National projects

Built by DPWH in Santa Cruz since 2016.

201projects
₱6.10Bin all
30ongoing
3slow
  • Roads and bridges ₱4.01B
  • Flood control ₱660.4M
  • Schools ₱502.0M
  • Buildings ₱490.1M
  • Other ₱406.6M
  • Water ₱31.8M

Showing 61 to 90 of 201

Concreting of quiawit road to demo farm fmr Roads and bridges · 2023 · MARK ANTHONY CONSTRUCTION & SUPPLY
₱49.8MCompleted · 100%
₱67.5MCompleted · 100%
Construction of multi- purpose building(function hall) Buildings · 2023 · VIBRANIUM BUILDERS CORPORATION
₱19.8MCompleted · 100%
₱14.8MCompleted · 100%
Construction of marawer-pogpog road Roads and bridges · 2023 · TKS BUILDERS & SUPPLIES
₱99.0MCompleted · 100%
Construction of multi-purpose building, Barangay zone iii, Poblacion Buildings · 2023 · HI-VIEW RESOURCES & DEVELOPMENT CORPORATION
₱5.0MCompleted · 100%
₱5.0MCompleted · 100%
Construction of flood mitigation structure, Pilan river Flood control · 2023 · DREIRICH BUILDERS / THREE W BUILDERS, INC.
₱62.7MCompleted · 100%
Construction of bato-matutungan-binaton road Roads and bridges · 2022 · H-ROYAL CONSTRUCTION
₱86.8MCompleted · 100%
₱4.8MCompleted · 100%
Construction of multi-purpose building (government center), Zone 3. sta. cruz Buildings · 2021 · VIBRANIUM BUILDERS CORPORATION
₱4.9MCompleted · 100%
Construction of multi-purpose building in brgy. poblacion Buildings · 2022 · SOUTH IRONROCK CORPORATION
₱5.9MCompleted · 100%
Construction of road from junction national highway barangay tuban to barangay sinoron Roads and bridges · 2022 · DREIRICH BUILDERS / THREE W BUILDERS, INC.
₱86.8MCompleted · 100%
₱4.9MCompleted · 100%
Construction of pedestrian overpass along davao-cotabato road, Coronon Roads and bridges · 2022 · ROSBILL CONSTRUCTION AND SUPPLY
₱24.5MCompleted · 100%
Construction of municipal drop center, Brgy. zone 3 Buildings · 2021 · VIBRANIUM BUILDERS CORPORATION
₱4.9MCompleted · 100%
Construction of pedestrian overpass along davao-cotabato road, Brgy. tuban Roads and bridges · 2022 · ROSBILL CONSTRUCTION AND SUPPLY
₱24.5MCompleted · 100%
₱24.5MCompleted · 100%
₱5.0MCompleted · 100%
₱4.9MCompleted · 100%
Construction of revetment along coronon river Flood control · 2022 · DREIRICH BUILDERS / THREE W BUILDERS, INC.
₱49.0MCompleted · 100%
₱2.0MCompleted · 100%
Construction of water system level ii, Barangay darong Water · 2021 · TWO DEGREES CONSTRUCTION AND SUPPLY
₱3.0MCompleted · 100%
₱17.7MCompleted · 100%
Construction of multi-purpose building, Government center Buildings · 2021 · VIBRANIUM BUILDERS CORPORATION
₱4.9MCompleted · 100%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Santa Cruz since 2016.

1
LTB BUILDERS & CONSTRUCTION18 projects · ₱167.1M
2
VIBRANIUM BUILDERS CORPORATION17 projects · ₱167.7M
3
LEAMOR CONSTRUCTION AND SUPPLY10 projects · ₱50.3M
4
TWO DEGREES CONSTRUCTION AND SUPPLY9 projects · ₱44.7M
5
MARK ANTHONY CONSTRUCTION & SUPPLY8 projects · ₱210.1M

See something wrong?

A project that looks finished on paper but not on the ground, or work that stopped. Post a photo on the Talk board, or report it to DPWH on the project's own page.

Post on Talk →