Town hall contracts
194projects
₱278.0Min all
- Buildings ₱122.4M
- Roads and bridges ₱72.5M
- Other ₱38.5M
- Water ₱30.1M
- Flood control ₱11.5M
- Schools ₱3.0M
The last construction award Alcantara posted on PhilGEPS is from October 2025. A town has to post every award, so the list below is likely not all of its work. The town's own reports are in "Town hall papers".
Showing 31 to 60 of 194
Completion of multi purpose building / evacuation center at barangay candabong
Buildings · 2024 · NEW GLOBALDEV CORPORATION
₱499K
Completion of mpb/evacuation center at brgy. palanas, Polo, Cabil isan. candabong. cabadiangan, Salagmaya and manga
Buildings · 2024 · JUST CLICK INTEGRATED SOLUTION
₱560K
Construction/rehabilitation/improvement of alcantara boardwalk
Other · 2024 · JUST CLICK INTEGRATED SOLUTION
₱4.0M
Completion of legislative building
Buildings · 2024 · NEW GLOBALDEV CORPORATION
₱2.5M
Completion of multi purpose building / evacuation center at barangay poblacion
Buildings · 2024 · PJA CONSTRUCTION
₱500K
Completion of multi purpose building / evacuation center at barangay manga
Buildings · 2024 · PJA CONSTRUCTION
₱500K
Construction/rehabilitation/improvement of rural health unit building
Buildings · 2024 · JUST CLICK INTEGRATED SOLUTION
₱1.5M
Completion of multi purpose building / evacuation center at barangay cabadiangan
Buildings · 2024 · NEW GLOBALDEV CORPORATION
₱499K
Completion of multi purpose building / evacuation center at barangay salagmaya
Buildings · 2024 · NEW GLOBALDEV CORPORATION
₱499K
Completion of multi purpose building / evacuation center at barangay salagmaya
Buildings · 2024 · NEW GLOBALDEV CORPORATION
₱499K
Concreting project
Roads and bridges · 2024 · JUST CLICK INTEGRATED SOLUTION
₱2.0M
Rehabilitation and improvement of motorpool
Other · 2024 · JUST CLICK INTEGRATED SOLUTION
₱1,000K
Construction and rehabilitation of drainage system at barangay poblacion
Flood control · 2024 · JUST CLICK INTEGRATED SOLUTION
₱1,000K
Improvement of multi purpose hall ( fire exit & comfort room )
Buildings · 2024 · JUST CLICK INTEGRATED SOLUTION
₱227K
Construction/rehabilitation/improvement of foot bridge
Roads and bridges · 2024 · JUST CLICK INTEGRATED SOLUTION
₱239K
Restoration of roof and ceiling of multi purpose hall
Buildings · 2024 · PJA CONSTRUCTION
₱679K
Completion of evacuation center ( phase 1 )
Buildings · 2024 · NEW GLOBALDEV CORPORATION
₱519K
Rehabilitation and improvement of administrative hall
Buildings · 2024 · WARSKY VENTURES INC.
₱4.0M
Construction of drainage system
Flood control · 2024 · JUST CLICK INTEGRATED SOLUTION
₱999K
Completion of multi purpose building/evacuation center at brgy cabil isan
Buildings · 2024 · NEW GLOBALDEV CORPORATION
₱498K
Construction of concrete road at road 50 junction tim adams brgy polo
Roads and bridges · 2024 · JUST CLICK INTEGRATED SOLUTION
₱999K
Construction of concrete road at road 16 ( palanas-tawig-cabil isan )
Roads and bridges · 2024 · JUST CLICK INTEGRATED SOLUTION
₱2.0M
Construction/rehabilitation/improvement of admin hall building
Buildings · 2024 · WARSKY VENTURES INC.
₱2.0M
Construction/rehabilitation/improvement of boardwalk at brgy poblacion
Other · 2023 · JUST CLICK INTEGRATED SOLUTION
₱999K
Completion of multi purpose building / evacuation center at barangay polo
Buildings · 2023 · PJA CONSTRUCTION
₱500K
Completion of multi purpose building / evacuation center at barangay candabong
Buildings · 2023 · PJA CONSTRUCTION
₱500K
Completion of multi purpose building / evacuation center at barangay palanas
Buildings · 2023 · PJA CONSTRUCTION
₱500K
Completion of multi purpose building / evacuation center at barangay manga
Buildings · 2023 · PJA CONSTRUCTION
₱500K
Completion of multi purpose building/ evacuation center at barangay lawaan
Buildings · 2023 · WARSKY VENTURES INC.
₱500K
Completion of multi purpose building / evacuation center at barangay lawaan
Buildings · 2023 · WARSKY VENTURES INC.
₱500K
Source: PhilGEPS award notices, from the BetterGov.ph open data (CC0).
Town hall papers
1
Budget and 20% development fundDILG Full Disclosure Policy portal
2
Audit reportsCommission on Audit