KA
Kananga: Government
Municipality in Leyte, Eastern Visayas, Visayas · 23 barangays
National projects
162projects
₱4.46Bin all
10ongoing
0slow
- Roads and bridges ₱2.70B
- Flood control ₱1.26B
- Water ₱283.4M
- Schools ₱131.3M
- Buildings ₱83.3M
Rehabilitation of public water supply system, Barangay masarayao
Water · 2026 · RJIR ENTERPRISES CORPORATION
₱47.0MOn-Going · 41%
Construction of canawagan flood control (upstream) poblacion and brgy. natubgan
Flood control · 2025 · LEDA CONSTRUCTION INCORPORATED
₱96.4MOn-Going · 100%
Rehabilitation/reconstruction/upgrading of damaged paved roads - tertiary roads - libungao - matag-ob - palompon rd - k0995+580 - k0996+128.1, K0996+172 - k0996+673.5, K0996+700 - k0996+980, K0998+518 - k0998+993
Roads and bridges · 2025 · RJIR ENTERPRISES CORPORATION
₱33.4MOn-Going · 100%
Rehabilitation/reconstruction of roads with slips, Slope collapse, And landslide - primary roads - palo - carigara - ormoc rd - k0984+(-361.4)-k0984+(-264), K0984+088 - k0984+238, K0985+063 - k0985+160, K0985+774 - k0985+800, K0989+645 - k0989+705, K0990+
Roads and bridges · 2025 · JM COLLERA KONSTRACT
₱19.5MOn-Going · 100%
Construction of santo niño flood control structure, Barangay santo niño
Flood control · 2025 · RJIR ENTERPRISES CORPORATION
₱96.0MOn-Going · 100%
Construction of tugbong flood control (downstream) barangay tugbong
Flood control · 2025 · LEDA CONSTRUCTION INCORPORATED
₱96.4MOn-Going · 98%
Construction of natubgan flood control (downstream) barangay natubgan
Flood control · 2025 · LEDA CONSTRUCTION INCORPORATED
₱96.4MOn-Going · 98%
Repair/rehabilitation/improvement of existing cross drain & drainage system structure along palo - carigara - ormoc road - k0988+588 - k0989+073
Flood control · 2024 · RJIR ENTERPRISES CORPORATION
₱19.2MOn-Going · 0%
Construction of multi-purpose building, Poblacion
Buildings · 2024 · RJIR ENTERPRISES CORPORATION
₱49.4MOn-Going · 78%
Rehabilitation/reconstruction of national roads with slips, Slope collapse and landslide - tertiary roads - kananga - tungonan hot spring rd. - k0996+306 - k0996+416, K0996+432 - k0996+484, K0996+609 - k0996+719, ....... leyte 4th ld
Roads and bridges · 2021 · RJIR ENTERPRISES CORPORATION
₱100.7MOn-Going · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
Who builds here
1
RJIR ENTERPRISES CORPORATION54 projects · ₱1.49B
2
LEDA CONSTRUCTION INCORPORATED11 projects · ₱795.1M
3
CIRCLE Z VENTURES & DEVELOPMENT CORP.9 projects · ₱72.7M
4
GMP BUILDERS9 projects · ₱39.6M
5
MAC BUILDERS CORP.8 projects · ₱302.5M