DA
Daraga: Government
Municipality in Albay, Bicol, Luzon · 54 barangays
National projects
530projects
₱22.67Bin all
228ongoing
47slow
- Flood control ₱9.59B
- Roads and bridges ₱7.63B
- Buildings ₱4.25B
- Schools ₱914.5M
- Water ₱240.1M
- Other ₱47.5M
Showing 151 to 180 of 280
Construction of by-pass and diversion roads, Daraga urban traffic eco route (duterte) project, Albay including row and dike, Albay 2nd legislative district
Flood control · 2018 · NEWBIG FOUR J CONSTRUCTION INC. / NUMERICAL GATE CONSTRUCTION & SUPPLY CORPORATION
₱125.4MCompleted · 100%
Construction of a multi-purpose building/covered court, Matnog elementary school
Schools · 2018 · DN'D CONSTRUCTION AND DEVELOPMENT
₱2.4MCompleted · 100%
Construction of a multi-purpose building, Barangay ibaungan
Buildings · 2018 · LAW-AN BUILDERS AND SUPPLY
₱1.5MCompleted · 100%
Construction of a multi-purpose building/covered court, Villahermosa elementary school
Schools · 2018 · VERZONTAL INFRASTRUCTURE CORPORATION
₱2.4MCompleted · 100%
Construction of multipurpose building, Daraga national high school (new site), Brgy. sagpon
Schools · 2018 · CBC CONSTRUCTION AND SUPPLY INC.
₱7.2MCompleted · 100%
Construction of multi-purpose building, Brgy. malabog
Buildings · 2018 · LIENEL BUILDERS AND SUPPLY
₱4.9MCompleted · 100%
Construction/maintenance of flood mitigation structures and drainage systems: rehabilitation/improvement of busay flood control dike, Busay, Sta.7+267.00-sta.8+321.80
Flood control · 2018 · HI-TONE CONSTRUCTION & DEVELOPMENT CORP.
₱96.5MCompleted · 100%
Widening-primary roads-daang maharlika (lz) including row, Albay 2nd legislative district
Roads and bridges · 2018 · HI-TONE CONSTRUCTION & DEVELOPMENT CORP.
₱154.2MCompleted · 100%
Daraga-legazpi national road jct. f. lotivio street
Roads and bridges · 2018 · SUNWEST, INC.
₱47.3MCompleted · 100%
Concreting of villahermosa fmr, Brgy. villahermosa
Roads and bridges · 2018 · PEDXING BUILDERS, INC.
₱9.5MCompleted · 100%
Construction/rehabilitation of flood mitigation facilities within major river basins and principal rivers- construction of flood control system along yawa river, Brgy. culliat-bañag section
Flood control · 2018 · NUMERICAL GATE CONSTRUCTION & SUPPLY CORPORATION
₱18.0MCompleted · 100%
Construction of a multi-purpose building (multi-purpose hall/evacuation center) in malabog elementary school
Schools · 2018 · CBC CONSTRUCTION AND SUPPLY INC.
₱2.9MCompleted · 100%
Construction of multi-purpose building, Impact elementary school, Brgy. salvacion
Schools · 2018 · VERZONTAL INFRASTRUCTURE CORPORATION
₱7.2MCompleted · 100%
Construction of by-pass and diversion roads daraga, Albay diversion road, Albay province
Roads and bridges · 2018 · B.C. CUERPO CONSTRUCTION CORPORATION / VERZONTAL INFRASTRUCTURE CORPORATION
₱217.8MCompleted · 100%
Concreting of gabawan fmr, Brgy. gabawan
Roads and bridges · 2018 · EUS CONSTRUCTION
₱13.9MCompleted · 100%
Construction of multi-purpose building brgy. balinad elementary school, Brgy. balinad
Schools · 2018 · MARCIVAN CONSTRUCTION AND SUPPLY
₱4.8MCompleted · 100%
Construction/maintenance of flood mitigation structures and drainage systems - construction of tagas-binitayan flood control system
Flood control · 2018 · PEDXING BUILDERS, INC.
₱13.2MCompleted · 100%
Construction/repair/rehabilitation of road barangay penafrancia to barangay gabawan
Roads and bridges · 2018 · MARCIVAN CONSTRUCTION AND SUPPLY
₱4.8MCompleted · 100%
Construction/rehabilitation of salvacion - budiao - matnog - mabinit road, Albay/legazpi city
Roads and bridges · 2018 · SUNWEST, INC.
₱65.5MCompleted · 100%
Construction of 3sty6cl school building pawa elementary school, Pawa, Legazpi city (9.5m x 23.00m)
Schools · 2018 · JURASSIC CONSTRUCTION & SUPPLIES
₱16.5MCompleted · 100%
Construction of 3sty6cl school building bogtong elementary school, Bogtong, Legazpi city (9.5m x 23.00m)
Schools · 2018 · MUNTOPAR BUILDERS CORP.
₱16.9MCompleted · 100%
Construction of classrooms 2sty4cl, Bañadero high school, Albay (9.5m x 23.00m)
Schools · 2018 · EMRA CONSTRUCTION AND SUPPLY SERVICES
₱9.4MCompleted · 100%
Construction of classrooms 2sty4cl, Matanag elementary school, Legazpi city (9.5m x 23.00m)
Schools · 2018 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION
₱9.4MCompleted · 100%
Construction of classrooms 2sty4cl, Bonga elementary school, Legazpi city (9.5m x 23.00m)
Schools · 2018 · NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION
₱9.3MCompleted · 100%
Construction of classrooms 2sty6cl, Bañadero es, Daraga (locsin) (9.5m x 32.00m)
Schools · 2018 · NUMERICAL GATE CONSTRUCTION & SUPPLY CORPORATION
₱12.1MCompleted · 100%
Construction of multi-purpose building, Kilicao elementary school, Brgy. kilicao
Schools · 2018 · VERZONTAL INFRASTRUCTURE CORPORATION
₱7.2MCompleted · 100%
Construction/maintenance of flood mitigation structures and drainage systems - construction of flood mitigation system along budiao-busay river
Flood control · 2018 · SUNWEST, INC.
₱45.2MCompleted · 100%
Construction/maintenance of flood mitigation structures and drainage systems - construction of flood control system along sagumayon river
Flood control · 2018 · SUNWEST, INC.
₱45.1MCompleted · 100%
Asphalt overlay along daraga-legazpi city diversion road
Roads and bridges · 2018 · SUNWEST, INC.
₱47.2MCompleted · 100%
Construction/maintenance of flood mitigation structures and drainage systems - construction of flood control system brgy. bagumbayan
Flood control · 2018 · SUNWEST, INC.
₱46.7MCompleted · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
HI-TONE CONSTRUCTION & DEVELOPMENT CORP.52 projects · ₱2.74B
2
NEXT GENERATION CONSTRUCTION AND SUPPLY CORPORATION51 projects · ₱1.64B
3
SUNWEST, INC.35 projects · ₱3.33B
4
NUMERICAL GATE CONSTRUCTION & SUPPLY CORPORATION25 projects · ₱987.3M
5
CBC CONSTRUCTION AND SUPPLY INC.17 projects · ₱353.7M