Polomolok: Government

Municipality in South Cotabato, Soccsksargen, Mindanao · 23 barangays

National projects

Built by DPWH in Polomolok since 2016.

272projects
₱4.69Bin all
12ongoing
2slow
  • Roads and bridges ₱2.67B
  • Flood control ₱1.28B
  • Schools ₱470.7M
  • Buildings ₱197.1M
  • Water ₱70.6M

Showing 121 to 150 of 246

Construction of multi-purpose building, Barangay poblacion Buildings · 2021 · NIRVANA CONSTRUCTION & SUPPLIES
₱3.1MCompleted · 100%
₱54.8MCompleted · 100%
Preventive maintenance - primary roads - marbel - makar rd - k1668 + 704 - k1669 + 265 Roads and bridges · 2020 · MGBJ RISING CONSTRUCTION & LAND DEVELOPER
₱29.4MCompleted · 100%
Concreting, Including drainage, Amgoo, Brgy. landan (access road leading to a wellness village for blaan tribe) Roads and bridges · 2020 · CHL CONSTRUCTION & DEVELOPMENT ENTERPRISES, INC.
₱28.6MCompleted · 100%
Construction of multi-purpose building, Prk. dignadice, Brgy. poblacion Buildings · 2020 · SHEPPERD CONSTRUCTION AND SUPPLY
₱1.7MCompleted · 100%
Construction of drainage structure (lined canal), Brgy. upper klinan, 1st ld Flood control · 2020 · C.A.V. BUILDERS AND SUPPLY CORPORATION
₱1.8MCompleted · 100%
Construction of multi-purpose building, Prk. kaunlaran, Brgy. poblacion Buildings · 2020 · C E K CONSTRUCTION AND WATER SUPPLY
₱1.7MCompleted · 100%
Construction of covered court, Purok 5, Brgy. lamcaliaf Buildings · 2020 · ROCKSTONE CONSTRUCTION SERVICES & SUPPLY
₱1.6MCompleted · 100%
Construction of multi-purpose building, Brgy. klinan 6 Buildings · 2020 · ROCKSTONE CONSTRUCTION SERVICES & SUPPLY
₱1.8MCompleted · 100%
Construction/completion of multi-purpose building, Brgy. polo Buildings · 2020 · SAMLIN CONSTRUCTION
₱1.2MCompleted · 100%
Desilting/rechanneling of riverbank along purok masipag, Riverbank, Klinan 6 Flood control · 2020 · ROCKSTONE CONSTRUCTION SERVICES & SUPPLY
₱2.5MCompleted · 100%
Construction of water system with overhead tank Water · 2020 · HANNA VIA CONSTRUCTION, INC.
₱3.0MCompleted · 100%
Construction of multi-purpose building, Brgy. lumakil Buildings · 2020 · ROCKSTONE CONSTRUCTION SERVICES & SUPPLY
₱1.7MCompleted · 100%
Concreting, Crossing palkan Roads and bridges · 2020 · DUMALAG SURVEYING AND ENGINEERING SERVICES
₱1.8MCompleted · 100%
Concreting, Koronadal proper Roads and bridges · 2020 · PASE CONSTRUCTION
₱2.4MCompleted · 100%
Construction of multi-purpose building, Brgy. silway 8 Buildings · 2020 · VERGUZ CONSTRUCTION
₱1.4MCompleted · 100%
₱1.2MCompleted · 100%
₱13.3MCompleted · 100%
Rehabilitation of polomolok public market, Brgy. poblacion Buildings · 2019 · ROCKSTONE CONSTRUCTION SERVICES & SUPPLY
₱5.0MCompleted · 100%
₱45.3MCompleted · 100%
Construction of multi-purpose building, Brgy. landan Buildings · 2020 · F.H. GOPITEO CONSTRUCTION & SUPPLY
₱1.5MCompleted · 100%
Construction of multi-purpose building, Purok summerlight, Brgy. magsaysay Buildings · 2020 · FASTRUCT DESIGN AND CONSTRUCTION
₱1.5MCompleted · 100%
₱1.7MCompleted · 100%
Construction of multi-purpose building, Purok dole, Gawad, Brgy. cannery site Buildings · 2020 · FUENTABUILT CONSTRUCTION CORP.
₱2.5MCompleted · 100%
₱2.5MCompleted · 100%
₱1.4MCompleted · 100%
Construction of multi-purpose building, Brgy. lapu Buildings · 2020 · TROPILAND ENTERPRISES
₱1.6MCompleted · 100%
Construction of multi-purpose building, Brgy. landan Buildings · 2020 · C E K CONSTRUCTION AND WATER SUPPLY
₱1.7MCompleted · 100%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Polomolok since 2016.

1
CHL CONSTRUCTION & DEVELOPMENT ENTERPRISES, INC.21 projects · ₱1.12B
2
J.G. ORANZA CONSTRUCTION20 projects · ₱611.0M
3
VERGUZ CONSTRUCTION11 projects · ₱30.5M
4
ROCKSTONE CONSTRUCTION SERVICES & SUPPLY10 projects · ₱45.6M
5
F.H. GOPITEO CONSTRUCTION & SUPPLY7 projects · ₱135.4M

See something wrong?

A project that looks finished on paper but not on the ground, or work that stopped. Post a photo on the Talk board, or report it to DPWH on the project's own page.