MA
Magsaysay: Government
Municipality in Palawan, Mimaropa, Luzon · 11 barangays
National projects
30projects
₱284.1Min all
2ongoing
2slow
- Schools ₱125.6M
- Roads and bridges ₱97.5M
- Buildings ₱41.3M
- Water ₱19.6M
Construction of level ii water supply system, Lucbuan
Water · 2024 · EUS CONSTRUCTION
₱4.9MOn-Going · 0%Slow
Construction of level ii water supply system, Cocoro
Water · 2024 · EUS CONSTRUCTION
₱4.9MOn-Going · 0%Slow
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
GOLDROCK CONSTRUCTION & DEVELOPMENT CORP.7 projects · ₱133.2M
2
MARYKNOLL BUILDERS AND SUPPLY6 projects · ₱44.1M
3
ST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196)4 projects · ₱24.8M
4
EUS CONSTRUCTION3 projects · ₱14.8M
5
KAYANO TRADING AND CONSTRUCTION2 projects · ₱24.5M