National projects

Built by DPWH in Daraga since 2016.

530projects
₱22.67Bin all
228ongoing
47slow
  • Flood control ₱9.59B
  • Roads and bridges ₱7.63B
  • Buildings ₱4.25B
  • Schools ₱914.5M
  • Water ₱240.1M
  • Other ₱47.5M

Showing 91 to 120 of 228

₱19.0MOn-Going · 100%
Construction of barangay bascaran to barangay mariawa road Roads and bridges · 2024 · FIRST OMB CONSTRUCTION AND DEVELOPMENT CORP.
₱20.4MOn-Going · 98%
Construction of dike along cagsawa river (package 1), Busay Flood control · 2024 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION
₱93.6MOn-Going · 84%
Construction of classroom building, Anislag elementary school Schools · 2024 · WIND RIVER COURT CONSTRUCTION AND DEVELOPMENT
₱9.6MOn-Going · 73%
₱115.8MOn-Going · 95%
Construction of busay-budiao dike (phase 2) Flood control · 2024 · MARCIVAN CONSTRUCTION AND SUPPLY / NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION
₱93.6MOn-Going · 90%
Construction of flood control structure (dike), Yawa river, Barangay cullat, Binitayan Flood control · 2024 · ALRO CONSTRUCTION & DEVELOPMENT CORP.
₱57.5MOn-Going · 17%Slow
₱14.2MOn-Going · 94%
Construction of salvacion-lacag-quituinan road at barangay salvacion and lacag Roads and bridges · 2024 · FIRST OMB CONSTRUCTION AND DEVELOPMENT CORP.
₱96.5MOn-Going · 79%
Construction of classroom building, Malabog national high school, Daraga albay Schools · 2024 · FIRST OMB CONSTRUCTION AND DEVELOPMENT CORP.
₱9.6MOn-Going · 74%
Improvement of brgy. burgos - brgy. mabini road Roads and bridges · 2024 · HI-TONE CONSTRUCTION & DEVELOPMENT CORP.
₱29.7MOn-Going · 99%
Construction of flood mitigation structure along barangay namantao Flood control · 2024 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION
₱36.1MOn-Going · 77%
Construction (completion) of evacuation center, Barangay alobo Buildings · 2024 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION
₱4.9MOn-Going · 97%
Construction/ maintenance of flood mitigation structures and drainage systems - construction of riverbank protection structure at gabawan Flood control · 2024 · 3RB CONSTRUCTION & SUPPLY / NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION
₱47.5MOn-Going · 90%
Construction of road, Barangay canarom to barangay san ramon, Albay (package 5) Roads and bridges · 2024 · FEDERAL AGGREGATES AND DEVELOPMENT CORP.
₱28.8MOn-Going · 1%Slow
Construction of road, Barangay canarom to barangay san ramon, Albay (package 2) Roads and bridges · 2024 · FEDERAL AGGREGATES AND DEVELOPMENT CORP.
₱28.8MOn-Going · 91%
Construction of road, Barangay canarom to barangay san ramon, Albay (package 4) Roads and bridges · 2024 · FEDERAL AGGREGATES AND DEVELOPMENT CORP.
₱28.8MOn-Going · 17%Slow
Construction of road, Barangay canarom to barangay san ramon, Albay (package 3) Roads and bridges · 2024 · FEDERAL AGGREGATES AND DEVELOPMENT CORP.
₱28.8MOn-Going · 42%Slow
Construction (completion) of dpwh albay 2nd deo building Buildings · 2023 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION
₱47.1MOn-Going · 0%Slow
₱475.3MOn-Going · 82%
Construction of namantao road, Phase 3, Brgy. namantao Roads and bridges · 2023 · A3 CONSTRUCTION & SUPPLY
₱92.8MOn-Going · 44%Slow
Construction of drainage system Flood control · 2023 · HI-TONE CONSTRUCTION & DEVELOPMENT CORP.
₱42.6MOn-Going · 40%Slow
Construction of barangay permanent evacation holding center, Brgy. tabon-tabon Buildings · 2023 · FLFB ENTERPRISES AND CONSTRUCTION SERVICES
₱13.9MOn-Going · 59%Slow

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.

Who builds here

Contractors with the most projects in Daraga since 2016.

1
HI-TONE CONSTRUCTION & DEVELOPMENT CORP.52 projects · ₱2.74B
2
NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION51 projects · ₱1.64B
3
SUNWEST, INC.35 projects · ₱3.33B
4
NUMERICAL GATE CONSTRUCTION & SUPPLY CORPORATION25 projects · ₱987.3M
5
CBC CONSTRUCTION AND SUPPLY INC.17 projects · ₱353.7M

See something wrong?

A project that looks finished on paper but not on the ground, or work that stopped. Post a photo on the Talk board, or report it to DPWH on the project's own page.

Post on Talk →