Built by DPWH in Tiaong since 2016.

182projects
₱4.08Bin all
33ongoing
5slow
  • Roads and bridges ₱2.54B
  • Flood control ₱707.8M
  • Schools ₱391.8M
  • Buildings ₱345.7M
  • Water ₱90.6M

Showing 1 to 30 of 145

Construction of water supply system, Barangay bula Water · 2025 · JAICA CONST. CORP
₱7.4MCompleted · 100%
₱7.3MCompleted · 100%
Construction of water supply system, Barangay tagbakin Water · 2025 · LASENT CONSTRUCTION AND SUPPLY
₱7.2MCompleted · 100%
Construction of water supply system, Barangay ayusan 1 Water · 2025 · I.A . BOSQUE CONSTRUCTION CORPORATION
₱7.2MCompleted · 100%
Construction of water supply system, Barangay tamisian Water · 2025 · I.A . BOSQUE CONSTRUCTION CORPORATION
₱7.2MCompleted · 100%
Construction of water supply system, Barangay behia Water · 2025 · JAICA CONST. CORP
₱6.4MCompleted · 100%
Construction of water supply system, Barangay del rosario Water · 2025 · I.A . BOSQUE CONSTRUCTION CORPORATION
₱7.2MCompleted · 100%
₱7.3MCompleted · 100%
₱4.9MCompleted · 100%
₱4.9MCompleted · 100%
Preventive maintenance-tertiary roads, Msr jct tiaong-dolores rd- k0095+260 - k0097+171 Roads and bridges · 2024 · WAYCON BUILDERS AND CONSTRUCTION SUPPLY CORP.
₱96.5MCompleted · 100%
Preventive maintenance -secondary roads, Quezon - batangas rd - k0099+ 146 - k0101+240 Roads and bridges · 2024 · WAYCON BUILDERS AND CONSTRUCTION SUPPLY CORP.
₱81.1MCompleted · 100%
Concreting of brgy. ayusan 2 fmr, Brgy. ayusan 2 Roads and bridges · 2024 · JAICA CONST. CORP
₱9.9MCompleted · 100%
₱2.5MCompleted · 100%
₱9.9MCompleted · 100%
₱7.4MCompleted · 100%
Construction of flood control structure, Barangay ayusan 2, Quezon province Flood control · 2024 · WAYCON BUILDERS AND CONSTRUCTION SUPPLY CORP.
₱5.0MCompleted · 100%
Construction of road, Brgy. tamisian Roads and bridges · 2024 · JAICA CONST. CORP
₱5.9MCompleted · 100%
Widening-tertiary roads, Msr jct tiaong-dolores rd-k0096+081 - k0096+516 Roads and bridges · 2024 · ROMHEAD S.J. BUILDERS AND DEVELOPMENT INCORPORATED.
₱24.3MCompleted · 100%
₱7.4MCompleted · 100%
Construction of bridge, Barangay tamisian Roads and bridges · 2024 · JAICA CONST. CORP
₱5.0MCompleted · 100%
₱2.5MCompleted · 100%
Construction (completion) of multi-purpose building, Barangay bulakin, Quezon province Buildings · 2024 · WAYCON BUILDERS AND CONSTRUCTION SUPPLY CORP.
₱2.5MCompleted · 100%
Construction of multi-purpose building, Barangay lalig Buildings · 2024 · I.A . BOSQUE CONSTRUCTION CORPORATION
₱7.4MCompleted · 100%
Installation of road safety devices along tiaong bypass rd-k0095+000, Lumingon Roads and bridges · 2024 · ROMHEAD S.J. BUILDERS AND DEVELOPMENT INCORPORATED.
₱940KCompleted · 100%
Preventive maintenance-secondary roads, Tiaong bypass rd-k0094+136-k0094+360 Roads and bridges · 2024 · ROMHEAD S.J. BUILDERS AND DEVELOPMENT INCORPORATED.
₱19.7MCompleted · 100%
Construction of multi-purpose building, Claro m recto central school, Poblacion 1 Schools · 2024 · WAYCON BUILDERS AND CONSTRUCTION SUPPLY CORP.
₱7.4MCompleted · 100%
Construction of road, Barangay bukal Roads and bridges · 2024 · I.A . BOSQUE CONSTRUCTION CORPORATION
₱11.9MCompleted · 100%
Construction of road, Barangay anastacia Roads and bridges · 2024 · I.A . BOSQUE CONSTRUCTION CORPORATION
₱11.9MCompleted · 100%
Construction of road, Brgy. tamisian to brg Roads and bridges · 2023 · JAICA CONST. CORP
₱9.7MCompleted · 100%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Tiaong since 2016.

1
WAYCON BUILDERS AND CONSTRUCTION SUPPLY CORP.33 projects · ₱925.4M
2
I.A . BOSQUE CONSTRUCTION CORPORATION31 projects · ₱423.3M
3
ROMHEAD S.J. BUILDERS AND DEVELOPMENT INCORPORATED.19 projects · ₱229.3M
4
JAICA CONST. CORP19 projects · ₱99.1M
5
WYDERWAYS BUILDERS AND SUPPLIES8 projects · ₱26.1M