National projects

Built by DPWH in Cabarroguis since 2016.

199projects
₱1.86Bin all
6ongoing
0slow
  • Roads and bridges ₱894.6M
  • Buildings ₱635.8M
  • Schools ₱244.8M
  • Water ₱88.4M

Showing 61 to 90 of 199

Construction/rehabilitation of multi-purpose building barangay san marcos Buildings · 2021 · JURIS CONSTRUCTION & BUILDERS
₱4.9MCompleted · 100%
Concreting of brgy. mangandingay fmr phase 2, Brgy. mangandingay Roads and bridges · 2022 · KMD BUILDERS AND CONST. SUPPLY
₱11.9MCompleted · 100%
Rehabilitation of (purok 5 - purok 6) road, Barangay san marcos Roads and bridges · 2022 · A.P.D. CONSTRUCTION, INC.
₱14.8MCompleted · 100%
Rehabilitation of san marcos road, Barangay san marcos Roads and bridges · 2022 · A.P.D. CONSTRUCTION, INC.
₱29.7MCompleted · 100%
Improvement of burgos road, Barangay burgos Roads and bridges · 2022 · KMD BUILDERS AND CONST. SUPPLY
₱9.5MCompleted · 100%
Improvement of calaocan road, Barangay calaocan Roads and bridges · 2022 · JMD-68 BUILDERS
₱4.9MCompleted · 100%
Improvement of mangandingay road, Barangay mangandingay Roads and bridges · 2022 · KMD BUILDERS AND CONST. SUPPLY
₱4.7MCompleted · 100%
Improvement of banuar road, Barangay banuar Roads and bridges · 2022 · JMD-68 BUILDERS
₱4.9MCompleted · 100%
Improvement of eden road, Barangay eden Roads and bridges · 2022 · KMD BUILDERS AND CONST. SUPPLY
₱4.7MCompleted · 100%
Improvement of gomez road, Barangay gomez Roads and bridges · 2022 · JMD-68 BUILDERS
₱4.9MCompleted · 100%
Construction of multi-purpose buildings 2 & 3 san marcos Buildings · 2021 · NTL BUILDERS AND DEVELOPER
₱23.1MCompleted · 100%
Concreting of brgy. tucod fmr brgy. tucod Roads and bridges · 2021 · KMD BUILDERS AND CONST. SUPPLY
₱13.5MCompleted · 100%
₱11.4MCompleted · 100%
₱49.5MCompleted · 100%
Construction of multi-purpose building (main building) san marcos Buildings · 2021 · JURIS CONSTRUCTION & BUILDERS
₱19.8MCompleted · 100%
₱4.5MCompleted · 100%
₱7.9MCompleted · 100%
Construction of multi-purpose building san marcos Buildings · 2021 · NTL BUILDERS AND DEVELOPER
₱10.3MCompleted · 100%
₱11.9MCompleted · 100%
Construction of footbridge, Calaocan Roads and bridges · 2021 · JURIS CONSTRUCTION & BUILDERS
₱2.0MCompleted · 100%
Improvement of multi-purpose building brgy. san marcos Buildings · 2020 · NTL BUILDERS AND DEVELOPER
₱10.2MCompleted · 100%
Construction of multi-purpose building (senior citizen office) villa rose Buildings · 2020 · JURIS CONSTRUCTION & BUILDERS
₱2.0MCompleted · 100%
Construction of senior citizens office villarose Buildings · 2020 · JURIS CONSTRUCTION & BUILDERS
₱2.0MCompleted · 100%
₱4.9MCompleted · 100%
Improvement/concreting of local road, Villamor Roads and bridges · 2020 · KMD BUILDERS AND CONST. SUPPLY
₱2.9MCompleted · 100%
Improvement of multi-purpose building 2 brgy. san marcos Buildings · 2020 · JURIS CONSTRUCTION & BUILDERS
₱4.5MCompleted · 100%
Concreting of brgy. villamor fmr brgy. villamor Roads and bridges · 2020 · KMD BUILDERS AND CONST. SUPPLY
₱12.4MCompleted · 100%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

Who builds here

Contractors with the most projects in Cabarroguis since 2016.

1
JMD-68 BUILDERS36 projects · ₱147.9M
2
KMD BUILDERS AND CONST. SUPPLY35 projects · ₱225.2M
3
A.P.D. CONSTRUCTION, INC.23 projects · ₱663.2M
4
NTL BUILDERS AND DEVELOPER19 projects · ₱282.8M