DI
Diplahan: Government
Municipality in Zamboanga Sibugay, Zamboanga, Mindanao · 22 barangays
National projects
191projects
₱5.12Bin all
51ongoing
6slow
- Roads and bridges ₱2.46B
- Flood control ₱2.08B
- Buildings ₱313.9M
- Schools ₱144.3M
- Water ₱94.3M
- Other ₱26.3M
Showing 121 to 133 of 133
Paving with drainage improvement at imelda-bayog-kumalarang-lapuyan-margosatubig road, K1751+(-602.00) to k1769+693.00 (intermittent sections), Zamboanga sibugay (1st deo)
Flood control · 2017 · GENETIAN BUILDERS AND ENTERPRISES INCORPORATED
₱87.8MCompleted · 100%
Construction of flood control along imelda-bayog-kumalarang-lapuyan-margosatubig road, Part of sibuguey river, (sta. 00+384 - sta.00+689.50), Barangay paradise, Zamboanga sibugay 1st ld
Flood control · 2017 · JAYKRIS ENTERPRISES & CONSTRUCTION
₱31.5MCompleted · 100%
Rehabilitation of flood control structure along imelda-bayog- kumalarang-lapuyan-margosatubig road, Part of sibuguey river, (k1763+219- k1763+497) barangay pilar, Zamboanqa sibugay 1st ld
Flood control · 2017 · RUDHIL CONSTRUCTION & ENTERPRISES, INC.
₱28.1MCompleted · 100%
Construction of flood control structure (revetment wall) along sibuguey river, (k00+002 - k00+384), Barangay paradise, Zamboanga sibugay1st ld
Flood control · 2017 · JAYKRIS ENTERPRISES & CONSTRUCTION
₱41.2MCompleted · 100%
Rehabilitation of flood control structure (revetment wall, K1763+663 - k1763+750) along imelda-bayog- kumalarang-lapuyan-margosatubig road, Barangay pilar, Zamboanga sibugay 1st ld
Flood control · 2017 · LAKEWOOD CONSTRUCTION COMPANY
₱9.3MCompleted · 100%
Rehabilitation of flood control structure (revetment wall) along sibuguey river, (k1763+497 to k1763+663), Barangay pilar, Zamboanga sibugay 1st ld
Flood control · 2017 · RUDHIL CONSTRUCTION & ENTERPRISES, INC.
₱17.2MCompleted · 100%
Construction of multi-purpose building in the municipalities of buug and diplahan
Buildings · 2017 · L.C. CONSTRUCTION CORPORATION
₱11.8MCompleted · 100%
Construction of two (2) units two (2) storey-eight (8) classroom school buildings at diplahan nhs
Schools · 2016 · DIPLAHAN COMMERCIAL AND CONSTRUCTION / RCDG CONSTRUCTION CORPORATION
₱21.1MCompleted · 100%
Construction of one (1) unit two (2) storey-eight (8) classroom school building at ditay nhs
Schools · 2016 · MJMARI BUILDERS AND DEVELOPMENT CORPORATION
₱10.5MCompleted · 100%
Concreting of barangay poblacion - gutas fmr, Brgy. poblacion
Roads and bridges · 2016 · DIPLAHAN COMMERCIAL AND CONSTRUCTION
₱9.9MCompleted · 100%
Construction of one (1) unit techvoc workshop building/laboratory for senior high school at diplahan nhs
Schools · 2016 · JAYKRIS ENTERPRISES & CONSTRUCTION
₱2.3MCompleted · 100%
Upgrading (unpaved to paved) of imelda - bayog - kumalarang - lapuyan - margosatubig road, K1766 + 160.00 to k1767 + 100.00; net length = 940.00 ln.m.
Flood control · 2016 · BADSBRO CONSTRUCTION AND GENERAL MERCHANDISE
₱59.1MCompleted · 100%
Concreting of rd. along imelda-bayog-kumalarang rd. (k1758+000-k1758+420), Z.s.
Roads and bridges · 2016 · MJMARI BUILDERS AND DEVELOPMENT CORPORATION
₱12.2MCompleted · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
RUDHIL CONSTRUCTION & ENTERPRISES, INC.19 projects · ₱1.10B
2
BADSBRO CONSTRUCTION AND GENERAL MERCHANDISE19 projects · ₱566.0M
3
DIPLAHAN COMMERCIAL AND CONSTRUCTION16 projects · ₱169.6M
4
KAYE-VENICE CONSTRUCTION16 projects · ₱85.3M
5
STONE THROW CONSTRUCTION & ENTERPRISES11 projects · ₱56.3M