Vintar: Government

Municipality in Ilocos Norte, Ilocos, Luzon · 33 barangays

National projects

Built by DPWH in Vintar since 2016.

504projects
₱10.21Bin all
185ongoing
20slow
  • Flood control ₱6.59B
  • Roads and bridges ₱3.06B
  • Buildings ₱283.7M
  • Schools ₱249.0M
  • Water ₱20.0M
Construction ofroad, Barangay p.f. alviar Roads and bridges · 2024 · BJMJB CONSTRUCTION & SUPPLY
₱4.8MOn-Going · 54%Slow
Construction of sinamar bridge, Barangay lubnac Roads and bridges · 2024 · NORTHLANDER CONSTRUCTION
₱7.7MOn-Going · 39%Slow
₱23.5MOn-Going · 25%Slow
Construction of canal lining, Barangay sta. maria Flood control · 2024 · BJMJB CONSTRUCTION & SUPPLY
₱4.9MOn-Going · 53%Slow
Construction of road, Barangay #11 bulbulala Roads and bridges · 2024 · BJMJB CONSTRUCTION & SUPPLY
₱4.8MOn-Going · 41%Slow
Concreting of brgy. 29 and 30, San jose and sto. tomas fmr Roads and bridges · 2024 · BJMJB CONSTRUCTION & SUPPLY
₱4.8MOn-Going · 44%Slow
₱4.8MOn-Going · 41%Slow
Construction of multi purpose building, Barangay cabisuculan Buildings · 2024 · BJMJB CONSTRUCTION & SUPPLY
₱4.8MOn-Going · 23%Slow
Construction of road, Barngay 13 mabanbanag Roads and bridges · 2024 · BJMJB CONSTRUCTION & SUPPLY
₱4.7MOn-Going · 51%Slow
Improvement of road, Barangay #7 alejo malasig Roads and bridges · 2024 · NORTHLANDER CONSTRUCTION
₱2.8MOn-Going · 0%Slow
₱4.8MOn-Going · 48%Slow
₱4.9MOn-Going · 55%Slow
Construction of multi purpose building, (covered court) sitio dasar, Barangay #34 isic isic Buildings · 2024 · MEGAPOLITAN BUILDERS AND CONSTRUCTION SUPPLY
₱4.8MOn-Going · 55%Slow
₱4.8MOn-Going · 48%Slow
Construction of multi purpose building, (covered court) barangay #34 isic isic Buildings · 2024 · MEGAPOLITAN BUILDERS AND CONSTRUCTION SUPPLY
₱4.9MOn-Going · 46%Slow
₱2.0MOn-Going · 55%Slow
₱3.4MOn-Going · 24%Slow
₱2.9MOn-Going · 29%Slow
Construction of road, Brgy. alsem Roads and bridges · 2023 · HEKLER BUILDERS CORP.
₱23.5MOn-Going · 49%Slow

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Vintar since 2016.

1
MEGAPOLITAN BUILDERS AND CONSTRUCTION SUPPLY67 projects · ₱1.87B
2
BJMJB CONSTRUCTION & SUPPLY58 projects · ₱1.03B
3
JCA CONSTRUCTION AND CONSTRUCTION SUPPLY34 projects · ₱482.9M
4
KATHA BUILDERS & SUPPLIES INC.27 projects · ₱894.2M
5
ZEDIK BUILDERS25 projects · ₱136.3M