National projects
392projects
₱10.64Bin all
39ongoing
3slow
- Flood control ₱4.88B
- Roads and bridges ₱4.10B
- Buildings ₱1.14B
- Schools ₱480.6M
- Water ₱30.7M
- Other ₱15.5M
Construction of by-pass and diversion roads san juan bypass (rosario-san juan-laiya tourism bypass road) candelaria-san juan
Roads and bridges · 2024 · KATHA BUILDERS & SUPPLIES INC. / STRUKTURA TEKNIKA SERVICES CO.
₱131.9MOn-Going · 0%Slow
Rehabilitation of laiya-malabrigo road, Brgy. hugom, Batangas (phase 4)
Roads and bridges · 2024 · E.M. CUERPO, INC. / STRUKTURA TEKNIKA SERVICES CO.
₱96.3MOn-Going · 0%Slow
Rehabilitation of laiya - malabrigo road, Phase 3, Brgy. hugom
Roads and bridges · 2024 · E.M. CUERPO, INC. / STRUKTURA TEKNIKA SERVICES CO.
₱159.9MOn-Going · 53%Slow
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
THREE W BUILDERS, INC.43 projects · ₱1.17B
2
KENSAL RISE CONSTRUCTION33 projects · ₱427.7M
3
JASMIG CONSTRUCTION CORPORATION19 projects · ₱542.6M
4
A.M. ABDON CONSTRUCTION & SUPPLIES15 projects · ₱74.5M
5
V.R. PATRON BUILDERS & DEVELOPERS CORP. (PREVIOUSL11 projects · ₱706.2M