National projects
127projects
₱2.25Bin all
15ongoing
1slow
- Roads and bridges ₱979.8M
- Flood control ₱883.0M
- Buildings ₱254.7M
- Other ₱49.7M
- Water ₱42.2M
- Schools ₱35.8M
Showing 121 to 127 of 127
Const. of level ii water system, Brgy. santa cruz
Water · 2016 · AFG ZILLION CONSTRUCTION CORPORATION
₱1.9MCompleted · 100%
Const./rehab. of brgy. poblacion mpb
Buildings · 2016 · G.F. ROVERO MERCHANDISING
₱9.6MCompleted · 100%
Concreting of brgy. maloco fmr, Brgy. maloco
Roads and bridges · 2024
₱0For Procurement · 0%
Construction of road sta. 0 + 000 - sta. 0 + 380, Barangay regador
Roads and bridges · 2026
₱0For Procurement · 0%
Construction of 3-storey 6-classroom & 1-storey 2-classroom school building in maloco national high school, Brgy. maloco
Schools · 2024
₱0For Procurement · 0%
Concreting of brgy. mina-a fmr, Brgy. mina-a
Roads and bridges · 2024
₱0For Procurement · 0%
Concreting of brgy. tagbaya fmr, Brgy. tagbaya
Roads and bridges · 2024
₱0For Procurement · 0%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
BENZEN CONSTRUCTION18 projects · ₱62.7M
2
G.F. ROVERO MERCHANDISING14 projects · ₱173.3M
3
LEADCORE-CON INC.11 projects · ₱21.2M
4
NAGAMOS BUILDERS9 projects · ₱61.9M
5
SOLID MERCHANDISING8 projects · ₱99.3M