National projects
97projects
₱1.96Bin all
16ongoing
1slow
- Roads and bridges ₱1.45B
- Buildings ₱262.2M
- Flood control ₱174.4M
- Schools ₱68.2M
- Water ₱4.3M
Showing 91 to 97 of 97
Preventive maint. secondary rds along pal-bal-bats rd.k0096+000-k0096+289, K0096+327-k0096+642, K0107+760-k0107+827, K0107+863-k0108+000, K0119+000-k0119+125, K0120+137-k0121+000, K0122+000-k0122+236.50, K0127+000-k0127+610, K0131+673.20-k01
Roads and bridges · 2018 · VICMAR CONSTRUCTION, INC.
₱90.8MCompleted · 100%
Palico-balayan-batangas rd k0141+(-735.00)-k0142+142.00
Flood control · 2017 · JASMIG CONSTRUCTION CORPORATION / W. RIVERA CONST. AND EQUIPT. RENTALS, INC.
₱97.2MCompleted · 100%
Construction/rehabilitation of multi-purpose building, Barangay poblacion 1
Buildings · 2016 · GAWANATO CONSTRUCTION CORPORATION
₱2.9MCompleted · 100%
Improvement/widening of national roads, S
Flood control · 2016 · RUSMEN BUILDERS & DEVELOPMENT CORPORATION (FORMERL
₱29.2MCompleted · 100%
Preventive maintenance b
Roads and bridges · 2016 · 830 BUILDERS & DEVELOPERS CORP.
₱3.4MCompleted · 100%
₱0For Procurement · 0%
₱0For Procurement · 0%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
NDA BUILDERS AND DEVELOPERS21 projects · ₱162.0M
2
OIC CONZTRUCT AND SUPPLY CORPORATION13 projects · ₱137.7M
3
ARSVICO CONSTRUCTION AND DEVELOPMENT CORP. (FORMER9 projects · ₱153.2M
4
JERIS CONSTRUCTION AND SUPPLY6 projects · ₱15.0M
5
ROSTEL CONSTRUCTION & SUPPLY4 projects · ₱72.2M