Showing 781 to 810 of 2,305
Rehabilitation / reconstruction/ upgrading of damaged paved roads - tertiary roads - juan luna st. - k0003+(-632.0) to k0003+(125.0)
Roads and bridges · 2022 · M.V. CALDO CONSTRUCTION AND SUPPLY CORPORATION
₱17.6MCompleted · 100%
Improvement of singalong st. and vicinity, Zone 79 & 80
Roads and bridges · 2022 · KPSL GENERAL CONTRACTOR INC.
₱14.8MCompleted · 100%
Improvement of roads and alleys, Zone 86
Roads and bridges · 2022 · M.C. LAYGO BUILDERS
₱4.9MCompleted · 100%
Construction of multi-purpose building, Zone 88
Buildings · 2022 · 5 JEWEL'S CONSTRUCTION AND SUPPLY CORP.
₱5.9MCompleted · 100%
Improvement of roads and alleys, Brgy. 767
Roads and bridges · 2022 · ALE BUILDERS CONSTRUCTION AND DEVELOPMENT CORP.
₱9.6MCompleted · 100%
Improvement of roads and alleys, Brgy. 766
Roads and bridges · 2022 · ALE BUILDERS CONSTRUCTION AND DEVELOPMENT CORP.
₱6.4MCompleted · 100%
Improvement of roads and alleys, Malate
Roads and bridges · 2022 · KPSL GENERAL CONTRACTOR INC.
₱7.9MCompleted · 100%
Rehabilitation/reconstruction/upgrading of damaged paved roads-secondary roads-roxas blvd., K0000+216.50-k0002+011.50, Maniila
Roads and bridges · 2022 · ALPHA & OMEGA GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 38958) / JMK BUILDERS CONSTRUCTION
₱89.1MCompleted · 100%
Construction of multi-purpose buildings, Zone 89
Buildings · 2022 · 5 JEWEL'S CONSTRUCTION AND SUPPLY CORP.
₱4.9MCompleted · 100%
Construction of retarding basin at estero de san miguel
Flood control · 2022 · ALPHA & OMEGA GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 38958)
₱48.8MCompleted · 100%
Rehabilitation of school building with drainage improvement
Schools · 2022 · DOUBLE 12 CONSTRUCTION & SUPPLY
₱45.6MCompleted · 100%
Rehabilitation of road, Zone 1 - 7 barangay 1 - 90
Roads and bridges · 2022 · ALLEYWAY CONSTRUCTION
₱33.6MCompleted · 100%
Rehabilitation / major repair of permanent bridges -1. j.p. laurel br. 1 (b03347lz) along j.p. laurel st. - 9, 799, 617.652. j.p. laurel br. 2 (b03348lz) along j.p. laurel st. - 979, 354.54
Roads and bridges · 2022 · D.T. RECIO INCORPORATED
₱10.4MCompleted · 100%
Improvement (steel sheet pile) along estero de magdalena, Sta. 0+155.20 to sta. 0+307.20 left side tondo
Flood control · 2022 · J. SIMEON CONSTRUCTION
₱49.0MCompleted · 100%
Construction of multi-purpose building at barangay 343
Buildings · 2022 · RAICON DEVELOPMENT CORPORATION
₱45.8MCompleted · 100%
Preventive maintenance - secondary roads - alfonso mendoza st (s02250lz) - ch 476.80 - ch. 597. 20, Ch. 757.30 - ch. 930.00
Roads and bridges · 2022 · MANGEN TECHNO-BUILDERS INC.
₱9.8MCompleted · 100%
Construction of multi-purpose building at abad santos high school
Schools · 2022 · GOLDEN J'S CONSTRUCTION SERVICES
₱11.6MCompleted · 100%
Rehabilitation / reconstruction of presidential security group (psg), Multi -purpose building (mhq)
Buildings · 2021 · GOLDEN J'S CONSTRUCTION SERVICES
₱23.2MCompleted · 100%
Construction of multi-purpose building barangay 385
Buildings · 2022 · FLORDES CONSTRUCTION & TRADING CORP.
₱9.7MCompleted · 100%
Construction of multi-purpose building barangay 330
Buildings · 2022 · FLORDES CONSTRUCTION & TRADING CORP.
₱6.9MCompleted · 100%
Improvement (steel sheet pile) along estero de magdalena, Sta. 0+076.00 to sta. 0+155.20 both side, Tondo
Flood control · 2022 · J. SIMEON CONSTRUCTION
₱49.0MCompleted · 100%
Construction of multi-purpose building barangay 314
Buildings · 2022 · MACSTRENGTH CONSTRUCTION
₱10.9MCompleted · 100%
Preventive maintenance-secondary roads -sen. gil puyat ave., (so3325lz) (roxas blvd to tripa de gallina bridge)
Roads and bridges · 2022 · JMK BUILDERS CONSTRUCTION
₱14.7MCompleted · 100%
Improvement of j. bocobo st. and vicinity, Malate
Roads and bridges · 2022 · YPR GEN. CONTRACTOR AND CONSTRUCTION SUPPLY INC. ([REVOKED] 45002)
₱4.8MCompleted · 100%
Basic infrastructure program (bip)- major strategic public buildings/facilities-structural and resilience program-rehab. of aurora quezon elementary school building/facilities, Brgy. 703
Schools · 2022 · AMETHYST HORIZON BUILDERS AND GEN. CONTRACTOR AND DEVELOPMENT CORP. ([REVOKED] 49129)
₱4.9MCompleted · 100%
Construction of drainage system (box culvert) along labores st., Pandacan
Flood control · 2022 · ST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196)
₱54.5MCompleted · 100%
Preventive maintenance-tertiary roads-muralla st., (so2801lz) (sta.lucia to plaza españa)
Roads and bridges · 2022 · BAO-IDANG CONSTRUCTION
₱9.6MCompleted · 100%
Convergence and special support program-basic infrastructure program (bip)-major/strategic public buildings/facilities-structural and resilience program-rehab. of aurora quezon elementary school, Malate
Schools · 2022 · SLHAV CONSTRUCTION
₱4.9MCompleted · 100%
Rehabilitation of multi-purpose building, Brgy. 890, Sta. ana
Buildings · 2022 · KPGONZALES CONSTRUCTION SUPPLY AND TRADING
₱4.9MCompleted · 100%
Const. of road including drainage impv't. of b
Roads and bridges · 2022 · SLHAV CONSTRUCTION
₱4.9MCompleted · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
FLORDES CONSTRUCTION & TRADING CORP.95 projects · ₱2.82B
2
EIGHT J'S CONSTRUCTION SERVICES73 projects · ₱5.03B
3
JMK BUILDERS CONSTRUCTION67 projects · ₱695.0M
4
JELSIE CONSTRUCTION & SUPPLY64 projects · ₱4.17B
5
N.M.E. CONSTRUCTION62 projects · ₱506.9M