BA
Basilisa: Government
Municipality in Dinagat Islands, Caraga, Mindanao · 27 barangays
National projects
177projects
₱2.37Bin all
19ongoing
1slow
- Roads and bridges ₱1.54B
- Buildings ₱442.3M
- Schools ₱203.3M
- Flood control ₱141.2M
- Other ₱31.9M
- Water ₱9.5M
Showing 61 to 90 of 153
Improvement dinagat-loreto road - k0039+474-k0039+889, K0039+911-k0040+381, K0040+540-k0040+830
Roads and bridges · 2022 · RJB CONSTRUCTION & SUPPLY
₱14.7MCompleted · 100%
Construction of bridge along ferdinand-melgar road
Roads and bridges · 2022 · JMT CONSTRUCTION CORPORATION
₱62.1MCompleted · 100%
Construction of multi-purpose building, Barangay melgar
Buildings · 2022 · RJB CONSTRUCTION & SUPPLY
₱4.9MCompleted · 100%
Improvement dinagat-loreto road-k0027+300-k0027+418, K0027+432-k0027+464, K0027+927-k0028+063, Dinagat to loreto road, Basilisa section
Roads and bridges · 2022 · RJB CONSTRUCTION & SUPPLY
₱5.4MCompleted · 100%
Construction of flood control structure, Barangay tag-abaca
Flood control · 2022 · ALGAMON CONSTRUCTION CORPORATION
₱29.7MCompleted · 100%
Rehabilitation/reconstruction of roads with slips, Slope collapse and landslide along dinagat - loreto road - k0024+000-k0024 +097
Roads and bridges · 2022 · CARTESIAN BUILDERS CORPORATION
₱39.5MCompleted · 100%
Construction of multi-purpose building, Purok-4, Doña helene
Buildings · 2022 · HJV CONSTRUCTION
₱4.9MCompleted · 100%
Contruction of multi-purpose building, Barangay roxas
Buildings · 2022 · TREBNYL CONSTRUCTION
₱4.9MCompleted · 100%
Construction of multi-purpose building, Barangay roma
Buildings · 2022 · TREBNYL CONSTRUCTION
₱4.9MCompleted · 100%
Construction/improvement of access roads leading to declared tourism destinations diegas-ritaglenda-benglen road leading to gaas inlet
Roads and bridges · 2022 · WINDFALL CONSTRUCTION
₱4.9MCompleted · 100%
Construction/improvement of access roads leading to declared tourism destinations municipal coastal road from ferdinand-melgar leading to the nearest point to lake bababu, Basilisa (rizal)
Roads and bridges · 2022 · TREBNYL CONSTRUCTION
₱4.9MCompleted · 100%
Concreting of barangay road, Brgy. nazareth
Roads and bridges · 2021 · RJB CONSTRUCTION & SUPPLY
₱4.9MCompleted · 100%
Concreting of barangay road, Brgy. sering
Roads and bridges · 2021 · RJB CONSTRUCTION & SUPPLY
₱4.9MCompleted · 100%
Concreting of p-2 to p-1, Brgy. villa pantinople fmr phase ii, Brgy. villa pantinople
Roads and bridges · 2021 · CARTESIAN BUILDERS CORPORATION
₱24.8MCompleted · 100%
Reconstruction to concrete pavement-diegas-rita glenda road leading to gaas inlet
Roads and bridges · 2020 · CARTESIAN BUILDERS CORPORATION
₱28.9MCompleted · 100%
Construction (completion) of multi-purpose building, Barangay sta. monica
Buildings · 2021 · R.F. VARQUEZ CONSTRUCTION
₱3.0MCompleted · 100%
Construction (completion) of multi-purpose building (building a) barangay navarro
Buildings · 2021 · RJB CONSTRUCTION & SUPPLY
₱2.0MCompleted · 100%
Construction (completion) of multi-purpose building, Barangay geotina
Buildings · 2021 · HEAVY JOHN ENGINEERING CONSULTANCY
₱3.0MCompleted · 100%
Construction of roads (phase-i), Brgy. villa pantinople-sombrado
Roads and bridges · 2021 · RONWOOD CORPORATION (DOING BUSINESS UNDER THE NAME
₱24.7MCompleted · 100%
Construction (completion) of multi-purpose building (building b), Barangay villa ecleo
Buildings · 2021 · GEVANS CONSTRUCTION AND SUPPLY
₱4.0MCompleted · 100%
Construction of panaad farmers multi-purpose building, Barangay villa pantinople
Buildings · 2021 · BIAO BUILDERS
₱4.9MCompleted · 100%
Construction/improvement of access roads leading to declared tourism destinations, Municipal coastal road from ferdinand-melgar leading to the nearest point to lake bababu, Basilisa (rizal)
Roads and bridges · 2021 · BIAO BUILDERS
₱2.9MCompleted · 100%
Construction (completion) of multi-purpose building (building b), Barangay navarro
Buildings · 2021 · HJV CONSTRUCTION
₱3.0MCompleted · 100%
Construction of multi-purpose building (barangay hall), Barangay imee
Buildings · 2021 · HJV CONSTRUCTION
₱3.0MCompleted · 100%
Construction (completion) of multi-purpose building, Barangay catadman
Buildings · 2021 · TREBNYL CONSTRUCTION
₱3.0MCompleted · 100%
Rehabilitation/reconstruction of national roads with slips, Slope collapse, And landslide along dinagat-loreto road - k0029+088 - k0029+288, K0037+034-k0037+290, K0037+700-k0037+760, K0040+088-k0040+929, K0043+437-k0043+544, K0045+128-k0045+144
Roads and bridges · 2021 · CARTESIAN BUILDERS CORPORATION
₱72.6MCompleted · 100%
Construction of flood control structure protecting doña helene br. ii
Flood control · 2021 · CARTESIAN BUILDERS CORPORATION
₱4.9MCompleted · 100%
Construction (completion) of multi-purpose building, Barangay benglen
Buildings · 2021 · TREBNYL CONSTRUCTION
₱3.0MCompleted · 100%
Construction (completion) of multi-purpose building (building a), Barangay villa ecleo
Buildings · 2021 · ALGAMON CONSTRUCTION CORPORATION
₱2.0MCompleted · 100%
Construction (completion) of multi-purpose building, Barangay rita glenda
Buildings · 2021 · ALGAMON CONSTRUCTION CORPORATION
₱3.0MCompleted · 100%
Source: DPWH Transparency Portal. Each project links to its page there, with the contract and the bidders.
The red "Slow" tag is a plain fact, not a charge: the project started more than two years ago and is under 60% done. We say what DPWH reports and link to it.
Who builds here
1
HEAVY JOHN ENGINEERING CONSULTANCY19 projects · ₱95.5M
2
CARTESIAN BUILDERS CORPORATION12 projects · ₱409.6M
3
RADIAN CONSTRUCTION AND SUPPLY12 projects · ₱77.6M
4
GEVANS CONSTRUCTION AND SUPPLY10 projects · ₱30.8M
5
ALGAMON CONSTRUCTION CORPORATION7 projects · ₱67.9M