Bambang: Government

Municipality in Nueva Vizcaya, Cagayan Valley, Luzon · 25 barangays

National projects

Built by DPWH in Bambang since 2016.

254projects
₱7.86Bin all
17ongoing
1slow
  • Flood control ₱3.75B
  • Roads and bridges ₱3.25B
  • Buildings ₱736.1M
  • Schools ₱110.2M
  • Water ₱6.4M
Construction (completion) of multi-purpose building, (new municipal building) bambang Buildings · 2025 · D.L CERVANTES CONSTRUCTION CORPORATION
₱96.1MOn-Going · 16%
Construction of multi-purpose building Buildings · 2025 · GERCEL CONSTRUCTION AND DEVELOPMENT GROUP INC.
₱12.9MOn-Going · 90%
Retrofitting/ strengthening of permanent bridges - abian br. (b01226lz) along maharlika highway Roads and bridges · 2025 · JLL PULSAR CONSTRUCTION CORPORATION
₱9.3MOn-Going · 0%
₱38.3MOn-Going · 100%
Construction of pallas-pinayag Roads and bridges · 2025 · BIG G BUILDERS
₱28.9MOn-Going · 94%
₱47.7MOn-Going · 0%
Preventive maintenance - primary roads along maharlika highway - k0257 + 000 - k0258 + 100 Roads and bridges · 2025 · JANN-NORRIS CONSTRUCTION AND SUPPLIES INC. (FORMELY: JANN-NORRIS CONSTRUCTION AND SUPPLIES)
₱68.7MOn-Going · 90%
Construction of by-pass and diversion roads - bambang by-pass road Roads and bridges · 2025 · JANN-NORRIS CONSTRUCTION AND SUPPLIES INC. (FORMELY: JANN-NORRIS CONSTRUCTION AND SUPPLIES)
₱93.3MOn-Going · 5%
Widening of permanent bridges - batu br. (b01227lz) along maharlika highway Roads and bridges · 2024 · JANN-NORRIS CONSTRUCTION AND SUPPLIES INC. (FORMELY: JANN-NORRIS CONSTRUCTION AND SUPPLIES)
₱87.1MOn-Going · 88%
Improvement of intersection daang maharlika (s00857lz) - k0249 + 800 and bambang kasibu - solano road (s00880lz) Roads and bridges · 2024 · JANN-NORRIS CONSTRUCTION AND SUPPLIES INC. (FORMELY: JANN-NORRIS CONSTRUCTION AND SUPPLIES)
₱9.6MOn-Going · 65%
Completion of multi-purpose bldg., Phase ii Buildings · 2024 · GERCEL CONSTRUCTION AND DEVELOPMENT GROUP INC.
₱74.2MOn-Going · 91%
Construction of multipurpose bldg., Nueva vizcaya phase ii Buildings · 2024 · GERCEL CONSTRUCTION AND DEVELOPMENT GROUP INC.
₱46.5MOn-Going · 90%
₱6.9MOn-Going · 74%
Installation of signage-warning, Advisory and regulatory signs, Pavement markings, And street lights along daang maharlika (lz) (s00857lz) - k024 Roads and bridges · 2024 · JANN-NORRIS CONSTRUCTION AND SUPPLIES INC. (FORMELY: JANN-NORRIS CONSTRUCTION AND SUPPLIES)
₱3.5MOn-Going · 100%
Rehabilitation/ reconstruction/ upgrading of damaged paved roads along daang maharlika (lz) - k0249 + 000 - k0251 + 000, K0284 + 542.70 - Roads and bridges · 2024 · EGB CONSTRUCTION CORPORATION / JC PALOMO CONSTRUCTION & CONSTRUCTION SUPPLY
₱181.3MOn-Going · 68%
Rehabilitation/reconstruction/ upgrading of damaged paved roads - primary roads - daang maharlika (lz) - k0248 + 000 - k0249 + 000, K0252 + 000 - k0253 + 000, K0253 + 000 - k02 Roads and bridges · 2024 · JANN-NORRIS CONSTRUCTION AND SUPPLIES INC. (FORMELY: JANN-NORRIS CONSTRUCTION AND SUPPLIES) / MONTALBAN CONCRETE AND ASPHALT INC.
₱137.5MOn-Going · 94%
Construction of by-pass and diversion roads - bambang bypass road Roads and bridges · 2024 · JANN-NORRIS CONSTRUCTION AND SUPPLIES INC. (FORMELY: JANN-NORRIS CONSTRUCTION AND SUPPLIES)
₱148.5MOn-Going · 55%Slow

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Bambang since 2016.

1
JANN-NORRIS CONSTRUCTION AND SUPPLIES INC. (FORMELY: JANN-NORRIS CONSTRUCTION AND SUPPLIES)37 projects · ₱1.89B
2
BRG CONSTRUCTION22 projects · ₱594.1M
3
DALCON CONSTRUCTION21 projects · ₱1.43B
4
JOVIC CONSTRUCTION AND SUPPLY17 projects · ₱33.5M
5
N-J CONSTRUCTION16 projects · ₱71.9M

See something wrong?

A project that looks finished on paper but not on the ground, or work that stopped. Post a photo on the Talk board, or report it to DPWH on the project's own page.

Post on Talk →