Concreting of obra street to quirat road, Brgy. rizal Roads and bridges · 2020 · V.B. MANUBAY CONSTRUCTION
₱9.7MCompleted · 100%
Concreting of brgy. ramos east fmr Roads and bridges · 2020 · V.B. MANUBAY CONSTRUCTION
₱9.8MCompleted · 100%
Concreting of brgy. libertad to brgy. sta. ana fmr Roads and bridges · 2020 · V.B. MANUBAY CONSTRUCTION
₱9.8MCompleted · 100%
Concreting of brgy. babaran fmr Roads and bridges · 2020 · DALCON CONSTRUCTION
₱9.7MCompleted · 100%
Construction of by-pass and diversion roads - santiago circumferential road Roads and bridges · 2021 · C.R. DOMINGO CONSTRUCTION AND POWER DEVELOPMENT, INC. (FOR. C.R. DOMINGO CONSTRUCTION, INC.)
₱104.5MCompleted · 100%
₱42.2MCompleted · 100%
₱3.0MCompleted · 100%
Construction of multi-purpose building phase ii, Barangay rosario Buildings · 2021 · V.B. MANUBAY CONSTRUCTION
₱9.6MCompleted · 100%
₱4.0MCompleted · 100%
₱3.0MCompleted · 100%
Concreting of local road, Barangay malvar Roads and bridges · 2021 · V.B. MANUBAY CONSTRUCTION
₱8.6MCompleted · 100%
Construction of multi-purpose building, Luna elementary school Schools · 2021 · V.B. MANUBAY CONSTRUCTION
₱3.0MCompleted · 100%
₱1.5MCompleted · 100%
₱1.5MCompleted · 100%
₱3.0MCompleted · 100%
Construction of multi-purpose building, Sicat tesda, Barangay calaocan Buildings · 2021 · V.B. MANUBAY CONSTRUCTION
₱2.5MCompleted · 100%
Construction of local road, Barangay rizal Roads and bridges · 2021 · NTL BUILDERS AND DEVELOPER
₱5.0MCompleted · 100%
Concreting of local road, Barangay calao east Roads and bridges · 2021 · V.B. MANUBAY CONSTRUCTION
₱4.2MCompleted · 100%
Rehabilitation of flood control/drainage, Barangay victory norte Flood control · 2021 · NTL BUILDERS AND DEVELOPER
₱2.0MCompleted · 100%
₱2.5MCompleted · 100%
₱7.2MCompleted · 100%
Construction of multi-purpose building - brgy. calaocan Buildings · 2020 · V.B. MANUBAY CONSTRUCTION
₱1.5MCompleted · 100%
Construction of multi-purpose building, Brgy. batal Buildings · 2020 · V.B. MANUBAY CONSTRUCTION
₱4.9MCompleted · 100%
Construction/rehabilitation of multi-purpose building, Brgy. sinili Buildings · 2020 · MONTE CARLO CONST. CORP.
₱2.0MCompleted · 100%
₱990KCompleted · 100%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Santiago City since 2016.

1
V.B. MANUBAY CONSTRUCTION50 projects · ₱782.7M
2
NTL BUILDERS AND DEVELOPER42 projects · ₱1.02B
3
CASAN CONSTRUCTION AND TRADING19 projects · ₱91.6M
4
VBM CONSTRUCTION CORP.15 projects · ₱92.0M
5
MONTE CARLO CONST. CORP.14 projects · ₱37.0M

See something wrong?

A project that looks finished on paper but not on the ground, or work that stopped. Post a photo on the Talk board, or report it to DPWH on the project's own page.

Post on Talk →