National projects
191projects
₱3.00Bin all
9ongoing
2slow
- Roads and bridges ₱1.67B
- Flood control ₱831.3M
- Buildings ₱343.2M
- Schools ₱80.2M
- Other ₱36.1M
- Water ₱31.1M
Showing 1 to 30 of 191
Construction of classrooms, Omnhs talabaan extension
Schools · 2025 · SOUTHPEAK CONSTRUCTION
₱4.9MCompleted · 100%
Preventive maintenance- secondary roads- mindoro west coastal road, K0368+000-k0411+250 (intermittent sections), Occ. mindoro
Roads and bridges · 2025 · EGB CONSTRUCTION CORPORATION
₱186.2MOn-Going · 2%
Improvement - secondary roads - mindoro west coastal rd - k0408+ 709 - k0408 + 809
Roads and bridges · 2025 · D. DOLOR CONSTRUCTION
₱2.9MCompleted · 100%
Const. of flood control structure along abra de ilog river, Sitio kuli-kuli section (rs), Armado, Sta. 000+234-sta. 000+900, Abra de il
Flood control · 2025 · D.T. RECIO INCORPORATED
₱284.3MOn-Going · 30%
Widening of permanent bridges - armado br.2 (b00122mr) along mindoro west coastal rd
Roads and bridges · 2025 · ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 31762)
₱23.8MOn-Going · 54%
Construction/upgrading/rehabilitation of drainage along national roads - mindoro west coastal rd (section 7) (s00121mr) - k0409+620 - k0410+000
Flood control · 2025 · F-NINE CONSTRUCTION
₱8.2MCompleted · 100%
Construction of flood control structures payompon fc (dapi - boribor section)
Flood control · 2025 · STX ENTERPRISES
₱28.6MCompleted · 100%
Flood mitigation structure, Barangay 7
Flood control · 2025 · KEJAMARENIK CONSTRUCTION & CONSTRUCTION SUPPLIES
₱32.8MCompleted · 100%
Widening of mindoro west coastal rd (section 7) (s00121mr) - k0402+ 947 - k0404 + 005
Roads and bridges · 2025 · KEJAMARENIK CONSTRUCTION & CONSTRUCTION SUPPLIES
₱29.2MCompleted · 100%
Widening of mindoro west coastal rd (section 7) (s00121mr) - k0399+ 1013 - k0400 + 850
Roads and bridges · 2025 · F.A. TORRES CONSTRUCTION
₱26.8MCompleted · 100%
Construction of multi-purpose building, Barangay san luis
Buildings · 2025 · KGB ENGINEERING AND CONSTRUCTION
₱6.9MOn-Going · 31%
Widening of mindoro west coastal rd (section 7) (s00121mr) - k0421+ 1007 - k0422 + 351, K0422+519 - k0423+562
Roads and bridges · 2025 · F.A. TORRES CONSTRUCTION
₱48.6MOn-Going · 100%
Widening of permanent bridges - boribor br. (b00243mr) along mindoro west coastal rd
Roads and bridges · 2025 · KEJAMARENIK CONSTRUCTION & CONSTRUCTION SUPPLIES
₱47.1MCompleted · 100%
Construction of road, Barangay tangkalan
Roads and bridges · 2025 · KGB ENGINEERING AND CONSTRUCTION
₱4.8MCompleted · 100%
Completion/upgrading/repair and equipping of rhus- mamburao rural health unit, Occ. mindoro
Other · 2024 · ROGE CONSTRUCTION AND CONSTRUCTION SUPPLY
₱5.8MOn-Going · 61%
Rehabilitation/ reconstruction/upgrading of damaged paved roads - secondary roads - mindoro west coastal road - k0412+305 - k0412+781
Roads and bridges · 2024 · KGB ENGINEERING AND CONSTRUCTION
₱8.8MCompleted · 100%
Construction of protection dike (gabions) at tayamaan river, Tayamaan
Flood control · 2024 · NEW MINDORENOS LUMBER, HARDWARE AND GEN MERCHANDISE
₱11.5MCompleted · 100%
Construction of protection dike at barangay talabaan
Flood control · 2024 · KGB ENGINEERING AND CONSTRUCTION
₱4.9MCompleted · 100%
Widening of permanent bridge - sugsugin br. (b00112mr) along mindoro west coastal rd
Roads and bridges · 2024 · 1129 BUILDERS / SYNDTITE CONSTRUCTION CORPORATION
₱64.3MOn-Going · 21%Slow
Construction of protection dike at barangay 8
Flood control · 2024 · ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 31762)
₱94.7MCompleted · 100%
Construction of protection dike along east bank of tiguilan river, Barangay tayamaan
Flood control · 2024 · KGB ENGINEERING AND CONSTRUCTION
₱24.4MCompleted · 100%
Construction of flood mitigation structure, Barangay 5
Flood control · 2024 · STX ENTERPRISES
₱4.9MCompleted · 100%
Construction of flood mitigation structure, Barangay 7
Flood control · 2024 · STX ENTERPRISES
₱9.8MCompleted · 100%
Widening - mindoro west coastal rd (s000095mr) - k0408+800 - k0408+924, K0408+936 - k0409+000
Roads and bridges · 2024 · F-NINE CONSTRUCTION
₱5.9MCompleted · 100%
Widening of permanent bridges - maculbo br. (b00242mr) along mindoro west coastal rd. mamburao
Roads and bridges · 2024 · F.A. TORRES CONSTRUCTION
₱24.5MCompleted · 100%
Widening of permanent bridges - baboy br. (b00119mr) along mindoro west coastal rd.
Roads and bridges · 2024 · MMQ ENTERPRISES
₱24.5MCompleted · 100%
Rehabilitation / reconstruction of roads with slips, Slope collapse, And landslide - mindoro west coastal rd (s00095mr) - k0409+435 - k409+580
Roads and bridges · 2024 · KGB ENGINEERING AND CONSTRUCTION
₱24.5MCompleted · 100%
Construction of concrete road - construction of lagundian - maasim road
Roads and bridges · 2023 · HI-TONE CONSTRUCTION & DEVELOPMENT CORP.
₱49.5MCompleted · 100%
Construction (completion) of two (2) storey hostel building, Dpwh mindoro occidental district engineering office
Buildings · 2023 · WAY MAKER GENERAL CONTRACTOR OPC ([REVOKED] 52351)
₱6.6MCompleted · 100%
Construction/improvement of various infrastructures in support of national security (tatag ng imprastraktura para sa kapayapaan at seguridad program-tikas)- construction of pnp building, Phase ii
Buildings · 2023 · KGB ENGINEERING AND CONSTRUCTION
₱14.1MOn-Going · 87%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
NEW MINDORENOS LUMBER, HARDWARE AND GEN MERCHANDISE63 projects · ₱458.3M
2
KGB ENGINEERING AND CONSTRUCTION17 projects · ₱135.1M
3
KEJAMARENIK CONSTRUCTION & CONSTRUCTION SUPPLIES14 projects · ₱192.4M
4
F.A. TORRES CONSTRUCTION10 projects · ₱208.2M
5
SYNDTITE CONSTRUCTION CORPORATION7 projects · ₱198.8M