Santa Praxedes: Government
Municipality in Cagayan, Cagayan Valley, Luzon · 10 barangays
National projects
75projects
₱1.55Bin all
5ongoing
3slow
- Roads and bridges ₱1.20B
- Flood control ₱243.9M
- Buildings ₱54.7M
- Schools ₱28.3M
- Water ₱19.6M
Showing 61 to 65 of 65
Construction of centro o2- salongsong farm to market road, Centro 02-salongsong
Roads and bridges · 2016 · DANDEX CONSTRUCTION
₱1.9MCompleted · 100%
Upgrading(unpaved to paved) based on gravel road strategies, Traffic benchmark for upgrading to paved road standards (hdm-4 analysis)(intermittent section) of ckr, K0606+439 to k0606+649
Roads and bridges · 2016 · JDL5 CONSTRUCTION CORPORATION
₱4.7MCompleted · 100%
Reconstruction of national roads w/ slips, Slope collapse and landslide along cadcadir-kabugao road, K0602+262-k0602+510
Roads and bridges · 2016 · JLL PULSAR CONSTRUCTION CORPORATION
₱46.6MCompleted · 100%
Construction of langgangan river control
Flood control · 2016 · D.J.D. CONSTRUCTION INC.
₱10.7MCompleted · 100%
Construction/concreting of barangay road brgy. san juan
Roads and bridges · 2016 · OCP CONSTRUCTION
₱1.9MCompleted · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
OCP CONSTRUCTION13 projects · ₱123.5M
2
DYLAN EQUIPMENT CONSTRUCTION AND SUPPLIES9 projects · ₱115.2M
3
SKYLINE CONSTRUCTION, EQUIPMENT AND DEVELOPMENT CORPORATION6 projects · ₱258.5M
4
JLL PULSAR CONSTRUCTION CORPORATION6 projects · ₱167.5M
5
J.B. ALCANTARA BUILDERS6 projects · ₱36.6M