National projects
81projects
₱3.44Bin all
10ongoing
2slow
- Roads and bridges ₱1.81B
- Flood control ₱1.40B
- Buildings ₱185.7M
- Schools ₱36.1M
- Water ₱3.9M
Construction of slope protection works along carmona river, Phase 1
Flood control · 2025 · OMNICON BUILDERS
₱94.8MOn-Going · 81%
Widening - primary roads - juanito r. remulla, Sr. rd - k0036 + 977.40 - k0037 + 066, K0037 + 285 - k0037 + 950, K0039 + 318 - k0039 + 437
Roads and bridges · 2025 · HAUSLAND CONSTRUCTION
₱36.8MOn-Going · 3%
Widening - tertiary roads - bacoor-dasmariñas national rd - k0034 + 312 - k0034 + 350, K0034 + 354 - k0034 + 482, K0034 + 522 - k0034 + 936
Roads and bridges · 2025 · CBS CONSTRUCTION AND CONSTRUCTION SUPPLY
₱33.2MOn-Going · 0%
Rehabilitation/ reconstruction of roads with slips, Slope collapse, And landslide - primary roads - juanito r. remulla, Sr. rd - k0036 + 977 - k0037 + 066
Roads and bridges · 2025 · IGB DESIGN AND CONSTRUCTION
₱2.9MOn-Going · 87%
Construction of pedestrian overpass - juanito r. remulla, Sr. rd. - k0043 + 129
Roads and bridges · 2024 · T.E. TRINIDAD CONSTRUCTION
₱24.3MOn-Going · 47%Slow
Construction of multi-purpose building, Barangay f. reyes, Cavite and construction of multi-purpose building, Barangay olaes
Buildings · 2024 · ALMAKAR BUILDERS & METAL WORKS
₱11.8MOn-Going · 100%
Construction of dasmariñas city - san pedro - muntinlupa link road
Roads and bridges · 2023 · I&E CONSTRUCTION CORPORATION
₱48.1MOn-Going · 70%
Construction of road from paligawan ma
Roads and bridges · 2023 · SAN MARCELINO BUILDERS, INC.
₱91.7MOn-Going · 78%
Construction of dasmariñas - general mariano alvarez - carmona bypass road, General mariano alvarez cavite
Roads and bridges · 2023 · MARCBILT CONSTRUCTION, INC.
₱56.5MOn-Going · 0%Slow
Construction of riverbank and slope protection along san isidro river crossing, Phase 2, Barangay iba section, Silang, Cavite and construction of riverbank and slope protection along san isidro river crossing governors drive (gma section), Phase 2, Genera
Flood control · 2023 · HGG BUILDERS & SUPPLY
₱96.5MOn-Going · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
ALMAKAR BUILDERS & METAL WORKS11 projects · ₱322.9M
2
KLDS TRADING & CONSTRUCTION10 projects · ₱495.2M
3
OMNICON BUILDERS9 projects · ₱254.8M
4
HAUSLAND CONSTRUCTION8 projects · ₱367.3M
5
SAN MARCELINO BUILDERS, INC.3 projects · ₱140.9M