National projects

Built by DPWH in Cotabato City since 2016.

419projects
₱10.07Bin all
27ongoing
2slow
  • Flood control ₱4.99B
  • Roads and bridges ₱4.05B
  • Schools ₱499.1M
  • Buildings ₱449.1M
  • Water ₱61.0M
  • Other ₱15.8M

Showing 1 to 30 of 419

Construction/completion of water system for bfp at barangay poblacion a, Mlang Water · 2026 · ALZEN ENGINEERING & CONSTRUCTION SUPPLIES
₱3.0MOn-Going · 18%
Construction of solar water system at barangay la suerte, Mlang Water · 2026 · SAREX BUILDERS AND SUPPLY
₱4.9MOn-Going · 4%
Construction of road, Sta. 0+000 - sta. 2+498, Barangay pag-asa, Mlang Roads and bridges · 2026 · TIPICON ENGINEERING INNOVATIONS
₱46.9MOn-Going · 5%
Construction of solar water system at barangay ugpay, Mlang Water · 2026 · SAREX BUILDERS AND SUPPLY
₱4.9MOn-Going · 8%
₱91.9MOn-Going · 32%
Construction of covered court at dungo-an high school (305794), Barangay dungo-an, Mlang Schools · 2026 · BATUA ENGINEERING SERVICES AND CONSTRUCTION SUPPLY
₱4.8MOn-Going · 57%
₱46.9MOn-Going · 71%
₱9.1MCompleted · 100%
Construction of multi-purpose building, Purok 1, Barangay poblacion, Pres. roxas Buildings · 2025 · ARBY'S BUILDERS AND CONSTRUCTION SUPPLY CORP.
₱4.9MOn-Going · 90%
₱19.9MOn-Going · 98%
₱56.4MOn-Going · 78%
₱4.7MCompleted · 100%
₱4.7MOn-Going · 0%
₱4.7MCompleted · 100%
Concreting of road in barangay lepaga, Mlang Roads and bridges · 2025 · JARGON CONSTRUCTION & SUPPLY
₱9.4MOn-Going · 80%
Construction of multi-purpose building, Usm-kabacan in kabacan Buildings · 2025 · BORDERLINE CONSTRUCTION & SUPPLY
₱4.7MCompleted · 100%
Construction of road from purok 4 to purok 6 in brgy. langkong, Mlang Roads and bridges · 2025 · JOHN RAY DEVELOPER AND SUPPLIES
₱9.4MCompleted · 100%
Completion/rehabilitation of multi-purpose building (covered court) in brgy. kalunasan, Mlang Buildings · 2025 · BATUA ENGINEERING SERVICES AND CONSTRUCTION SUPPLY
₱4.7MCompleted · 100%
₱4.9MCompleted · 100%
₱4.9MCompleted · 100%
Concreting of brgy. poblacion to brgy. bulacaon fmr, Brgy. poblacion and brgy. bulacaon, Pigcawayan Roads and bridges · 2025 · GFJ CONSTRUCTION SUPPLY & MERCHANDISE
₱14.5MCompleted · 100%
₱4.8MOn-Going · 100%
Construction of 1-storey dialysis center Buildings · 2024 · KLD ENGINEERING CONSTRUCTION
₱9.9MOn-Going · 100%
₱77.0MCompleted · 100%
₱14.6MCompleted · 100%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Cotabato City since 2016.

1
BRE CONSTRUCTION36 projects · ₱656.6M
2
LLABAN CONSTRUCTION & SUPPLY16 projects · ₱426.3M
3
STONELINE CONSTRUCTION16 projects · ₱127.5M
4
GEMMA CONSTRUCTION SUPPLY, INC.15 projects · ₱1.13B
5
JARGON CONSTRUCTION & SUPPLY15 projects · ₱923.5M