National projects

Built by DPWH in Badian since 2016.

237projects
₱7.10Bin all
53ongoing
1slow
  • Roads and bridges ₱4.94B
  • Flood control ₱1.87B
  • Water ₱110.5M
  • Buildings ₱102.0M
  • Schools ₱80.1M

Showing 1 to 30 of 53

Construction (completion) of water system, Brgy. zaragoza Water · 2026 · A.C. TACULAD BUILDERS
₱3.0MOn-Going · 0%
Preventive maintenance - secondary roads, Santander-barili-toledo rd - k0184 + 355 - k0186 + 382 Roads and bridges · 2026 · WTG CONSTRUCTION & DEVELOPMENT CORPORATION
₱88.5MOn-Going · 30%
Construction of road leading to butong u Roads and bridges · 2025 · ADAMANT DEVELOPMENT CORPORATION / QM BUILDERS
₱38.4MOn-Going · 10%
Construction of alawijao-tubod road, Alawij Roads and bridges · 2025 · WTG CONSTRUCTION & DEVELOPMENT CORPORATION
₱48.0MOn-Going · 56%
Construction of sulsugan road, Sulsugan, B Roads and bridges · 2025 · QUIRANTE CONSTRUCTION CORPORATION
₱48.0MOn-Going · 23%
Preventive maintenance - secondary roads, Santander-barili-toledo rd - k0189+000 - k0190+000 Roads and bridges · 2025 · W.GO CONSTRUCTION AND SUPPLY / WTG CONSTRUCTION & DEVELOPMENT CORPORATION
₱94.5MOn-Going · 53%
₱145.5MOn-Going · 53%
Construction of road, Barangay sohoton - Roads and bridges · 2025 · QUIRANTE CONSTRUCTION CORPORATION
₱141.9MOn-Going · 52%
₱94.6MOn-Going · 28%
₱4.8MOn-Going · 48%
₱100.8MOn-Going · 100%
₱71.0MOn-Going · 100%
₱71.3MOn-Going · 100%
₱2.0MOn-Going · 100%
₱14.6MOn-Going · 100%
₱1.9MOn-Going · 100%
Construction of revetment wall along basak river (downstream right side), Badi Flood control · 2025 · VICTORIANO C. LIM CONSTRUCTION CORPORATION
₱49.0MOn-Going · 100%
₱1.9MOn-Going · 100%
₱1.9MOn-Going · 100%
Construction (completion) of water supply system, Barangay tiguib Water · 2025 · MACTAN ROCK INDUSTRIES, INC.
₱3.0MOn-Going · 28%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Badian since 2016.

1
QM BUILDERS64 projects · ₱3.84B
2
WORLDWIDE BUILDERS32 projects · ₱76.3M
3
DT&C CONSTRUCTION28 projects · ₱155.9M
4
FIRST GRANDEUR BUILDERS INC.27 projects · ₱245.7M
5
WTG CONSTRUCTION & DEVELOPMENT CORPORATION25 projects · ₱1.03B