San Sebastian: Government
Municipality in Samar, Eastern Visayas, Visayas · 14 barangays
National projects
17projects
₱443.7Min all
8ongoing
1slow
- Flood control ₱275.8M
- Roads and bridges ₱106.7M
- Schools ₱32.5M
- Buildings ₱28.8M
Const./maint. of flood mitigation structures and drainage systems-const. of flood control structure, Bulacan bridge, Sta. 0+000.00 - sta. 0+116.29, Brgy. canduyocan
Flood control · 2025 · JFR CONSTRUCTION INC.
₱52.5MOn-Going · 97%
Lgu hospitals - san sebastian district hospital, Occidental mindoro
Buildings · 2024 · MIGHTY DRAGON BUILDERS INC.
₱28.8MOn-Going · 41%Slow
Const. of flood control bucalan bridge, Barangay canduyocan
Flood control · 2024 · JFR CONSTRUCTION INC.
₱96.4MOn-Going · 99%
Construction of road, Barangay dolores-barangay hitaasan, Samar- sta. 0+000-sta. 0+293, Sta. 0+302-sta. 0+991, Sta. 1+367-sta. 2+055
Roads and bridges · 2024 · ETAN CONSTRUCTION
₱29.3MOn-Going · 100%
Const. of standard 1- storey 3 classroom school building, San sebastian ces
Schools · 2023 · ETAN CONSTRUCTION
₱6.6MOn-Going · 99%
Construction of modified design with parapet 1-storey, 2-cl. school building, Inobongan integrated school
Schools · 2022 · PYUKEI CONSTRUCTION INC.
₱5.0MOn-Going · 100%
Construction of road, Brgy. camanhagay - brgy. dolores, San sebantian
Roads and bridges · 2022 · ETAN CONSTRUCTION
₱9.9MOn-Going · 79%
Widening of permanent bridges, Balugo bridge along daang maharlika
Roads and bridges · 2018 · FRD CONSTRUCTION
₱27.1MOn-Going · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
ETAN CONSTRUCTION5 projects · ₱85.0M
2
JFR CONSTRUCTION INC.4 projects · ₱200.3M
3
A.C. RIVERO DEVELOPMENT CORPORATION1 project · ₱49.4M
4
STEVEN CONSTRUCTION & SUPPLY1 project · ₱28.8M
5
MIGHTY DRAGON BUILDERS INC.1 project · ₱28.8M