National projects

Built by DPWH in Pulupandan since 2016.

47projects
₱1.14Bin all
8ongoing
0slow
  • Flood control ₱564.7M
  • Roads and bridges ₱330.7M
  • Other ₱197.9M
  • Schools ₱31.7M
  • Buildings ₱17.9M

Showing 1 to 30 of 47

₱19.8MOn-Going · 100%
₱74.2MOn-Going · 65%
₱98.9MOn-Going · 100%
Construction of shoreline protection along guimaras strait - brgy. zone 1 Other · 2025 · LEGACY CONSTRUCTION CORPORATION
₱98.9MOn-Going · 100%
Widening - secondary roads - jct. pulupandan - pulupandan pier road - k0026+259 - k0027+143 Roads and bridges · 2025 · LEGACY CONSTRUCTION CORPORATION
₱31.8MOn-Going · 90%
₱4.9MCompleted · 100%
Construction of flood mitigation structure along patic creek (phase 4), Barangay patic Flood control · 2024 · GROUND UP CONSTRUCTION AND SUPPLIES
₱48.5MCompleted · 100%
Construction of road with slope protection structure, Brgy. culo - brgy. tapong Roads and bridges · 2024 · GROUND UP CONSTRUCTION AND SUPPLIES
₱24.5MCompleted · 100%
₱49.0MCompleted · 100%
Construction of flood mitigation structure along patic creek (phase 3), Barangay patic Flood control · 2024 · GROUND UP CONSTRUCTION AND SUPPLIES
₱49.0MCompleted · 100%
Construction of road, Brgy. culo Roads and bridges · 2024 · GROUND UP CONSTRUCTION AND SUPPLIES
₱49.0MOn-Going · 100%
Construction of shoreline protection along patic creek, Brgy. utod Flood control · 2024 · GROUND UP CONSTRUCTION AND SUPPLIES
₱49.0MCompleted · 100%
₱61.9MOn-Going · 98%
₱96.4MCompleted · 100%
Preventive maintenance-primary roads-bacolod south road-k0024+(-036)-k0024+331 Roads and bridges · 2024 · HOMEWORLD CONSTRUCTION CORP.
₱13.3MOn-Going · 100%
₱99.0MCompleted · 100%
Construction of access road, Brgy. ubay Roads and bridges · 2023 · EJJ CONSTRUCTION AND SUPPLY
₱9.8MCompleted · 100%
₱49.5MCompleted · 100%
₱2.9MCompleted · 100%
Concreting of road, Brgy. culo Roads and bridges · 2021 · EZ GOLD CONSTRUCTION & SUPPLY
₱19.0MCompleted · 100%
Construction of multi-purpose building (covered court), Barangay zone 2 Buildings · 2021 · EZ GOLD CONSTRUCTION & SUPPLY
₱2.9MCompleted · 100%
₱1.6MCompleted · 100%
₱485KCompleted · 100%
₱9.6MCompleted · 100%
₱485KCompleted · 100%
Rehabilitation completion of multi-purpose building, Brgy. culo Buildings · 2019 · JAIME B. CHING ENTERPRISES
₱485KCompleted · 100%
₱485KCompleted · 100%
₱485KCompleted · 100%
Construction of flood mitigation structures along patik creek Flood control · 2019 · JAIME B. CHING ENTERPRISES
₱30.3MCompleted · 100%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

Who builds here

Contractors with the most projects in Pulupandan since 2016.

1
SILVER DRAGON CONSTRUCTION & LUMBER & GLASS SUPPLY INC.10 projects · ₱59.2M
2
JAIME B. CHING ENTERPRISES9 projects · ₱98.7M
3
GROUND UP CONSTRUCTION AND SUPPLIES6 projects · ₱269.0M
4
EZ GOLD CONSTRUCTION & SUPPLY6 projects · ₱31.4M
5
LEGACY CONSTRUCTION CORPORATION5 projects · ₱323.7M