MA
Mabinay: Government
Municipality in Negros Oriental, Negros Island, Visayas · 32 barangays
National projects
263projects
₱4.61Bin all
22ongoing
3slow
- Roads and bridges ₱2.91B
- Flood control ₱980.7M
- Schools ₱418.9M
- Buildings ₱266.6M
- Other ₱17.0M
- Water ₱14.3M
Construction of box culvert bridge, Barangay hagtu
Flood control · 2026 · PHILSOUTH BUILDERS INC
₱9.8MOn-Going · 0%
Construction of road, Sta. 0+000 -sta. 0+390, Barangay inapoy
Roads and bridges · 2026 · ASHLEYKA CONSTRUCTION AND SUPPLIES CORP.
₱7.4MOn-Going · 0%
Construction of multi-purpose building (covered court), Pantao national high school (school id no. 303260), Brgy. pantao
Schools · 2026 · PER CONSTRUCTION AND SUPPLY
₱4.9MOn-Going · 0%
Rehabilitation/reconstruction/upgrading of damaged paved roads - primary roads - bais - kabankalan rd k0090+000 - k0091+000
Roads and bridges · 2026 · TRINITYCAD CORPORATION
₱33.1MOn-Going · 21%
Preventive maintenance - primary roads - bais - kabankalan rd - k0064+209 - k0065+430
Roads and bridges · 2026 · HOMEWORLD CONSTRUCTION CORP.
₱29.4MOn-Going · 98%
Construction of farm-to-mill road, So. iranun, Brgy. himocdungon, Negros oriental-so. maasin, Barangay tara
Roads and bridges · 2025 · VESA ENGINEERING AND CONSTRUCTION
₱34.5MOn-Going · 72%
Repair/rehabilitation of classrooms, Tampa elementary school
Schools · 2025 · MG CONSTRUCTION
₱4.9MOn-Going · 74%
Construction of multi-purpose building (sports complex)
Buildings · 2025 · PHILSOUTH BUILDERS INC
₱48.5MOn-Going · 60%
Concreting of sitio proper to sitio camadmad fmr, Brgy. old namangka
Roads and bridges · 2025 · VESA ENGINEERING AND CONSTRUCTION
₱14.2MOn-Going · 100%
Rehabilitation/reconstruction/upgrading of damaged paved road-primary roads-bais-kabankalan road-k0097+000-k0097+415
Roads and bridges · 2025 · VESA ENGINEERING AND CONSTRUCTION
₱15.0MOn-Going · 100%
Construction/improvement of access roads leading to declared tourism destinations(tourism road infrastructure program-trip)-access road leading to cantumbol dos falls
Roads and bridges · 2025 · VESA ENGINEERING AND CONSTRUCTION
₱4.9MOn-Going · 97%
Construction/maintenance of flood mitigation structures and drainage systems - construction of flood control structure, Batang river, Barangay lumbang
Flood control · 2025 · C.T. LEONCIO CONSTRUCTION & TRADING / S-ANG CONSTRUCTION & GENERAL TRADING, INC.
₱141.2MOn-Going · 49%
Construction/maintenance of flood mitigation structures and drainage systems - construction of flood control structure, Di-ay river, Negros o
Flood control · 2025 · C.T. LEONCIO CONSTRUCTION & TRADING / S-ANG CONSTRUCTION & GENERAL TRADING, INC.
₱141.0MOn-Going · 50%
Construction/maintenance of flood mitigation structures and drainage systems - construction of flood control structure (downstream), Barangay luyang
Flood control · 2025 · C.T. LEONCIO CONSTRUCTION & TRADING / S-ANG CONSTRUCTION & GENERAL TRADING, INC.
₱141.1MOn-Going · 47%
Widening - primary roads - bais - kabankalan rd - k0085+190 - k0085+848, K0088+074.10 - k0088+500
Roads and bridges · 2025 · VESA ENGINEERING AND CONSTRUCTION
₱68.8MOn-Going · 40%
Construction of road, Barangay inapoy
Roads and bridges · 2025 · SUPREME MEGA STRUCTURE BUILDERS, INC.
₱9.7MOn-Going · 100%
Construction of multi-purpose building(sports complex)
Buildings · 2024 · R.E. SINGSON CONSTRUCTION AND DEVELOPMENT INC.
₱29.7MOn-Going · 100%
Construction of bulod river control(upstream), Negros o
Flood control · 2024 · ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 31762)
₱96.5MOn-Going · 59%Slow
Construction/rehabilitation of flood mitigation facilities within major river basins and principal rivers-construction of namangyan river control, Bagtic
Flood control · 2024 · ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. ([REVOKED] 31762)
₱96.5MOn-Going · 94%
Construction of 2 units 2-storey 6-classroom school building in mabinay central school, Barangay poblacion, Municipality of mabinay
Schools · 2024 · PER CONSTRUCTION AND SUPPLY / VVER CONSTRUCTION DEVELOPMENT CORPORATION
₱39.8MOn-Going · 100%
Construction (completion) of multi-purpose building, Barangay luyang
Buildings · 2024 · PER CONSTRUCTION AND SUPPLY
₱2.0MOn-Going · 53%Slow
Rainwater system: 1) lamdas elementary school, Brgy. lamdas, Mabinay; 2) inapoy elementary school, Brgy. lamdas; 3) canggohob elementary school, Brgy. canggohob; 4) cansal-ing elementary school, Brgy. cansal-ing and 5) samac elementary school, Brgy. samac
Schools · 2023 · DOUBLE J AND T CONSTRUCTION AND SUPPLY CORPORATION
₱2.3MOn-Going · 16%Slow
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
SUPREME MEGA STRUCTURE BUILDERS, INC.40 projects · ₱119.1M
2
VESA ENGINEERING AND CONSTRUCTION17 projects · ₱259.3M
3
ASHLEYKA CONSTRUCTION AND SUPPLIES CORP.17 projects · ₱63.5M
4
PHILSOUTH BUILDERS INC16 projects · ₱674.6M
5
R.E. SINGSON CONSTRUCTION AND DEVELOPMENT INC.16 projects · ₱287.3M