Malibcong: Government

Municipality in Abra, Cordillera, Luzon · 12 barangays

National projects

Built by DPWH in Malibcong since 2017.

82projects
₱4.27Bin all
14ongoing
2slow
  • Roads and bridges ₱3.63B
  • Flood control ₱541.9M
  • Water ₱56.7M
  • Buildings ₱24.7M
  • Schools ₱19.6M

Showing 61 to 82 of 82

Concreting of barangay gacab, Fmr, Barangay gacab Roads and bridges · 2021 · R.A. FANGLAYAN (RAF) GENERAL CONSTRUCTION INC.
₱11.9MCompleted · 100%
Concreting of barangay pacqued, Fmr, Barangay pacqued Roads and bridges · 2021 · R.A. FANGLAYAN (RAF) GENERAL CONSTRUCTION INC.
₱11.9MCompleted · 100%
Concreting of brgy. mataragan farm to market road, Mataragan Roads and bridges · 2020 · R.A. FANGLAYAN (RAF) GENERAL CONSTRUCTION INC.
₱24.9MCompleted · 100%
Concreting of brgy. buanao, Farm to market road, Brgy. buanao Roads and bridges · 2020 · R.A. FANGLAYAN (RAF) GENERAL CONSTRUCTION INC.
₱24.9MCompleted · 100%
Construction of multi-purpose building (covered court), Poblacion Buildings · 2021 · R.A. FANGLAYAN (RAF) GENERAL CONSTRUCTION INC.
₱3.0MCompleted · 100%
Construction of multi-purpose building (covered court), Taripan Buildings · 2021 · R.A. FANGLAYAN (RAF) GENERAL CONSTRUCTION INC.
₱3.0MCompleted · 100%
₱143.1MCompleted · 100%
Construction of multi-purpose building (covered court), Binasaran Buildings · 2019 · R.A. FANGLAYAN (RAF) GENERAL CONSTRUCTION INC.
₱3.0MCompleted · 100%
Construction of multi-purpose building, Buanao Buildings · 2019 · PHESCO, INCORPORATED
₱3.0MCompleted · 100%
Construction of multi-purpose building (covered court), Bayabas Buildings · 2019 · R.A. FANGLAYAN (RAF) GENERAL CONSTRUCTION INC.
₱3.0MCompleted · 100%
₱9.6MCompleted · 100%
₱3.4MCompleted · 100%
₱4.8MCompleted · 100%
Rehabilitation/improvement of aguibo-poblacion road Roads and bridges · 2018 · KVC CONSTRUCTION
₱47.5MCompleted · 100%
Rehabilitation of baseng - poblacion road Roads and bridges · 2018 · 739 BUILDERS
₱4.8MCompleted · 100%
₱96.0MCompleted · 100%
Construction of balbalasang 1 & 2 along saltan river Flood control · 2017 · BHM CONSTRUCTION
₱9.3MCompleted · 100%
₱0For Procurement · 0%
₱0For Procurement · 0%
Last mile schools program- bayabas elementary school Schools · 2025 · SUPREME ABF CONST. & CONST. SUPPLY COMPANY INC.
₱11.3MNot Yet Started · 0%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Malibcong since 2017.

1
SILVERWOLVES CONSTRUCTION CORPORATION17 projects · ₱1.60B
2
739 BUILDERS16 projects · ₱490.8M
3
BHM CONSTRUCTION12 projects · ₱531.5M
4
R.A. FANGLAYAN (RAF) GENERAL CONSTRUCTION INC.9 projects · ₱134.5M
5
PHESCO, INCORPORATED5 projects · ₱388.5M

See something wrong?