National projects

Built by DPWH in New Washington since 2016.

105projects
₱1.16Bin all
15ongoing
0slow
  • Flood control ₱493.9M
  • Roads and bridges ₱415.3M
  • Schools ₱141.8M
  • Buildings ₱97.7M
  • Water ₱9.7M

Showing 31 to 60 of 105

Rehabilitation of seawall sitio dumlog, Barangay tambak Flood control · 2023 · GREENLAND BUILDERS / MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC.
₱49.0MCompleted · 100%
Rehabilitation of mpb (public market) barangay poblacion Buildings · 2023 · GREENLAND BUILDERS
₱4.9MCompleted · 100%
Rehabilitation of seawall barangay poblacion Flood control · 2023 · GREENLAND BUILDERS / MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC.
₱72.4MCompleted · 100%
₱3.0MCompleted · 100%
Jaime cardinal sin avenue k0291+678 k0292+000, K0295+000 k0296+423 jaime cardinal sin avenue Roads and bridges · 2023 · IBC INTERNATIONAL BUILDERS CORPORATION
₱19.6MCompleted · 100%
₱4.9MCompleted · 100%
Widening - at specific locations along jaime cardinal sin ave (s00335pn) k0286+600 - k0287+595, (s00481pn) k0288+(-618) - k0290+493 Roads and bridges · 2022 · GREENLAND BUILDERS / ST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196)
₱172.8MCompleted · 100%
Construction (completion) of mpb (evacuation center) at brgy. dumaguit Buildings · 2022 · FIRST MAKEEN CONSTRUCTION
₱2.0MCompleted · 100%
Construction (completion) of mpb (evacuation center) at brgy. jugas Buildings · 2022 · FIRST MAKEEN CONSTRUCTION
₱2.0MCompleted · 100%
Construction (completion) of 2-storey of mpb brgy. poblacion Buildings · 2022 · FIRST MAKEEN CONSTRUCTION
₱2.0MCompleted · 100%
Construction of road at sitio maeabago & sitio kuntang to sitio bato brgy. ochando Roads and bridges · 2022 · FIRST MAKEEN CONSTRUCTION
₱4.9MCompleted · 100%
Construction of road at sitio eo-ok brgy. mabilo Roads and bridges · 2022 · FIRST MAKEEN CONSTRUCTION
₱4.9MCompleted · 100%
Construction of road at brgy. cawayan Roads and bridges · 2022 · FIRST MAKEEN CONSTRUCTION
₱4.9MCompleted · 100%
₱2.0MCompleted · 100%
₱4.9MCompleted · 100%
₱398KCompleted · 100%
Construction/completion of 2sty8cl candelaria nhs brgy. candelaria Buildings · 2021 · FIRST MAKEEN CONSTRUCTION
₱1.2MCompleted · 100%
Widening of jaime cardinal sin avenue k0284+075 - k0286+653 jaime cardinal sin avenue Roads and bridges · 2021 · ALPHA & OMEGA GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 38958)
₱47.1MCompleted · 100%
Construction of mpb (brgy. health center) sitio ilaya, Brgy. dumaguit Buildings · 2021 · FIRST MAKEEN CONSTRUCTION
₱2.0MCompleted · 100%
₱1.9MCompleted · 100%
Construction (continuing) of mpb (covered court) brgy. pinamuk-an Buildings · 2021 · FIRST MAKEEN CONSTRUCTION
₱2.0MCompleted · 100%
Construction of mpb (covered court) brgy. fatima Buildings · 2021 · FIRST MAKEEN CONSTRUCTION
₱1.9MCompleted · 100%
Construction of mpb (covered court) barangay polo Buildings · 2021 · FIRST MAKEEN CONSTRUCTION
₱1.5MCompleted · 100%
Concreting of road at sitio martabana brgy. poblacion Roads and bridges · 2021 · FIRST MAKEEN CONSTRUCTION
₱2.9MCompleted · 100%
₱9.6MCompleted · 100%
₱2.2MCompleted · 100%
Concreting of road barangay lawa-an Roads and bridges · 2021 · SLW8 BUILDERS
₱1.4MCompleted · 100%
Reconstruction of jaime cardinal sin avenue Roads and bridges · 2020 · FIRST MAKEEN CONSTRUCTION
₱6.0MCompleted · 100%
Const. of senior citizen bldg., In brgy. poblacion Buildings · 2020 · FIRST MAKEEN CONSTRUCTION
₱2.9MCompleted · 100%
Const. (completion) of multi-purpose covered court, Brgy. pinamuk-an Buildings · 2020 · FIRST MAKEEN CONSTRUCTION
₱1.9MCompleted · 100%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

Who builds here

Contractors with the most projects in New Washington since 2016.

1
FIRST MAKEEN CONSTRUCTION33 projects · ₱135.3M
2
GREENLAND BUILDERS18 projects · ₱137.7M
3
AUDRIC CONSTRUCTION & SUPPLY11 projects · ₱23.8M
4
G.F. ROVERO MERCHANDISING6 projects · ₱136.6M