SL
Santa Lucia: Government
Municipality in Ilocos Sur, Ilocos, Luzon · 36 barangays
National projects
47projects
₱753.1Min all
2ongoing
0slow
- Roads and bridges ₱371.1M
- Flood control ₱313.0M
- Schools ₱30.6M
- Buildings ₱28.9M
- Water ₱9.5M
Showing 31 to 47 of 47
Construction/rehabilitation of flood mitigation facilities within major basins and principal river, Construction of buaya river control, (brgy. paoc norte, Bani and cabaritan section)
Flood control · 2018 · FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORP.
₱18.6MCompleted · 100%
Rehabilitation/reconstruction/upgrading of damaged paved roads- tertiary roads, Jct. sta. lucia-salcedo road, K0342+000-k0343+000
Roads and bridges · 2018 · 739 BUILDERS
₱25.0MCompleted · 100%
Construction of classrooms paoc es
Schools · 2017 · FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORP.
₱2.7MCompleted · 100%
Construction of classrooms sabuanan es
Schools · 2017 · J.A. OLIVAR ENGINEERING DESIGN, CONSTRUCTION AND SUPPLIES
₱4.0MCompleted · 100%
Construction of classrooms don pedro festejo memorial school, Ilocos
Schools · 2017 · FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORP.
₱2.7MCompleted · 100%
Rehabilitation/reconstruction/upgrading of damaged paved national roads including drainaged based on pavement management-4(hdm-4), Jct. sta. lucia-salcedo road, K0340+000-k0341+000 and k0341+918-k0342+000
Roads and bridges · 2017 · R.S. SEPIAN CONSTRUCTION & TRUCKING
₱31.3MCompleted · 100%
Concreting of brgy. sapang fmr, Brgy. sapang
Roads and bridges · 2017 · FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORP.
₱1.9MCompleted · 100%
Construction/maintenance of flood mitigation structures and drainage systems - construction of flood control along cavite bridge 1 & 2, Mnr
Flood control · 2017 · FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORP.
₱24.5MCompleted · 100%
Concreting of parioco-alincaoegsta. lucia
Roads and bridges · 2016 · NGEC-NESTOR GENERAL ENGINEERING & CONSTRUCTION
₱1.9MCompleted · 100%
Construction of classrooms, (4 sty-12 cl.)teodoro hernaez nhs
Schools · 2016 · VIGAN FORTUNE CONSTRUCTION
₱21.3MCompleted · 100%
Upgrading of damaged paved national roads including drainage based on (pms/hdm-4), Tertiary road jct sta. lucia-salcedo rd, K0339+(-880) - k0339+(-715), K0339+(-371)-k0339+083, K0345+100-k0345+600 & k0350+000-k0350+116
Roads and bridges · 2016 · FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORP.
₱27.5MCompleted · 100%
Widening of permanent bridges to more than two (2) lanes, San juan bridge 1 (b00613lz) along manila north road
Roads and bridges · 2016 · WERR CORPORATION INTERNATIONAL
₱5.6MCompleted · 100%
Widening of permanent bridges to more than two (2) lanes, San juan bridge 2 (b00614lz) along manila north road
Roads and bridges · 2016 · WERR CORPORATION INTERNATIONAL
₱5.2MCompleted · 100%
Widening of permanent bridges to more than two (2) lanes, Cavite bridge 1 (b00616lz) along manila north road
Roads and bridges · 2016 · M.V. SABALBURO CONSTRUCTION AND SUPPLY
₱8.3MCompleted · 100%
Conc, Of lubong-suagayan-sabuanan fmr
Roads and bridges · 2016 · FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORP.
₱4.7MCompleted · 100%
Construction of road, Barangay buliclic, Sta. 0+000 - sta.0+572
Roads and bridges · 2026
₱0For Procurement · 0%
Construction of bridge, Barangay paratong, Sta. 0+128 - sta. 0+146
Roads and bridges · 2026
₱0For Procurement · 0%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
Who builds here
1
FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORP.21 projects · ₱428.5M
2
MRK-SQUARE CONSTRUCTION AND SUPPLY5 projects · ₱39.4M
3
M.V. SABALBURO CONSTRUCTION AND SUPPLY3 projects · ₱47.3M
4
WERR CORPORATION INTERNATIONAL2 projects · ₱10.8M
5
A.P.B. CONSTRUCTION1 project · ₱46.5M