530projects
₱22.67Bin all
228ongoing
47slow
- Flood control ₱9.59B
- Roads and bridges ₱7.63B
- Buildings ₱4.25B
- Schools ₱914.5M
- Water ₱240.1M
- Other ₱47.5M
Construction of by-pass and diversion roads-daraga urban tourism eco route project, Package 3, Albay (2nd legislative district)
Roads and bridges · 2025 · FEDERAL AGGREGATES AND DEVELOPMENT CORP.
₱26.9MOn-Going · 0%
Construction of by-pass and diversion roads-daraga urban tourism eco route project, Package 1, Albay (2nd legislative district)
Roads and bridges · 2025 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION / ST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196)
₱47.3MOn-Going · 0%
Construction of by-pass and diversion roads-daraga urban tourism eco route project, Package 2, Albay (2nd legislative district)
Roads and bridges · 2025 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION / ST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196)
₱47.3MOn-Going · 0%
Construction of dike, Barangay malobago
Flood control · 2025 · FS CO BUILDERS AND SUPPLY
₱96.5MOn-Going · 5%
Construction/improvement of access roads leading to access roads leading to trades, Industries and economic zones (roads leveraging linkagees for industry and trade infrastructure program - roll-it) - barangay cullat-bongalon-balinad road connecting
Roads and bridges · 2025 · ALDACU CONSTRUCTION SUPPLY
₱4.8MOn-Going · 18%
Construction of flood wall structure along burgos river, Barangay burgos
Flood control · 2025 · AJAN JEADA, INC.
₱57.6MOn-Going · 26%
Construction of flood wall structure along namantao river, Albay (2
Flood control · 2025 · AJAN JEADA, INC.
₱28.8MOn-Going · 37%
Construction of by-pass and diversion roads-daraga albay diversion road, Albay (2nd legislative district)
Roads and bridges · 2025 · FEDERAL AGGREGATES AND DEVELOPMENT CORP.
₱17.9MOn-Going · 33%
Construction of flood mitigation structure along miisi gully, Pac
Flood control · 2024 · SUNWEST, INC.
₱189.1MOn-Going · 0%
Construction of flood mitigation structure along miisi gully, Pac
Flood control · 2024 · SUNWEST, INC.
₱189.1MOn-Going · 4%
Preventive maintenance -primary roads - maharlika highway - k0524+188-k0524+481, K0526+000-k0526+522, Albay (2nd legislative district)
Roads and bridges · 2025 · QDC CONSTRUCTION AND SUPPLY
₱29.0MOn-Going · 74%
Preventive maintenance-primary roads-maharlika highway-k0528+460-k0528+771, K0539+000-k0539+285.5, Albay (2nd legislative district)
Roads and bridges · 2025 · QDC CONSTRUCTION AND SUPPLY
₱27.6MOn-Going · 75%
Construction/maintenance of flood mitigation structures and drainage systems-construction of cagsawa flood mitigation structure along tributaries of barangay budiao to barangay
Flood control · 2024 · CBC CONSTRUCTION AND SUPPLY INC.
₱93.6MOn-Going · 2%
Construction/maintenance of flood mitigation structures and drainage systems construction of dike, Package 1, Barangay malabog
Flood control · 2025 · MUNTOPAR BUILDERS CORP.
₱69.8MOn-Going · 24%
Construction/maintenance of flood mitigation structures and drainage systems -rehabilitation of budiao tributary river channel, Package 2, Budiao
Flood control · 2024 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION
₱70.2MOn-Going · 40%
Construction of 3 units, 1-storey 2-classroom school building and 1 units, 2-storey 2-classroom school building at legazpi city and daraga, Albay 1) construction of 1-storey 2-classroom school building at
Schools · 2024 · HI-TONE CONSTRUCTION & DEVELOPMENT CORP.
₱38.7MOn-Going · 8%
Construction of flood control dike, Budiaomiisi (package 1)
Flood control · 2024 · SUNWEST, INC.
₱140.3MOn-Going · 34%
Construction/maintenance of flood mitigation structures and drainage systems -construction of cagsawa flood mitigation structure along tributaries of barangay budiao to
Flood control · 2024 · 9LEAVES BUILDERS & SUPPLY CORP. / STEVEN CONSTRUCTION & SUPPLY
₱93.6MOn-Going · 70%
Construction of 3-storey 9-classroom school building at binitayan elementary school, Barangay binitayan
Schools · 2024 · HI-TONE CONSTRUCTION & DEVELOPMENT CORP. / KNJ CONSTRUCTION AND SUPPLY
₱48.3MOn-Going · 1%
Construction/maintenance of flood mitigation structures and drainage systems-rehabilitation of cagsawa dike along 'tributary b channel' river including groundsill, Package 3
Flood control · 2024 · MUNTOPAR BUILDERS CORP.
₱69.8MOn-Going · 20%
Construction/maintenance of flood mitigation structures and drainage systems-construction of cagsawa flood mitigation structure along tributaries of barangay budiao
Flood control · 2024 · ALHADRAX CONSTRUCTION AND SUPPLY / MUNTOPAR BUILDERS CORP.
₱93.1MOn-Going · 25%
Construction/maintenance of flood mitigation structures and drainage systems - construction of flood mitigation structure and drainage system tributaries to yawa river
Flood control · 2024 · RCDS CONSTRUCTION & SUPPLY, INC.(FOR RCDS CONST.
₱93.6MOn-Going · 5%
Construction of bigao to sitio banasian, San ramon
Roads and bridges · 2024 · FIRST OMB CONSTRUCTION AND DEVELOPMENT CORP.
₱65.5MOn-Going · 43%
Construction of road including drainage system, Bagumbayan
Roads and bridges · 2024 · FIRST OMB CONSTRUCTION AND DEVELOPMENT CORP.
₱14.0MOn-Going · 99%
Concreting of brgy. kidaco - brgy. san roque fmr
Roads and bridges · 2024 · HI-TONE CONSTRUCTION & DEVELOPMENT CORP.
₱44.3MOn-Going · 35%
Construction of new bridges - siargao br. along sn pascual-claveria rd.
Roads and bridges · 2025 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION / ST. TIMOTHY CONSTRUCTION CORPORATION ([REVOKED] 39196)
₱56.2MOn-Going · 4%
Construction of road, Barangay maopi to barangay magogon, Alb
Roads and bridges · 2025 · HI-TONE CONSTRUCTION & DEVELOPMENT CORP.
₱57.3MOn-Going · 76%
Construction of flood mitigation structure along miisi gully, Pac
Flood control · 2024 · SUNWEST, INC.
₱189.0MOn-Going · 0%
Construction of 10-storey accountancy building, Phase 1, Bicol university, Albay - bicol university
Buildings · 2024 · SCHEIRMAN CONSTRUCTION CONSOLIDATED INC.
₱162.5MOn-Going · 0%
Construction of lahar mitigation dike along budiao-miisi river, Package 1, Barangay budiao and barangay miisi
Flood control · 2025 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION
₱48.0MOn-Going · 78%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
HI-TONE CONSTRUCTION & DEVELOPMENT CORP.52 projects · ₱2.74B
2
NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION51 projects · ₱1.64B
3
SUNWEST, INC.35 projects · ₱3.33B
4
NUMERICAL GATE CONSTRUCTION & SUPPLY CORPORATION25 projects · ₱987.3M
5
CBC CONSTRUCTION AND SUPPLY INC.17 projects · ₱353.7M