Malibcong: Government
Municipality in Abra, Cordillera, Luzon · 12 barangays
We get these projects from the DPWH Transparency Portal. The totals are our own sums of what DPWH reports, so they are only as right as DPWH's data. We refresh it every 7 days. If something looks off, open the project on DPWH's site and check.
Synced with DPWH · next check Sun 1 Nov
National projects
82projects
₱4.27Bin all
14ongoing
2slow
- Roads and bridges ₱3.63B
- Flood control ₱541.9M
- Water ₱56.7M
- Buildings ₱24.7M
- Schools ₱19.6M
Construction/upgrading/rehabilitation of drainage along national roads - secondary roads kalinga-abra rd - k0516+690-k0516+693
Flood control · 2026 · BHM CONSTRUCTION
₱5.0MOn-Going · 32%
Rehabilitation / reconstruction of roads with slips, Slope collapse and landslide: secondary roads - kalinga-abra road - k0515+488-k0515-508, K0515+869-k
Roads and bridges · 2026 · BHM CONSTRUCTION
₱42.4MOn-Going · 31%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga rd-k0480+214-k0480+232, K0480+354-k0480+399, K0481+892-k0481+920, K0483+010-k0483+050, K0487+285-k0487+345, K0488+084-k0488+099
Roads and bridges · 2025 · MG SAMIDAN CONSTRUCTION
₱6.1MOn-Going · 85%
Construction of missing links / new roads: abra-kalinga-apayao road along aciga (pinukpuk)-tawang-buaya-mabaca (balbalan section, Kalinga) kalinga.
Roads and bridges · 2025 · BHM CONSTRUCTION
₱120.5MOn-Going · 99%
Construction of malibcong flood control structure along abra river basin
Flood control · 2024 · MG SAMIDAN CONSTRUCTION
₱138.8MOn-Going · 90%
Rehabilitation/reconstruction of roads with slips, Slope collapse and landslide - secondary roads, Kalinga - abra road, K0526+000 to k0526+085
Roads and bridges · 2024 · ROAD EDGE TRADING & DEVELOPMENT SERVICES
₱96.5MOn-Going · 98%
Construction / rehabilitation of water suppy / septage and sewerage / rain water collectors - water supply system construction of water supply systems - construction of water supply system (level iii), Balbal
Water · 2024 · AQUATERRA KONSTRUKT INC.
₱34.3MCompleted · 100%
Construction/ maintenance of flood mitigation structures and drainage systems - construction (completion) of tapao flood control (callangan -ducligan), Sta.166+200 - sta. 166+641 (r/s), Sta. 166+694 - sta. 166+878 (r/s), Sta. 166+374 - sta. 166+926(l/s)
Flood control · 2024 · BHM CONSTRUCTION
₱96.5MOn-Going · 39%Slow
Rehabilitation of water supply / septage and sewerage / rain water collector systems - construction / rehabilitation of water supply / septage and sewerage / rainwater collector system
Water · 2024 · MPD3 CONSTRUCTION
₱2.9MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0480+459-k0480+574
Roads and bridges · 2024 · 739 BUILDERS
₱8.2MOn-Going · 94%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0462+500-k0462+508, K0464+238-k0464+2
Roads and bridges · 2024 · 739 BUILDERS
₱9.3MOn-Going · 100%
Construction/rehabilitation of flood mitigation facilities within major river basins and principal rivers: construction of oling river flood control str
Flood control · 2024 · BHM CONSTRUCTION
₱29.0MCompleted · 100%
Construction / rehabilitation of water supply / septage and sewerage / rain water collector / water supply system - construction of solar water supply project, Municipality balbalan, Province of kalinga
Water · 2023 · AQUATERRA KONSTRUKT INC.
₱19.6MCompleted · 100%
Rehabilitation of binasaran-manapnap road
Roads and bridges · 2023 · MG SAMIDAN CONSTRUCTION
₱96.5MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-tertiary roads, Abra-cervantes road, K0435+250-k0435+280
Roads and bridges · 2023 · 739 BUILDERS
₱2.8MOn-Going · 94%
Construction of road, Abra-kalinga road, K0485+000-k0488+000
Roads and bridges · 2023 · MG SAMIDAN CONSTRUCTION / TWINFORMERS CONSTRUCTION SERVICES
₱144.7MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-tertiary roads, Abra-cervantes road, K0445+650-k0445+665, K0448+300-k0448+
Roads and bridges · 2023 · 739 BUILDERS
₱21.9MOn-Going · 97%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0474+000-k0474+100
Roads and bridges · 2023 · SILVERWOLVES CONSTRUCTION CORPORATION
₱96.5MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0473+300-k0473+400
Roads and bridges · 2023 · SILVERWOLVES CONSTRUCTION CORPORATION
₱96.5MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0474+600-k0474+700
Roads and bridges · 2023 · SILVERWOLVES CONSTRUCTION CORPORATION
₱96.5MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0472+967-k0473+090
Roads and bridges · 2023 · SILVERWOLVES CONSTRUCTION CORPORATION
₱96.5MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0473+120-k0473+250
Roads and bridges · 2023 · SILVERWOLVES CONSTRUCTION CORPORATION
₱96.5MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0474+720-k0474+850
Roads and bridges · 2023 · SILVERWOLVES CONSTRUCTION CORPORATION
₱96.5MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0474+900-k0475+090
Roads and bridges · 2023 · SILVERWOLVES CONSTRUCTION CORPORATION
₱96.5MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0482+650-k0482+750
Roads and bridges · 2023 · SILVERWOLVES CONSTRUCTION CORPORATION
₱96.5MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0484+340-k0484+440
Roads and bridges · 2023 · SILVERWOLVES CONSTRUCTION CORPORATION
₱96.5MCompleted · 100%
Construction of multi-purpose building (covered court), Barangay duldulao
Buildings · 2023 · 739 BUILDERS
₱5.0MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0475+200-k0475+700
Roads and bridges · 2023 · SILVERWOLVES CONSTRUCTION CORPORATION
₱77.2MCompleted · 100%
Rehabilitation/ reconstruction of roads with slips, Slope collapse and landslide-secondary roads, Abra-kalinga road-k0473+450-k0473+600
Roads and bridges · 2023 · SILVERWOLVES CONSTRUCTION CORPORATION
₱96.5MCompleted · 100%
Construction of multi-purpose building (covered court), Barangay mataragan
Buildings · 2023 · 739 BUILDERS
₱5.0MCompleted · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
SILVERWOLVES CONSTRUCTION CORPORATION17 projects · ₱1.60B
2
739 BUILDERS16 projects · ₱490.8M
3
BHM CONSTRUCTION12 projects · ₱531.5M
4
R.A. FANGLAYAN (RAF) GENERAL CONSTRUCTION INC.9 projects · ₱134.5M
5
PHESCO, INCORPORATED5 projects · ₱388.5M