Tandag City: Government

City in Surigao del Sur, Caraga, Mindanao · 21 barangays

National projects

Built by DPWH in Tandag City since 2016.

191projects
₱6.75Bin all
14ongoing
1slow
  • Roads and bridges ₱3.77B
  • Flood control ₱1.82B
  • Buildings ₱715.0M
  • Schools ₱433.0M
  • Water ₱15.7M

Showing 1 to 30 of 159

₱5.2MCompleted · 100%
₱8.2MCompleted · 100%
Construction/improvement of drainage barangay telaje Flood control · 2025 · ED1SON DEVELOPMENT & CONSTRUCTION INC.
₱39.2MCompleted · 100%
₱3.0MCompleted · 100%
₱13.6MCompleted · 100%
Construction of multi-purpose building, San antonio Buildings · 2025 · ROWIE'S CONSTRUCTION
₱9.6MCompleted · 100%
₱4.8MCompleted · 100%
₱9.8MCompleted · 100%
₱4.9MCompleted · 100%
Butuan city-pianing-tandag road, Package 12 Roads and bridges · 2025 · J.M. LUCIANO CONSTRUCTION, INC.
₱18.7MCompleted · 100%
Construction of flood control structure at purok lansones i, Barangay san agustin Flood control · 2025 · J.M. LUCIANO CONSTRUCTION, INC.
₱48.5MCompleted · 100%
Const. of flood mitigation structure along tandag river, Brgy. quezon, Phase 2 Flood control · 2025 · LICSAL CONSTRUCTION CORPORATION
₱95.0MCompleted · 100%
Const. of flood mitigation along tandag river, Brgy. quezon, Phase 1 Flood control · 2025 · J.M. LUCIANO CONSTRUCTION, INC.
₱95.5MCompleted · 100%
₱47.9MCompleted · 100%
Const. of seawall, Barangay bagong lungsod Flood control · 2025 · J.M. LUCIANO CONSTRUCTION, INC.
₱95.5MCompleted · 100%
₱4.9MCompleted · 100%
Const. of dawis seawall, Phase ii Flood control · 2025 · J.M. LUCIANO CONSTRUCTION, INC.
₱95.5MCompleted · 100%
₱2.9MCompleted · 100%
₱4.9MCompleted · 100%
Const. of san agustin sur seawall Flood control · 2024 · EVENPAR CONSTRUCTION AND DEVELOPMENT CORPORATION / GICAR CONSTRUCTION, INC.
₱96.5MCompleted · 100%
Const. of flood control structure san agustin sur Flood control · 2024 · EVENPAR CONSTRUCTION AND DEVELOPMENT CORPORATION / ME 3 CONSTRUCTION
₱48.2MCompleted · 100%
₱5.0MCompleted · 100%
₱4.9MCompleted · 100%
₱3.5MCompleted · 100%
₱5.0MCompleted · 100%
₱24.9MCompleted · 100%
₱10.3MCompleted · 100%
₱19.8MCompleted · 100%
₱4.9MCompleted · 100%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Tandag City since 2016.

1
RJ CONSTRUCTION & SUPPLY28 projects · ₱136.9M
2
J.M. LUCIANO CONSTRUCTION, INC.24 projects · ₱2.09B
3
ROWIE'S CONSTRUCTION21 projects · ₱242.1M
4
LCTING CONSTRUCTION AND DEVELOPMENT CORPORATION10 projects · ₱481.2M