National projects
164projects
₱3.90Bin all
3ongoing
0slow
- Roads and bridges ₱2.60B
- Flood control ₱849.3M
- Buildings ₱265.1M
- Schools ₱144.5M
- Water ₱39.3M
Construction of concrete bridge -doroluman-president roxas-kadingilan road, Cotabato (north cotabato) phase ii, Sta 0+990 - sta 1+098, North cotabato
Roads and bridges · 2024 · JARGON CONSTRUCTION & SUPPLY
₱26.0MOn-Going · 100%
Construction of flood mitigation structure along tinanan river, Package 3, Barangay malibatuan
Flood control · 2025 · RAKKI CORPORATION / RELY CONSTRUCTION & SUPPLY INC.
₱112.3MOn-Going · 95%
Construction of flood mitigation structure along tinanan river, Package 1, Barangay malibatuan
Flood control · 2025 · P.L. SEBASTIAN CONSTRUCTION, INC.
₱93.6MOn-Going · 94%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
Who builds here
1
LLABAN CONSTRUCTION & SUPPLY17 projects · ₱365.1M
2
JARGON CONSTRUCTION & SUPPLY16 projects · ₱534.4M
3
VERGUZ CONSTRUCTION13 projects · ₱8.7M
4
SHEPPERD CONSTRUCTION AND SUPPLY8 projects · ₱47.4M
5
P.L. SEBASTIAN CONSTRUCTION, INC.7 projects · ₱711.8M