Naawan: Government

Municipality in Misamis Oriental, Northern Mindanao, Mindanao · 10 barangays

Town hall contracts

Construction contracts the town hall of Naawan awarded and posted on PhilGEPS.

32projects
₱359.0Min all
  • Roads and bridges ₱308.7M
  • Buildings ₱20.0M
  • Water ₱18.4M
  • Other ₱11.8M

The last construction award Naawan posted on PhilGEPS is from April 2024. A town has to post every award, so the list below is likely not all of its work. The town's own reports are in "Town hall papers".

All

Showing 1 to 30 of 32

Concreting of barangay maputi, Naawan fmr phase ii Roads and bridges · 2024 · ACG CONSTRUCTION
₱2.0M
Rehabilitation and improvement – simanoc, Linangkayan to don pedro Roads and bridges · 2023 · SILVER CONSTRUCTION
₱4.0M
Rehabilitation and improvement (purok 8, Brgy. maputi) Roads and bridges · 2023 · TESAR BUILDERS
₱2.0M
Construction of dairy post/harvest facility Buildings · 2023 · JIZAN BUILDERS
₱3.0M
Construction of dairy production center (cattle) Buildings · 2023 · MG & M CONSTRUCTION AND SUPPLIES
₱2.4M
Concreting of farm to market road at sitio sua, Purok 2 to purok 1b, Lubilan, Mis. or. Roads and bridges · 2023 · MG & M CONSTRUCTION AND SUPPLIES
₱3.4M
Construction of mapulog-tuboran fmr with arch bridges Roads and bridges · 2022 · JEJOR'S CONSTRUCTION CORPORATION
₱85.6M
Construction of dairy production center (buffalo) Buildings · 2022 · 4JY'S CONSTRUCTION SERVICES
₱2.4M
Concreting from magsaysay street, Poblacion to new municipal hall Roads and bridges · 2022 · 8 PILLARS CONSTRUCTION AND GENERAL MERCHANDISE CORPORATION
₱15.0M
Construction of chapel and concrete vault type burial structure Buildings · 2022 · ALFAHAD BUILDERS AND ENTERPRISES
₱2.0M
Construction of multi-purpose building including site development, Access roads and landscaping (design and build scheme) Roads and bridges · 2021 · JEJOR'S CONSTRUCTION CORPORATION
₱123.4M
Concreting of simanoc farm to market road Roads and bridges · 2021 · 8 PILLARS CONSTRUCTION AND GENERAL MERCHANDISE CORPORATION
₱8.0M
Rehabilitation and improvement Buildings · 2020 · SONFER CONSTRUCTION
₱1.8M
Rehabilitation & improvement/development Other · 2020 · DICON BUILDERS CORPORATION
₱5.0M
Construction of material recovery facility (11 units) Buildings · 2020 · 4JY'S CONSTRUCTION SERVICES
₱500K
Concreting of maputi-tuboran farm to market road Roads and bridges · 2020 · MG & M CONSTRUCTION AND SUPPLIES
₱6.0M
Construction of slaughter house Other · 2019 · DICON BUILDERS CORPORATION
₱2.5M
Construction of materials recovery facility at every barangay (11 units) Buildings · 2019 · 4JY'S CONSTRUCTION SERVICES
₱500K
Construction of materials recovery facility Buildings · 2019 · 4JY'S CONSTRUCTION SERVICES
₱550K
Concreting (marcelo h del pilar st.) Roads and bridges · 2019 · 4JY'S CONSTRUCTION SERVICES
₱2.4M
Construction of local access road at barangay don pedro Roads and bridges · 2019 · EIGHTEEN BUILDERS & ENTERPRISES
₱6.2M
Construction of mat-i reservoir and installation of distribution pipe Other · 2019 · AJD CONSTRUCTION AND SUPPLY
₱4.1M
Construction of early child care and development (eccd) building at macabagla, Mat-i Buildings · 2019 · AJD CONSTRUCTION AND SUPPLY
₱799K
Concreting of road to barangay maputi, Tuboran, Mapulog Roads and bridges · 2019 · 8 PILLARS CONSTRUCTION AND GENERAL MERCHANDISE
₱5.0M
Construction of local access road Roads and bridges · 2018 · 8 PILLARS CONSTRUCTION AND GENERAL MERCHANDISE
₱13.7M
Construction of naawan level iii water supply augmentation phase ii Water · 2018 · AJD CONSTRUCTION AND SUPPLY
₱18.4M
Construction of national child development center Buildings · 2017 · GIMPAB ENTERPRISES
₱2.3M
Constrcution of rain shelter Other · 2017 · JEJOR'S CONSTRUCTION CORPORATION
₱280K
Construction of solar dryer & storage facility Buildings · 2017 · L&L CONSTRUCTION
₱999K
Construction of community fish landing center Buildings · 2016 · FGW CONSTRUCTION CORPORATION
₱2.7M

Source: PhilGEPS award notices, from the BetterGov.ph open data (CC0).

Town hall papers

Not every project is on PhilGEPS. These are the town's own reports.

1
Budget and 20% development fundDILG Full Disclosure Policy portal
2
Audit reportsCommission on Audit

See something wrong?

A project that looks finished on paper but not on the ground, or work that stopped. Post a photo on the Talk board.

Post on Talk →