San Pablo: Government

Municipality in Isabela, Cagayan Valley, Luzon · 17 barangays

National projects

Built by DPWH in San Pablo since 2016.

125projects
₱1.85Bin all
12ongoing
0slow
  • Roads and bridges ₱1.13B
  • Flood control ₱402.3M
  • Buildings ₱153.4M
  • Schools ₱122.7M
  • Water ₱44.0M
₱2.6MOn-Going · 100%
Concreting of rodeo arena poblacion-sitio antagan fmr, Brgy. poblacion and brgy. dalena Roads and bridges · 2025 · DRAGON TWELVE BUILDERS & CONSTRUCTION SUPPLY
₱14.5MOn-Going · 100%
Construction of annanuman bridge, Barangay annanuman Roads and bridges · 2025 · RSKC CONSTRUCTION
₱19.2MOn-Going · 93%
Construction of multi-purpose building (evacuation center), Barangay caralucud Buildings · 2025 · DRAGON TWELVE BUILDERS & CONSTRUCTION SUPPLY
₱14.4MOn-Going · 100%
Construction of multi-purpose building (evacuation center), Barangay poblacion Buildings · 2025 · DRAGON TWELVE BUILDERS & CONSTRUCTION SUPPLY
₱14.4MOn-Going · 100%
Construction of multi-purpose building barangay poblacion Buildings · 2025 · DRAGON TWELVE BUILDERS & CONSTRUCTION SUPPLY
₱19.2MOn-Going · 100%
Construction of flood mitigation structure, Barangay simanu sur Flood control · 2025 · DRAGON TWELVE BUILDERS & CONSTRUCTION SUPPLY
₱9.6MOn-Going · 100%
Concreting of sitio magamian - cabannungan, Brgy. limbauan fmr, Brgy. limbauan Roads and bridges · 2024 · DRAGON TWELVE BUILDERS & CONSTRUCTION SUPPLY
₱14.9MOn-Going · 64%
Widening of permanent bridges - sn. pablo bridge (b01137lz) along daang maharlika Roads and bridges · 2021 · EGB CONSTRUCTION CORPORATION
₱131.0MOn-Going · 81%

Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.

Who builds here

Contractors with the most projects in San Pablo since 2016.

1
DRAGON TWELVE BUILDERS & CONSTRUCTION SUPPLY53 projects · ₱619.4M
2
EGB CONSTRUCTION CORPORATION22 projects · ₱550.0M
3
KWA CONSTRUCTION14 projects · ₱56.8M
4
FRAGERR CONSTRUCTION5 projects · ₱30.2M
5
RSKC CONSTRUCTION3 projects · ₱28.9M