165projects
₱2.43Bin all
7ongoing
1slow
- Roads and bridges ₱2.16B
- Flood control ₱100.9M
- Schools ₱87.5M
- Buildings ₱77.9M
- Water ₱1.8M
Showing 121 to 150 of 165
Upgrading (unpaved to paved) based on gravel road strategies, Traffic benchmark for upgrading to paved road standards (hdm-4 project analysis) along, Jct. victoria-maddela-alicia-kasibu boundary road (jct. victoria-kasibu boundary road), K0385+661-
Roads and bridges · 2017 · A.P.D. CONSTRUCTION, INC.
₱46.7MCompleted · 100%
Construction of multi-purpose building (completion) landingan
Buildings · 2017 · C-BROS CONSTRUCTION
₱2.0MCompleted · 100%
Reconstruction of pccp of scoured foundation including retaining structures along cordon-aurora boundary road, S04745lz, K0400+850, K0401+380, K0401+870, K0402+370, Disimungal
Roads and bridges · 2016 · A.P.D. CONSTRUCTION, INC.
₱14.7MCompleted · 100%
Reconstruction of pccp of scoured foundation including retaining structure along cordon-aurora bdry.(jct.dumabato-aurora bdry.)(s04547lz) k0404+300, K0408+120-k0408+140 ( right side k0408+120-k0408+160)left side), Disimungal
Roads and bridges · 2016 · A.P.D. CONSTRUCTION, INC.
₱7.8MCompleted · 100%
Repair/restoration of damage structures and removal of slides along cordon-diffun-maddela-aurora boundary, K0399+550
Roads and bridges · 2016 · KMD BUILDERS AND CONST. SUPPLY
₱7.0MCompleted · 100%
Construction of pccp of scoured foundation including retaining structures along cordon-aurora bdry.road (jct. dumabato-aurora bdry.) (s04746lz), K0394+850-k0394+855, K0396+005-k0396+033, K0400+050-k0400+086
Roads and bridges · 2016 · KMD BUILDERS AND CONST. SUPPLY
₱6.8MCompleted · 100%
Repair/restoration of damage structures and removal of slides along jct. abbag-guingin boundary road k0395+950, K0399+200, K0400+690
Roads and bridges · 2016 · KMD BUILDERS AND CONST. SUPPLY
₱3.2MCompleted · 100%
Repair/restoration/improvement along jct. abbag-guingin boundary road ( s04752lz), K0395+600, K0399+550
Roads and bridges · 2016 · KMD BUILDERS AND CONST. SUPPLY
₱4.4MCompleted · 100%
Repair/restoration/improvement along cordon-aurora boundary road ( jct. dumabato-aurora boundary) ( s04745lz) k0405+900
Roads and bridges · 2016 · C-BROS CONSTRUCTION
₱3.3MCompleted · 100%
Construction/rehabilitation of water supply/septage and sewerage/rain water collectors scala is (high school)
Schools · 2016 · JMD-68 BUILDERS
₱172KCompleted · 100%
Construction/rehabilitation of water supply/septage and sewerage/rain water collectors, Wasid is
Water · 2016 · JMD-68 BUILDERS
₱172KCompleted · 100%
Construction/rehabilitation of water supply/septage and sewerage/rain water collectors, Nagtipunan nhs
Water · 2016 · JMD-68 BUILDERS
₱172KCompleted · 100%
Construction/rehabilitation of water supply/septage and sewerage/rain water collectors, Sangbay is
Water · 2016 · JMD-68 BUILDERS
₱172KCompleted · 100%
Construction/rehabilitation of water supply/septage and sewerage/rain water collectors, Anak es
Water · 2016 · JMD-68 BUILDERS
₱172KCompleted · 100%
Construction/rehabilitation of water supply/septage and sewerage/rain water collectors, Asaklat es
Water · 2016 · JMD-68 BUILDERS
₱172KCompleted · 100%
Construction/rehabilitation of water supply/septage and sewerage/rain water collectors, Scala is (elementary)
Water · 2016 · JMD-68 BUILDERS
₱172KCompleted · 100%
Construction/rehabilitation of water supply/septage and sewerage/rain water collectors, Kimmabayo es
Water · 2016 · JMD-68 BUILDERS
₱172KCompleted · 100%
Concreting/improvement of sitio davinsin, San dionisio ii fmr, Barangay san dionisio ii
Roads and bridges · 2016 · COLBY CONSTRUCTION
₱4.9MCompleted · 100%
Concreting/improvement of asaklat fmr, Barangay asaklat
Roads and bridges · 2016 · COLBY CONSTRUCTION
₱4.9MCompleted · 100%
Construction/completion of multi-purpose building, Nagtipunan h/s
Buildings · 2016 · C-BROS CONSTRUCTION
₱2.0MCompleted · 100%
Rehabilitation/reconstruction of national roads with slips, Slope collapse, And landslide along jct. along abbag-guingin boundary road, K0392+776-k0392+830
Roads and bridges · 2016 · A.P.D. CONSTRUCTION, INC.
₱15.0MCompleted · 100%
Construction of multi-purpose building, Nagtipunan central school ponggo
Schools · 2016 · NTL BUILDERS AND DEVELOPER
₱2.0MCompleted · 100%
Construction/completion of multi-purpose building, Barangay asaklat
Buildings · 2016 · JMD-68 BUILDERS
₱1.9MCompleted · 100%
Upgrading (unpaved to paved) based on gravel rd strategies traffic benchmark for upgrading to pv
Roads and bridges · 2016 · ROYAL CROWN MONARCH CONSTRUCTION & SUPPLIES CORP.
₱48.0MCompleted · 100%
Construction of multi-purpose building barangay ponggo
Buildings · 2016 · JMD-68 BUILDERS
₱1.9MCompleted · 100%
Upgrading (unpaved to paved) based on gravel rd strategies traffic benchmark for upgrading to pav
Roads and bridges · 2016 · A.P.D. CONSTRUCTION, INC.
₱48.5MCompleted · 100%
Construction and maintenance of bridges along natl rd (rehab/major repair of permanent bridges)sangb
Roads and bridges · 2016 · C-BROS CONSTRUCTION
₱6.6MCompleted · 100%
Basic educational facilities fund (beff) - last mile school program - mainget ps
Schools · 2025 · A&A CANO GROUP OF COMPANIES INCORPORATED / MASAGANA DEVELOPMENT CORPORATION
₱19.9MNot Yet Started · 0%
Rehabilitation/ reconstruction of roads with slips, Slope collapse, And landslide - tertiary roads - jct abbag - nagtipunan-nueva vizcaya rd via dupax - k0453+135 - k0453+169
Roads and bridges · 2026 · NC CONSTRUCTION
₱3.3MNot Yet Started · 0%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
A.P.D. CONSTRUCTION, INC.40 projects · ₱1.55B
2
KMD BUILDERS AND CONST. SUPPLY28 projects · ₱109.0M
3
JMD-68 BUILDERS21 projects · ₱51.1M
4
NTL BUILDERS AND DEVELOPER12 projects · ₱34.5M
5
NC CONSTRUCTION11 projects · ₱77.1M