National projects
339projects
₱10.31Bin all
50ongoing
7slow
- Roads and bridges ₱4.81B
- Flood control ₱2.67B
- Buildings ₱1.77B
- Schools ₱942.9M
- Water ₱111.6M
Showing 1 to 30 of 339
Const./ upgrading/ rehab. of drainage along national roads - secondary roads - mactan circumferential rd - k0016 + 630 - k0017 + 650, Cebu
Flood control · 2026 · QUIRANTE CONSTRUCTION CORPORATION
₱77.6MOn-Going · 31%
Construction/ upgrading/ rehabilitation of drainage along national roads - primary roads - pajo-basak marigondon rd - chainage 1229 - chainage 1703, Cebu
Flood control · 2026 · MUANA CONSTRUCTION AND DEVELOPMENT CORP.
₱41.7MOn-Going · 0%
Construction of road from sudtungan, Brgy. basak to brgy. babag, Cebu (phase 3)
Roads and bridges · 2025 · QUIRANTE CONSTRUCTION CORPORATION
₱96.3MOn-Going · 0%
Preventive maintenance - secondary roads - mactan circumferential rd - k0017 + 642 - k0018 + 500, Cebu
Roads and bridges · 2026 · SOCOR CONSTRUCTION CORPORATION
₱12.4MOn-Going · 0%
Repair/rehabilitation of classrooms, Basak night high school, Cebu
Schools · 2025 · GONZALODO ENTERPRISES
₱5.9MOn-Going · 100%
Construction of evacuation center at brgy. canjulao (phase 2), Cebu
Buildings · 2025 · JANUARY BUILDERS
₱49.2MOn-Going · 0%
Construction of multi-purpose building at brgy. punta engano (phase 2), Cebu
Buildings · 2025 · PLD CONSTRUCTION AND DEVELOPMENT INC.
₱88.8MOn-Going · 55%
Improvement of road with drainage facilities, Timpolok road, Barangay gun-ob and barangay babag (phase 3), Cebu
Flood control · 2025 · QUIRANTE CONSTRUCTION CORPORATION
₱19.2MCompleted · 100%
Construction of multi-purpose buildings including other facilities, Cebu (package 1)
Buildings · 2025 · PHIL ASIA RESOURCES & DEVELOPMENT CORP. / QUIRANTE CONSTRUCTION CORPORATION
₱146.3MOn-Going · 0%
Construction of multi-purpose building at brgy. canjulao (phase 3), Cebu
Buildings · 2025 · GONZALODO ENTERPRISES
₱34.3MCompleted · 100%
Rehabilitation of road with drainage system along george tampus road (phase 2), Barangay basak
Roads and bridges · 2025 · GEETY REALTY AND DEVELOPMENT CORPORATION
₱24.3MOn-Going · 9%
Const./ maintenance of flood mitigation structures and drainage systems, Const. of flood control structure along calawisan creek (package 2), Brgy. calawisan
Flood control · 2025 · QUIRANTE CONSTRUCTION CORPORATION
₱144.6MOn-Going · 99%
Construction/ maintenance of flood mitigation structures and drainage systems - construction of drainage system at barangay buaya, Cebu
Flood control · 2025 · FDC CONSTRUCTION AND SUPPLIES CO.
₱28.8MOn-Going · 3%
Construction of evacuation center at olango island (phase 3), Cebu
Buildings · 2025 · GRAND TAISHAN CONSTRUCTION AND DEVELOPMENT INC.
₱9.7MCompleted · 100%
Improvement of road with drainage facilities, Humay-humay-ceres road, Cebu
Flood control · 2025 · PHIL ASIA RESOURCES & DEVELOPMENT CORP. / WTG CONSTRUCTION & DEVELOPMENT CORPORATION
₱28.8MOn-Going · 43%
Construction of multi-purpose building (lapu-lapu city college), Brgy. gun-ob (phase 5), Cebu
Buildings · 2025 · GBUILD SUPPLY AND DEVELOPMENT INC.
₱29.1MOn-Going · 37%
Construction of school building (phase 2), Cawhagan integrated school, Cebu
Schools · 2025 · PATIGDAS CONSTRUCTION & SUPPLY
₱19.5MOn-Going · 100%
Construction of road with drainage facilities, Phase 2, Barangay canjulao
Flood control · 2025 · PHIL ASIA RESOURCES & DEVELOPMENT CORP. / WTG CONSTRUCTION & DEVELOPMENT CORPORATION
₱28.8MOn-Going · 69%
Improvement of road with drainage system at s. osmena st., Cebu
Roads and bridges · 2025 · PHIL ASIA RESOURCES & DEVELOPMENT CORP.
₱14.4MOn-Going · 54%
Construction of multi purpose building at brgy. basak (phase 5), Cebu
Buildings · 2025 · A.A. MASONG CONSTRUCTION
₱19.4MOn-Going · 34%
Construction of seawall phase 1 at barangay ibo
Flood control · 2024 · QUIRANTE CONSTRUCTION CORPORATION
₱95.5MOn-Going · 0%
Retrofitting/ strengthening of permanent bridges, Marcelo fernan br. (b00619cb) along marcelo b. fernan br. & approaches
Roads and bridges · 2025 · GICAR CONSTRUCTION, INC. / ZLREJ TRADING AND CONSTRUCTION CORPORATION
₱173.6MOn-Going · 61%
Construction of multi-purpose facility phase 2 at barangay looc, Cebu
Buildings · 2024 · QUIRANTE CONSTRUCTION CORPORATION
₱145.5MOn-Going · 0%
Construction of multi-purpose facility phase 1 at barangay looc, Cebu
Buildings · 2024 · QUIRANTE CONSTRUCTION CORPORATION
₱145.5MOn-Going · 0%
Preventive maintenance - secondary roads - mactan circumferential rd - k0034+667 - k0035+100, Cebu
Roads and bridges · 2025 · SOCOR CONSTRUCTION CORPORATION
₱19.6MOn-Going · 64%
Improvement - secondary roads - mactan circumferential rd - k0014+(-962) - k0015+900, Cebu
Roads and bridges · 2025 · FLORIANE CONSTRUCTION CORPORATION
₱29.3MOn-Going · 100%
Construction/ upgrading/ rehabilitation of drainage along national roads - secondary roads - mactan circumferential rd - k0033+460-k0035+100, Cebu
Flood control · 2025 · SUPREA PHILS. DEVELOPMENT CORP.
₱70.9MOn-Going · 13%
Construction of multi-purpose building (lapu-lapu city college), Barangay gun-ob, Cebu
Buildings · 2025 · GONZALODO ENTERPRISES
₱38.8MOn-Going · 51%
Improvement of road with drainage facilities, Timpolok road, Brgy. gun-ob and brgy. babag (phase 4)
Flood control · 2025 · QUIRANTE CONSTRUCTION CORPORATION
₱19.2MCompleted · 100%
Construction/ upgrading/ rehabilitation of drainage along national roads - tertiary roads - opon-airport rd - (s00003lp) chainage 0 - chainage 654, Cebu
Flood control · 2025 · PHIL ASIA RESOURCES & DEVELOPMENT CORP. / WTG CONSTRUCTION & DEVELOPMENT CORPORATION
₱39.2MOn-Going · 87%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
QUIRANTE CONSTRUCTION CORPORATION27 projects · ₱2.08B
2
GONZALODO ENTERPRISES26 projects · ₱434.5M
3
JJ&J CONSTRUCTION AND GENERAL SUPPLY CORPORATION22 projects · ₱579.9M
4
GOLDFIN CONSTRUCTION & DEVELOPMENT CORPORATION20 projects · ₱351.5M
5
PLD CONSTRUCTION AND DEVELOPMENT INC.13 projects · ₱312.7M