National projects
197projects
₱6.03Bin all
21ongoing
3slow
- Roads and bridges ₱2.30B
- Flood control ₱2.16B
- Buildings ₱820.7M
- Schools ₱625.3M
- Other ₱100.0M
- Water ₱28.5M
Construction/ upgrading/ rehabilitation of drainage along national roads - primary roads - calamba-sta cruz-famy jct rd - k0061 + 085 - k0062 + 285
Flood control · 2024 · MAR-VEL CONSTRUCTION & SUPPLY
₱52.7MOn-Going · 44%Slow
Construction / upgrading / rehabilitation of drainage along national roads - tertiary roads - makiling park rd - k0063 + 385 - k0063 + 1000
Roads and bridges · 2024 · DATZLAV CONSTRUCTION
₱38.3MOn-Going · 16%Slow
Improvement- primary roads- calamba - sta. cruz- famy jct. rd.- k0057+727 - k0057+985, K0058+035 -k0058+059, K0058+220 -k0058+500, K0058+960-k0058+1020, K0060+050- k0061+580
Roads and bridges · 2020 · B.C. CUERPO CONSTRUCTION CORPORATION / JOSE CRIS BUILDERS
₱55.0MOn-Going · 0%Slow
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
POWER K CONSTRUCTION SUPPLY & SERVICES17 projects · ₱351.9M
2
BHENLLABIEN BUILDERS CORPORATION16 projects · ₱383.3M
3
11 DIAMOND EAGLE CONSTRUCTION CORPORATION12 projects · ₱650.1M
4
MAR-VEL CONSTRUCTION & SUPPLY10 projects · ₱387.7M
5
DATZLAV CONSTRUCTION9 projects · ₱104.6M