Santa Maria: Government

Municipality in Pangasinan, Ilocos, Luzon · 23 barangays

National projects

Built by DPWH in Santa Maria since 2016.

137projects
₱2.07Bin all
13ongoing
2slow
  • Roads and bridges ₱938.3M
  • Flood control ₱603.2M
  • Buildings ₱449.7M
  • Other ₱44.3M
  • Schools ₱37.4M

Showing 121 to 137 of 137

Concreting of brgy. pilar fmr, Brgy. pilar Roads and bridges · 2017 · 2-R CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Concreting of brgy. namagbagan fmr, Brgy. namagbagan Roads and bridges · 2017 · ROGENOX CONSTRUCTION AND SUPPLY CORP.
₱1.9MCompleted · 100%
Concreting of brgy. pataquid-cabuloan fmr, Brgy. pataquid and cabuloan Roads and bridges · 2017 · AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
₱1.9MCompleted · 100%
Constn of two stry four cl sb at sta. cruz i/s Buildings · 2016 · MKM MARKETING
₱6.0MCompleted · 100%
Concreting of road, Brgy pilar, Pilar namagbagan road Roads and bridges · 2017 · W.J.P. CONSTRUCTION AND SUPPLY
₱2.8MCompleted · 100%
Expansion of brgy. health station-birthing, Libsong bhs Buildings · 2016 · AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
₱918KCompleted · 100%
Concreting of brgy. san vicente fmr, Brgy. san vicente Roads and bridges · 2016 · W.J.P. CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Concreting of namagbagan fmr, Brgy. namagbagan Roads and bridges · 2016 · W.J.P. CONSTRUCTION AND SUPPLY
₱1.9MCompleted · 100%
Const of two unit three stry nine cl sb at sta. maria east i/s Other · 2016 · AC SOLIVEN CONSTRUCTION CORPORATION / BIG BERTHA CONSTRUCTION & DEVELOPMENT
₱29.9MCompleted · 100%
₱2.6MCompleted · 100%
Constn of one stry four cl sb w/ toilet attached at san pablo e/s Buildings · 2016 · 2-R CONSTRUCTION AND SUPPLY
₱3.7MCompleted · 100%
Constn of one stry one cl w/ toilet attached at pugot e/s Buildings · 2016 · AMP 723 CONSTRUCTION CORPORATION
₱1.1MCompleted · 100%
Preventive maint based on pavement mgmt system/highway devt & mgmt-4 (hdm-4) (intermittent sections) Roads and bridges · 2016 · ALCEL CONSTRUCTION / ORIENTAL SALES CENTER AND CONTRACTOR
₱45.1MCompleted · 100%
Const/completion of san alejandro mpb Buildings · 2016 · ALPHIN TRADING & CONSTRUCTION
₱1.5MCompleted · 100%
Constn/maint of flood mitigation structures& drainage system-agno river basin flood ctrl proj-rehab Flood control · 2016 · R.A. MATIAS CONSTRUCTION AND DEVELOPERS INC.
₱7.2MCompleted · 100%
Construction of road, Phase 2 Roads and bridges · 2025
₱0For Procurement · 0%
Construction of road, Phase 2 Roads and bridges · 2025
₱0For Procurement · 0%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Santa Maria since 2016.

1
JHI CONSTRUCTION & SUPPLY11 projects · ₱98.1M
2
W.J.P. CONSTRUCTION AND SUPPLY9 projects · ₱33.6M
3
AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION8 projects · ₱168.4M
4
RIVBROS CONSTRUCTION FACTORS & DEVELOPMENT8 projects · ₱151.8M
5
R.A. MATIAS CONSTRUCTION AND DEVELOPERS INC.8 projects · ₱140.0M