National projects
119projects
₱4.58Bin all
21ongoing
0slow
- Flood control ₱3.08B
- Roads and bridges ₱1.29B
- Buildings ₱167.1M
- Schools ₱47.0M
Showing 1 to 30 of 95
Preventive maintenance - secondary roads olangapo - bugallon rd - k0176 +564 - k0177 + 335, K0187 + 784 -k0188 + 000, K0189 + 000 - k0190 + 000, K0195 + 200 - k0195 + 390, K0199 + 735 - k0200 + 330, Cabangan & botolan
Roads and bridges · 2025 · R.A. PAHATI CONST. & SUPPLY, INC.
₱95.3MCompleted · 100%
Construction of public covered court including ground improvements, Brgy. feria, Phase 2 san felipe
Buildings · 2024 · ROCK-WBL CONSTRUCTION CORP.
₱19.5MCompleted · 100%
Construction of sindol - tektek road, Barangay sindol
Roads and bridges · 2024 · GASAT BUILDERS AND SUPPLIES INC.
₱14.5MCompleted · 100%
Construction of slope protection structure along gabor river, Balincaguing section (phase i)
Flood control · 2024 · RAIK CONSTRUCTION AND DEVELOPMENT CORPORATION
₱95.2MCompleted · 100%
Construction of maloma river flood control structure, Downstream, Package 4
Flood control · 2024 · HGG BUILDERS & SUPPLY / S-ANG CONSTRUCTION & GENERAL TRADING, INC.
₱96.5MCompleted · 100%
Construction of multi-purpose building, Barangay feria
Buildings · 2024 · ROCK-WBL CONSTRUCTION CORP.
₱19.6MCompleted · 100%
Construction of multi-purpose building (senior citizens building)
Buildings · 2024 · SMP-JADE CONSTRUCTION CORPORATION
₱4.9MCompleted · 100%
Flood control works/flood mitigation structure along gabor river, Package 1
Flood control · 2024 · RAAMDC CONSTRUCTION
₱28.5MCompleted · 100%
Flood control works/flood mitigation structure along gabor river, Package 2
Flood control · 2024 · RAAMDC CONSTRUCTION
₱28.5MCompleted · 100%
Preventive maintenance - secondary roads olangapo - bugallon rd.- k0170+178 - k0170+339, K0170+359 - k0172+025, K0174+649- k0175+000
Roads and bridges · 2024 · R.A. PAHATI CONST. & SUPPLY, INC.
₱96.2MCompleted · 100%
Construction of maloma river flood control structure, Upstream, Package 4, Sagpat section
Flood control · 2024 · C.T. LEONCIO CONSTRUCTION & TRADING
₱95.3MCompleted · 100%
Construction of maloma river flood control structure, Downstream, Package 1
Flood control · 2024 · AMETHYST HORIZON BUILDERS AND GEN. CONTRACTOR AND DEVELOPMENT CORP. ([REVOKED] 49129)
₱95.1MCompleted · 100%
Construction of maloma river flood control structure, Downstream, Package 3
Flood control · 2024 · ELITE GENERAL CONTRACTOR AND DEVELOPMENT CORP.
₱96.5MCompleted · 100%
Construction of maloma river flood control structure, Upstream, Package 1, Sagpat section
Flood control · 2024 · AMETHYST HORIZON BUILDERS AND GEN. CONTRACTOR AND DEVELOPMENT CORP. ([REVOKED] 49129)
₱95.2MCompleted · 100%
Construction of maloma river flood control structure, Upstream, Package 3, Sagpat section
Flood control · 2024 · C.T. LEONCIO CONSTRUCTION & TRADING
₱95.2MCompleted · 100%
Construction of maloma river flood control structure, Downstream, Package 2
Flood control · 2024 · AMETHYST HORIZON BUILDERS AND GEN. CONTRACTOR AND DEVELOPMENT CORP. ([REVOKED] 49129)
₱95.1MCompleted · 100%
Preventive maintenance - secondary roads olongapo-bugallon rd - k0175 + 000 - k0175 + 449, K0175 + 584 - k0176 + 533, K0177 + 924 - k0178 + 806, San felipe & cabangan
Roads and bridges · 2024 · R.A. PAHATI CONST. & SUPPLY, INC.
₱95.5MCompleted · 100%
Construction of slope protection along sto. tomas river brgy. rosete phase 2
Flood control · 2024 · VM BUILDERS CONSTRUCTION CORPORATION
₱28.5MCompleted · 100%
Construction of flood mitigation structure along santo tomas river (phase 6)
Flood control · 2024 · CDC CONSTRUCTION & SUPPLIES
₱96.5MCompleted · 100%
Preventive maintenance - secondary roads - olongapo - bugallon rd - k0 173+315 - k0 174+292
Roads and bridges · 2024 · R.A. PAHATI CONST. & SUPPLY, INC.
₱25.4MCompleted · 100%
Construction of multi-purpose building (phase 2), Barangay sindol
Buildings · 2024 · VM BUILDERS CONSTRUCTION CORPORATION
₱5.8MCompleted · 100%
Construction of flood control structure along gabor-liwliwa river (phase i)
Flood control · 2024 · T2B3 BUILDERS AND SUPPLIES CORP.
₱95.1MCompleted · 100%
Construction (completion) of multi-purpose building, Barangay feria
Buildings · 2024 · G.M.R CONSTRUCTION & SUPPLY
₱2.9MCompleted · 100%
Installation of solar lights along olongapo-bugallon road - k0170 + 359 - k0172 + 025
Roads and bridges · 2024 · AKPSN BUILDERS AND SUPPLY
₱5.8MCompleted · 100%
Construction of maloma river flood control structure, Upstream, Package 2, Sagpat section
Flood control · 2024 · C.T. LEONCIO CONSTRUCTION & TRADING
₱95.2MCompleted · 100%
Construction/maintenance of flood mitigation structures and drainage system-construction of flood control structures at sagpat river (maloma section), Province of zambales
Flood control · 2023 · R.A. PAHATI CONST. & SUPPLY, INC.
₱96.5MCompleted · 100%
Construction of liw-liwa river flood control structure, Downstream, Package 2, Sitio liw-liwa
Flood control · 2023 · CDC CONSTRUCTION & SUPPLIES
₱71.7MCompleted · 100%
Construction of roads, Brgy. maloma
Roads and bridges · 2023 · GASAT BUILDERS AND SUPPLIES INC.
₱9.6MCompleted · 100%
Installation of solar lights along coastal road/tourism roads, Brgy. sto. niño
Roads and bridges · 2023 · ECANGELES CONST. & CONST. SUPPLY
₱9.6MCompleted · 100%
Construction of slope protection structure along bukas river, Sitio anangka, Barangay rosete
Flood control · 2023 · VM BUILDERS CONSTRUCTION CORPORATION
₱9.7MCompleted · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
Who builds here
1
STO. CRISTO CONSTRUCTION & TRADING INC.10 projects · ₱336.5M
2
R.A. PAHATI CONST. & SUPPLY, INC.8 projects · ₱666.6M
3
CDC CONSTRUCTION & SUPPLIES8 projects · ₱576.1M
4
JORGZ KONZTRAK & SUPPLY6 projects · ₱24.0M
5
E.R. DELA CRUZ CONSTRUCTION & SUPPLY5 projects · ₱165.1M