Maria Aurora: Government

Municipality in Aurora, Central Luzon, Luzon · 40 barangays

National projects

Built by DPWH in Maria Aurora since 2016.

261projects
₱5.42Bin all
23ongoing
0slow
  • Roads and bridges ₱3.47B
  • Flood control ₱1.09B
  • Buildings ₱427.9M
  • Schools ₱360.2M
  • Water ₱45.5M
  • Other ₱23.3M

Showing 31 to 60 of 261

₱5.0MOn-Going · 100%
₱6.9MCompleted · 100%
₱6.9MCompleted · 100%
Construction of multi-purpose building (barangay hall), Barangay 4 Buildings · 2025 · VANMARVIL CONSTRUCTION
₱5.0MCompleted · 100%
Construction of multi-purpose building, Barangay debucao Buildings · 2025 · ALEXI LOUISSE CONSTRUCTION & GENERAL MERCHANDISE
₱4.9MOn-Going · 100%
₱6.9MOn-Going · 64%
₱6.9MCompleted · 100%
Construction of multi-purpose building (covered court), Diome elementary school, Barangay diome Schools · 2025 · CONRADO B. BAUTISTA CONST. & SUPPLY CORP. (FORMERL
₱6.9MCompleted · 100%
₱46.1MCompleted · 100%
₱6.9MCompleted · 100%
₱146.3MOn-Going · 20%
Concreting of sitio parang, Brgy. sto. cristo fmr, Brgy. sto. cristo Roads and bridges · 2024 · R.N.G.M. CONSTRUCTION CORPORATION
₱14.9MCompleted · 100%
Concreting of brgy. wenceslao to brgy. sto. tomas fmr, Brgy. wenceslao, And brgy. sto. tomas Roads and bridges · 2024 · 816 ALLEN CONSTRUCTION AND DEVELOPMENT CORPORATION
₱18.9MCompleted · 100%
Concreting of brgy. quirino to brgy. san leonardo to brgy. debucao fmr Roads and bridges · 2024 · DALCON CONSTRUCTION
₱24.9MCompleted · 100%
Construction of school facilities quirino elementary school, Quirino Schools · 2024 · BRENCON DEVELOPERS PHILS. INC.
₱48.5MOn-Going · 90%
Construction of multi-purpose building, Brgy. ramada Buildings · 2024 · 1ST CUT & FILL CONSTRUCTION CORP.
₱4.8MCompleted · 100%
Construction of rainwater collector system Water · 2024 · CONRADO B. BAUTISTA CONST. & SUPPLY CORP. (FORMERL
₱2.9MOn-Going · 92%
Construction of 2sty8cl, Suguit nhs Other · 2024 · JAVEN CONSTRUCTION
₱23.3MCompleted · 100%
Construction of bridge, Diaman Roads and bridges · 2024 · R.D. TALENS CONSTRUCTION AND TRADING
₱49.5MCompleted · 100%
Construction of road, Punglo to diaman Roads and bridges · 2024 · MORNING STEEL CONSTRUCTION / ZF CONSTRUCTION
₱99.0MOn-Going · 97%
Construction of road, Diat Roads and bridges · 2024 · SO CONSTRUCTION
₱11.9MCompleted · 100%
Construction of water system, Malasin Water · 2024 · VANMARVIL CONSTRUCTION
₱5.0MCompleted · 100%
Construction of road, Barangay ramada Roads and bridges · 2024 · VANMARVIL CONSTRUCTION
₱14.4MCompleted · 100%
₱6.3MCompleted · 100%
Construction of flood control structure, Barangay san jose, Ma. aurora Flood control · 2024 · IRC CONSTRUCTION & SUPPLIES
₱49.0MOn-Going · 99%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

Who builds here

Contractors with the most projects in Maria Aurora since 2016.

1
VANMARVIL CONSTRUCTION35 projects · ₱235.8M
2
JOHN DEE B. BUSTAMANTE CONSTRUCTION25 projects · ₱296.9M
3
R.N.G.M. CONSTRUCTION CORPORATION22 projects · ₱191.5M
4
SO CONSTRUCTION17 projects · ₱135.8M
5
ZF CONSTRUCTION15 projects · ₱618.6M

See something wrong?