BA
Babatngon: Government
Municipality in Leyte, Eastern Visayas, Visayas · 25 barangays
National projects
161projects
₱5.49Bin all
15ongoing
4slow
- Roads and bridges ₱4.38B
- Flood control ₱789.0M
- Schools ₱194.2M
- Buildings ₱133.9M
Showing 1 to 30 of 139
Construction of multi-purpose building, Barangay san isidro
Buildings · 2025 · 3A'S BUILDERS
₱4.9MCompleted · 100%
Construction of flood control structure along rizal bridge (downstream), Barangay rizal
Flood control · 2025 · JGO BUILDERS INC.
₱96.4MCompleted · 100%
Rehabilitation/reconstruction/upgrading of damaged paved roads - tertiary roads - bagahupi-babatngon-sta cruz-barugo-carigara rd - k0923 + 150 - k0923 + 550
Roads and bridges · 2025 · JDR CONSTRUCTION
₱14.7MCompleted · 100%
Construction (completion) of multi-purpose building, Barangay pagsulhugon
Buildings · 2025 · Z.A.S. CONSTRUCTION AND SUPPLY
₱2.5MCompleted · 100%
Rehabilitation/reconstruction of roads with slips, Slope collapse, And landslide - tertiary roads - bagahupi-babatngon-sta. cruz-barugo-carigara road, K0918+000 - k0920+000
Flood control · 2024 · ALPHAHAWK CONSTRUCTION CORP. / JFR CONSTRUCTION INC.
₱49.0MCompleted · 100%
Construction of 1 unit 2-storey 6-classroom school building in juan s. tismo national high school
Schools · 2024 · B. VICENCIO BUILDERS (BVB), INC.
₱15.4MCompleted · 100%
Construction of multi-purpose building, Barangay pagsulhugon
Buildings · 2024 · PAFJ CONSTRUCTION AND SUPPLY, INC.
₱4.9MCompleted · 100%
Const. of flood control structure along busay river, Brgy. district iii
Flood control · 2024 · GO_SOLID BUILDERS INC.
₱49.5MCompleted · 100%
Construction of road, Brgy.taguite to brgy. magcasuang
Roads and bridges · 2023 · LEDA CONSTRUCTION INCORPORATED
₱23.8MCompleted · 100%
Construction of flood control structure along magsalangi river (downstream), Brgy. district i
Flood control · 2023 · GO_SOLID BUILDERS INC. / LUG KONSTRACT, INC.
₱48.2MCompleted · 100%
Construction of multi-purpose building (evacuation center), Brgy. gov. e jaro
Buildings · 2024 · QUELLING CONSTRUCTION
₱4.9MCompleted · 100%
Construction of multi-purpose building (covered court), Gov.e. jaro elementary school, Barangay gov. e. jaro
Schools · 2024 · QUELLING CONSTRUCTION
₱6.9MCompleted · 100%
Construction of road, Pagsulhugon to badlas, Brgy. pasulhugon
Roads and bridges · 2024 · B Y A BUILDERS & CONSTRUCTION SUPPLY
₱9.9MCompleted · 100%
Rehabilitation/reconstruction of roads with slips, Slope collapse and landslide - tertiary roads - bagahupi - babatngon - sta cruz - barugo - carigara rd. - (s00066lt) k0927+(-348) - k0927+(-310), Leyte 1st ld
Roads and bridges · 2023 · AICON INDUSTRIES / PABLO S. LABASBAS CONSTRUCTION CORPORATION
₱101.2MCompleted · 100%
Construction of 1-unit 2cl school building, Emeterio-federica gerez national high school
Schools · 2023 · K.M. GOLONG CONSTRUCTION
₱5.0MCompleted · 100%
Construction of 1-unit 2cl school building, Pagsulhugon national high school
Schools · 2023 · B Y A BUILDERS & CONSTRUCTION SUPPLY
₱5.0MCompleted · 100%
Concreting of brgy. district iii to sitio tabang fmr, Brgy. district iii
Roads and bridges · 2023 · HARDLINE BUILDERS AND SALES
₱12.4MCompleted · 100%
Concreting of brgy. taguite to brgy. magcasuang fmr (phase iii), Brgy. taguite to brgy. magcasuang
Roads and bridges · 2023 · JANVIKE CONSTRUCTION AND SUPPLY
₱24.8MCompleted · 100%
Concreting of brgy. pagsulhugon fmr, Brgy. pagsulhugon
Roads and bridges · 2023 · GO_SOLID BUILDERS INC.
₱24.8MCompleted · 100%
Rehabilitation/reconstruction of roads with slips, Slope collapse and landslide - tertiary roads - bagahupi - babatngon - sta. cruz - barugo - carigara rd. - k0922+805 - k0923+011, Leyte 1st ld; & 2. asset preservation
Roads and bridges · 2023 · EZJONES CONSTRUCTION INC.
₱236.4MCompleted · 100%
Widening of permanent bridges - rizal bridge (b00059lt) along bagahupi-babatngon-sta. cruz-barugo-carigara road
Roads and bridges · 2023 · AICON INDUSTRIES / CTC BUILDER AND SUPPLIES INCORPORATED (FOR. CTC BU
₱52.9MCompleted · 100%
Concreting of brgy. bagong silang to zone 7 fmr, Brgy. bagong silang
Roads and bridges · 2023 · MAGA CONSTRUCTION AND SUPPLIES INC.
₱12.2MCompleted · 100%
Rehabilitation/reconstruction of roads with slips, Slope collapse and landslide - tertiary roads - bagahupi - babatngon - sta. cruz - barugo - carigara rd. - (s00066lt) k0927+058 - k0927+098, . . . and other 1 project
Roads and bridges · 2023 · EZJONES CONSTRUCTION INC.
₱279.8MCompleted · 100%
Rehabilitation/reconstruction of roads with slips, Slope collapse and landslide - tertiary roads - bagahupi - babatngon - sta. cruz - barugo - carigara rd. - (s00066lt) k097+(-310) - k0927+(-252), Leyte 1st ld
Roads and bridges · 2023 · AICON INDUSTRIES / CTC BUILDER AND SUPPLIES INCORPORATED (FOR. CTC BU
₱96.3MCompleted · 100%
Rehabilitation/reconstruction of roads with slips, Slope collaspe and landslide-tertiary roads-bagahupi-babatngon-sta. cruz-barugo-carigara rd. (s00066lt) k0927+923-k0928+023, K0928+073-k0925+153, Leyte 1st ld. 2. asset preservation-
Roads and bridges · 2023 · EZJONES CONSTRUCTION INC.
₱304.0MCompleted · 100%
Rehabilitation/reconstruction of roads with slips, Slope collapse and landslide - tertiary roads - bagahupi - babatngon - sta. cruz - barugo - carigara rd. - (s00066lt) k0927+173 - k0927+193, K0927+228 - k0927+283, K0928+236 - k0928+3
Roads and bridges · 2023 · EZJONES CONSTRUCTION INC.
₱154.4MCompleted · 100%
Rehabilitation/reconstruction of roads with slips, Slope collapse and landslide - tertiary roads - bagahupi - babatngon - sta. cruz - barugo - carigara rd. - k0924+060 - k0924+190, Leyte 1st ld; 2. asset preservation - r
Roads and bridges · 2023 · EZJONES CONSTRUCTION INC.
₱289.5MCompleted · 100%
Rehabilitation/reconstruction of roads with slips, Slope collapse and landslide - tertiary roads - bagahupi - babatngon - sta. cruz - barugo - carigara rd., K0928+314 - k0928+341, K0928+368 - k0928+442, Leyte 1st ld
Roads and bridges · 2023 · EZJONES CONSTRUCTION INC.
₱193.0MCompleted · 100%
Rehabilitation/reconstruction of roads with slips, Slope collapse and landslide - tertiary roads - bagahupi - babatngon - sta. cruz - barugo - carigara rd., - (s00066lt) k0928+442 - k0928+500, K0928+571 - k0928+673; 2.
Roads and bridges · 2023 · EZJONES CONSTRUCTION INC.
₱245.1MCompleted · 100%
Rehabilitation/reconstruction of roads with slips, Slope collapse and landslide - tertiary roads - bagahupi - babatngon - sta. cruz - barugo - carigara rd., K0916+494 - k0916+580, Leyte 1st ld
Roads and bridges · 2023 · EZJONES CONSTRUCTION INC.
₱82.9MCompleted · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
EZJONES CONSTRUCTION INC.16 projects · ₱2.60B
2
VHITS D. G. BUILDERS & ENTERPRISES10 projects · ₱47.5M
3
JGO BUILDERS INC.7 projects · ₱374.9M
4
GO_SOLID BUILDERS INC.6 projects · ₱162.1M
5
B. VICENCIO BUILDERS (BVB), INC.5 projects · ₱198.7M