National projects
61projects
₱824.2Min all
5ongoing
1slow
- Roads and bridges ₱417.8M
- Flood control ₱241.6M
- Buildings ₱104.1M
- Schools ₱51.0M
- Water ₱9.8M
Construction of jubasan bridge, Barangay jubasan
Roads and bridges · 2025 · AICON INDUSTRIES
₱24.5MOn-Going · 100%
Construction of can-angay bridge, Barangay can-angay
Roads and bridges · 2025 · LADY OF ASSUMPTION ENTERPRISES INC.
₱24.5MOn-Going · 92%
Construction of evacuation center, Barangay tinago
Buildings · 2024 · FOUR K BUILDERS AND CONSTRUCTION SUPPLIES
₱43.4MOn-Going · 0%Slow
Construction of road leading to santilmohan water spring, Barangay caminto
Roads and bridges · 2024 · FOUR K BUILDERS AND CONSTRUCTION SUPPLIES
₱24.1MOn-Going · 100%
Construction of retaining wall at the reclamation area of sto. rosario st. brgy. poblacion
Flood control · 2023 · JDR CONSTRUCTION
₱22.7MOn-Going · 83%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
JDR CONSTRUCTION12 projects · ₱81.7M
2
RJIR ENTERPRISES CORPORATION7 projects · ₱45.8M
3
C N E CONSTRUCTION6 projects · ₱111.4M
4
V. JYN ENTERPRISES5 projects · ₱24.4M
5
GREAT WALL BUILDERS4 projects · ₱19.5M