National projects
315projects
₱6.82Bin all
75ongoing
22slow
- Flood control ₱3.23B
- Roads and bridges ₱2.43B
- Buildings ₱684.6M
- Schools ₱327.3M
- Other ₱123.8M
- Water ₱19.7M
Showing 301 to 315 of 315
Upgrading of damaged paved nat'l. rds. including drainage, Drainage based on pavement management system/hwy. dev't. and mgt.-4(hdm-4) secondary roads, Mer, Riz
Flood control · 2016 · J.H.R. ENTERPRISES / MRRM TRADING & CONSTRUCTION
₱30.3MCompleted · 100%
Const./maint. of flood mitigation structures and drainage systems, Rehab. with slope protection at kaytickling creek, Brgy. dolores, 1st ld
Flood control · 2016 · C.F. TRINIDAD CONSTRUCTION AND SUPPLIES CORP. (FOR
₱18.4MCompleted · 100%
Const./maint. of flood mitigation structures and drainage systems, Rehab. with slope protection of kaytickling creek, Brgy. san isidro, 1st ld
Flood control · 2016 · C.F. TRINIDAD CONSTRUCTION AND SUPPLIES CORP. (FOR
₱18.4MCompleted · 100%
Repair/rehab. of prototype buildings, Sta. ana elementary school, Sta. ana, Rizal 1st ld
Schools · 2016 · DJL ROBLES BUILDERS
₱1.9MCompleted · 100%
Construction/maintenance of flood mitigation structures and drainage systems, Rehabilitation with slope protection of maningning creek, Brgy. san isidro and sta.ana, Rizal 1st ld
Flood control · 2016 · A.J. LAVA BUILDERS CORP.
₱19.6MCompleted · 100%
Construction/maintenance of flood mitigation structures and drainage systems, Rehabilitation with slope protection of ilog pugad creek, Brgy. san juan, Rizal 1st ld
Flood control · 2016 · A.J. LAVA BUILDERS CORP.
₱19.6MCompleted · 100%
Const./ maint. of flood mitigation structures and drainage systems, Rehab. with slope protection of diversion channel, Brgy. san juan, 1st ld
Flood control · 2016 · C.F. TRINIDAD CONSTRUCTION AND SUPPLIES CORP. (FOR
₱18.9MCompleted · 100%
Improvement of sitio tapayan road, Brgy. san juan, Rizal (first district)
Roads and bridges · 2024
₱0For Procurement · 0%
Construction of road, Block 17 mapalad street, Block 14 maganda street and block 15 mahogany street sta. 0+000 - sta 0+224, Sta. 0+000 - sta 0+126, Purok 2, Lupang arenda, Barangay santa ana, Rizal (first district)
Roads and bridges · 2026
₱0For Procurement · 0%
Construction of road with drainage system, Purok 1 and road 7, Abnai from main road to tertiary road sta. 0+000 - sta. 0+135, Barangay santa ana, Rizal (first district)
Roads and bridges · 2026
₱0For Procurement · 0%
Construction of road with drainage system, Block 27 masipag street and block 24 mahinahon street sta. 0+000 - sta. 0+190, Purok 5, Lupang arenda, Barangay santa ana, Rizal (first district)
Roads and bridges · 2026
₱0For Procurement · 0%
Construction of barkadahan bridge, Barangay san juan, Rizal (first district)
Roads and bridges · 2026
₱0For Procurement · 0%
Construction of road at highway 2000 phase ii sta. 1+376 - sta. 1+573, Rizal (first district)
Roads and bridges · 2026
₱0For Procurement · 0%
Construction of multipurpose bldg., (jvz emergency hospital waiting area), Brgy. san isidro, Rizal (first district)
Buildings · 2026
₱0For Procurement · 0%
Construction of tapayan bridge sta. 0+000 - sta. 0+035 at barangay san juan and barangay sta. ana, Rizal (first district)
Roads and bridges · 2026
₱0For Procurement · 0%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
STREAMLINE BUILDERS CORPORATION50 projects · ₱592.9M
2
LTDL BUILDERS47 projects · ₱572.6M
3
C.F. TRINIDAD CONSTRUCTION AND SUPPLIES CORP. (FOR28 projects · ₱584.0M
4
READYCON TRADING & CONSTRUCTION CORP.22 projects · ₱457.0M
5
HONY TRADING & CONSTRUCTION14 projects · ₱328.5M