1MCompleted · 100%
₱3.1MCompleted · 100%
₱8.9MCompleted · 100%
Flood mgt. program, Rehab./impv't. of matagangtang flood control, Matagangtang Flood control · 2018 · PARTIDO CONSTRUCTION & SUPPLY
₱18.6MCompleted · 100%
Const./upgrading/rehab. of drainage along national road Roads and bridges · 2018 · CL CARANDANG CONSTRUCTION AND SUPPLY CORPORATION
₱16.8MCompleted · 100%
Construction/upgrading/rehabilitation of drainage alang natl. road Roads and bridges · 2018 · CL CARANDANG CONSTRUCTION AND SUPPLY CORPORATION
₱11.2MCompleted · 100%
Const. & maint. of bridges along natl. roads, Replacement of perm. weak br., Matagangtang br.(b00053mt Roads and bridges · 2018 · ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 31762)
₱33.5MCompleted · 100%
Repair/rehab/improv of drainage struct. & slope prot. along mas-cat-pla road, Ban-ao, Masbat Flood control · 2017 · CL CARANDANG CONSTRUCTION AND SUPPLY CORPORATION
₱8.8MCompleted · 100%
₱4.3MCompleted · 100%
₱2.9MCompleted · 100%
₱2.9MCompleted · 100%
Const. of 1unit-1sty 2 classroom school building at luna e/s Schools · 2017 · S.A. TAMAYO CONSTRUCTION
₱2.9MCompleted · 100%
Repair/rehab./improv. of drainage struct. & slope prot along mas-cat-pla road, Aguada, Masba Roads and bridges · 2017 · CL CARANDANG CONSTRUCTION AND SUPPLY CORPORATION
₱8.6MCompleted · 100%
Construction of multi purpose covered court at brgy.poblacion, Masbate 3rd ld Buildings · 2017 · CL CARANDANG CONSTRUCTION AND SUPPLY CORPORATION
₱1.9MCompleted · 100%
Const. of multi-purpose covered court (mpb), Brgy.taboc Buildings · 2017 · CL CARANDANG CONSTRUCTION AND SUPPLY CORPORATION
₱1.9MCompleted · 100%
Const. of multi-purpose covered court (mpb), Brgy. guin-awayan Buildings · 2017 · CL CARANDANG CONSTRUCTION AND SUPPLY CORPORATION
₱1.9MCompleted · 100%
Upgrading of damaged paved natl. roads incl Roads and bridges · 2017 · ARKY CONSTRUCTION AND SUPPLY
₱27.8MCompleted · 100%
Const. of multipurpose covered court (14m x 15m) brgy. libas Buildings · 2017 · CL CARANDANG CONSTRUCTION AND SUPPLY CORPORATION
₱1.9MCompleted · 100%
Const. of multi purpose covered court (14m x 15m) brgy.dangpanan Buildings · 2017 · S.A. TAMAYO CONSTRUCTION
₱1.9MCompleted · 100%
Const. of multi purpose coverd court (14m x 15m) brgy. camayabsan Buildings · 2017 · S.A. TAMAYO CONSTRUCTION
₱1.9MCompleted · 100%
Const. of multi purpose covered court (14m x 15m) brgy. locso-an Buildings · 2017 · CL CARANDANG CONSTRUCTION AND SUPPLY CORPORATION
₱1.9MCompleted · 100%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Placer since 2016.

1
CL CARANDANG CONSTRUCTION AND SUPPLY CORPORATION15 projects · ₱143.0M
2
GRELIPS CONSTRUCTION & DEVELOPMENT8 projects · ₱69.5M
3
HKP CONSTRUCTION AND SUPPLY5 projects · ₱311.1M
4
SQUARE N CONSTRUCTION & SUPPLY5 projects · ₱76.7M
5
S.A. TAMAYO CONSTRUCTION5 projects · ₱13.8M

See something wrong?

A project that looks finished on paper but not on the ground, or work that stopped. Post a photo on the Talk board, or report it to DPWH on the project's own page.

Post on Talk →